NPDES FLR05I250 · Clean Water Act
ADVANCED DRAINAGE SYSTEM, Sebring, FL: NPDES FLR05I250 discharge permit, effluent exceedances, inspections, penalties
ADVANCED DRAINAGE SYSTEM, Sebring, Florida: General permit coverage FLR05I250, held by Advance Drainage System, Inc; Industrial stormwater; Administratively continued; issued August 17, 2018, term to August 16, 2023, by Florida Department of Environmental Protection; Plastics Pipe and Pipe Fitting Manufacturing.
- July 27, 2023: WW Storm Water Non-Construction - Failure to Maintain Records (ST6).
- July 27, 2023: WW Storm Water Non-Construction - Failure to properly install/implement BMPs (ST6).
- July 27, 2023: WW Storm Water Non-Construction - Failure to properly operate and maintain BMPs (ST6).
- July 27, 2023: WW Storm Water Non-Construction - Failure to develop any or adequate SWPPP/SWMP (ST6).
- July 27, 2023: WW Storm Water Non-Construction - Failure to Implement SWPPP/SWMP (ST6).
- July 27, 2023: WW Storm Water Non-Construction - Failure to Monitor (ST6).
- July 27, 2023: WW Storm Water Non-Construction - Failure to Conduct Inspections (ST6).
- September 10, 2019: WW Storm Water Non-Construction - Failure to develop any or adequate SWPPP/SWMP (ST6).
- September 10, 2019: WW Storm Water Non-Construction - Failure to Conduct Inspections (ST6).
- September 10, 2019: WW Storm Water Non-Construction - Failure to properly install/implement BMPs (ST6).
- September 10, 2019: WW Storm Water Non-Construction - Failure to Monitor (ST6).
Florida holds 3,868 Industrial stormwater coverages of this permit type in EPA’s file; 1,971 were issued before FLR05I250.
Coverages issued nearest FLR05I250
- 2018-08-09: DANDEE FOODS, Jacksonville: FLRNEE669, held by M E Thompson Inc
- 2018-08-13: ATLAS SIGN INDUSTRIES, Riviera Beach: FLR05I248, held by Atlas Signs
- 2018-08-13: C & D PRINTING CO, St Petersburg: FLRNEF550, held by Metempo Investment
- 2018-08-16: BONITA BAY MARINA, Bonita Springs: FLR05H541, held by Bonita Boat Harbor LLC
- 2018-08-17: ENVIROCYCLE, Fort Lauderdale: FLR05H566, held by Envirocycle, Inc.
- 2018-08-20: GLADES WWTF, Port St Lucie: FLR05G776, held by Port St. Lucie, City of
- 2018-08-23: ROYALE PALM YACHT BASIN, INC, Dania: FLR05H061, held by Royale Palm Yacht Basin, Inc.
- 2018-08-23: HB FULLER CONSTRUCTION PRODUCTS, INC., Gainesville: FLR05I249, held by HB Fuller Construction Products, Inc.
- 2018-08-24: JACKSONVILLE RETAIL DISTRIBUTION CENTER, Jacksonville: FLR05H537, held by C & S Wholesale Services, Inc
- 2018-08-24: HUDSON TECHNOLOGIES, Ormond Beach: FLRNEE257, held by Hudson Tool & Die Coompany, Inc
ADVANCED DRAINAGE SYSTEM among its neighbors
23 discharge permits are in the Lower Arbuckle Creek subwatershed (HUC 030901011802); FLR05I250 is one. Its county: 86, 0 major; FLR05I250 is minor permit.
Other permits in the Lower Arbuckle Creek subwatershed (HUC 030901011802)
- ALPHA GENERAL SERVICES INC., Sebring: FLRNEF827, minor, term to 2027-06-12
- DIVERSIFIED CPC INTERNATIONAL, Sebring: FLR05J064, minor, term to 2028-08-03
- E-STONE USA CORPORATION, Sebring: FLR05G996, minor, term to 2025-04-27
- FUNDER BY GENESIS PRODUCTS, Sebring: FLRNEG085, minor, term to 2030-08-27
- GENPAK, Sebring: FLR05G107, minor, term to 2018-08-29
- GULF COAST SUPPLY & MANUFACTURING LLC, Sebring: FLR05I263, minor, term to 2023-09-16
- HIGHLANDS CO LANDFILL, Sebring: FLR20HS83, minor, term to 2029-11-27
- HUCKE MANUFACTURING INC, Sebring: FLR10XS78, minor, term to 2030-06-12
- JIMS AUTO SALVAGE INC, Sebring: FLR05G191, minor, term to 2026-03-31
- MID-STATE PRECAST, Sebring: FLR05J516, minor, term to 2031-04-18
What stands out
- Its term runs 4 years and 364 days, August 17, 2018 to August 16, 2023; the term ended 1,155 days before EPA's file was loaded on October 14, 2026, and the file lists the permit as administratively continued.
- Its newest dated event on file is a single-event violation on July 27, 2023, 1,175 days before EPA's file was loaded.
- No dated event in the 365 days to October 14, 2026.
- EPA's file dates 11 events for it, from 2019 to 2023; the busiest year is 2023 with 7.
- It is one of 23,564 discharge permits on the register in Florida; 3,868 of them (16%) are in its program, Industrial stormwater, and it is a minor discharger.
Identity
| Facility | ADVANCED DRAINAGE SYSTEM |
|---|---|
| Permittee | Advance Drainage System, Inc |
| NPDES ID | FLR05I250 |
| Status | Administratively continued |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Industrial stormwater |
| Issued | August 17, 2018 |
| Expires | August 16, 2023 |
| Agency | Florida Department of Environmental Protection |
| Address | Sebring, FL 33870 |
| Receiving water impaired | 303(D) Listed |
| Subwatershed | Lower Arbuckle Creek (HUC 030901011802) |
| NAICS | 326122 – Plastics Pipe and Pipe Fitting Manufacturing |
| SIC | 3084 – Plastics Pipe |
NPDES FLR05I250: effluent limits and exceedances
ADVANCED DRAINAGE SYSTEM (NPDES FLR05I250): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES FLR05I250: no pollutant row on file.
NPDES FLR05I250: inspections, violations and enforcement
NPDES FLR05I250: 11 single-event violations
| Date | What EPA recorded | Agency |
|---|---|---|
| July 27, 2023 | WW Storm Water Non-Construction - Failure to Maintain Records | ST6 |
| July 27, 2023 | WW Storm Water Non-Construction - Failure to properly install/implement BMPs | ST6 |
| July 27, 2023 | WW Storm Water Non-Construction - Failure to properly operate and maintain BMPs | ST6 |
| July 27, 2023 | WW Storm Water Non-Construction - Failure to develop any or adequate SWPPP/SWMP | ST6 |
| July 27, 2023 | WW Storm Water Non-Construction - Failure to Implement SWPPP/SWMP | ST6 |
| July 27, 2023 | WW Storm Water Non-Construction - Failure to Monitor | ST6 |
| July 27, 2023 | WW Storm Water Non-Construction - Failure to Conduct Inspections | ST6 |
| September 10, 2019 | WW Storm Water Non-Construction - Failure to develop any or adequate SWPPP/SWMP | ST6 |
| September 10, 2019 | WW Storm Water Non-Construction - Failure to Conduct Inspections | ST6 |
| September 10, 2019 | WW Storm Water Non-Construction - Failure to properly install/implement BMPs | ST6 |
| September 10, 2019 | WW Storm Water Non-Construction - Failure to Monitor | ST6 |
NPDES FLR05I250 (ADVANCED DRAINAGE SYSTEM): no inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES FLR05I250
NPDES FLR05I250: one email when its EPA record changes — $99/month.
Permits near NPDES FLR05I250
NPDES FLR05I250: 0 pollutant rows, 11 dated events; ICIS-NPDES download, loaded October 14, 2026.