NPDES GAR25448D · Clean Water Act
BIG TAZEWELL SUBSTATION, Buena Vista, GA: NPDES GAR25448D discharge permit, effluent exceedances, inspections, penalties
BIG TAZEWELL SUBSTATION, Buena Vista, Georgia: General permit coverage GAR25448D, held by Georgia Power Company; Construction stormwater; Effective; issued August 1, 2023, term to July 31, 2028.
- August 11, 2026: Notice of Noncompliance Issued (State).
- August 5, 2026: Evaluation (S).
- April 29, 2026: Evaluation (S).
Georgia holds 40,604 Construction stormwater coverages of this permit type in EPA’s file; 31,933 were issued before GAR25448D. Georgia Power Company holds 99 permits in Georgia.
Other permits held by Georgia Power Company
- MCDONOUGH-ATKINSON COMBINED-CYCLE FACILITY, Smyrna: GA0001431, issued 2016-04-20
- GEORGIA POWER COMPANY (PLANT BOWEN), Cartersville: GA0001449, issued 2007-11-09
- GEORGIA POWER COMPANY (PLANT HAMMOND), Rome: GA0001457, issued 2024-03-22
- GEORGIA POWER COMPANY (PLANT MITCHELL), Albany: GA0001465, issued 2017-08-18
- GEORGIA POWER COMPANY (PLANT YATES), Newnan: GA0001473, issued 2019-03-01
- GEORGIA POWER COMPANY (GOAT ROCK HYDROELECTRIC PLANT), Fortson: GA0001503, issued 2018-09-28
- GEORGIA POWER COMPANY (MORGAN FALLS HYDROELECTRIC PLANT), Dunwoody: GA0001511, issued 2017-06-26
- GEORGIA POWER COMPANY (OLIVER DAM HYDROELECTRIC PLANT), Columbus: GA0001520, issued 2018-09-28
- GEORGIA POWER COMPANY (NORTH HIGHLANDS HYDROELECTRIC PLANT), Columbus: GA0001538, issued 2018-09-28
- GEORGIA POWER COMPANY (FLINT RIVER HYDROELECTRIC PLANT), Albany: GA0001546, issued 2018-09-28
Coverages issued nearest GAR25448D
- 2023-08-01: RICHLAND CONNECTOR SANITARY SEWERAGE SYSTEM IMPROVEMENTS, Greensboro: GAR254487, held by Adam Shaifer
- 2023-08-01: CLERMONT JUNCTION TO GAINESVILLE #1, Gainesville: GAR254488, held by Georgia Power Company
- 2023-08-01: US 17/SR 404 SPUR BRIDGE, Savannah: GAR254489, held by GDOT
- 2023-08-01: CALIFF PIPELINE, Macon: GAR25448A, held by Kamin LLC.
- 2023-08-01: SNAPFINGER CREEK ADVANCED WASTEWATER TREATMENT FACILITY, Ellenwood: GAR25448C, held by DeKalb County Watershed Dept. PM: Tidarat Strickland
- 2023-08-01: HILLS BRIDGE SUBSTATION, Hampton: GAR25448E, held by Georgia Power Company
- 2023-08-01: PI 0013763 OCONEE COUNTY, INTERCHANGE ON US 29 / SR 316 / SR 8 AT DIALS MILL ROA, Bogart: GAR25448F, held by Georgia Department of Transportation
- 2023-08-01: CENTRAL COWETA INDUSTRIAL PARKWAY EXT, Senoia: GAR254490, held by Central Coweta Industrial LLC
- 2023-08-01: HOLLZ PARKWAY EXTENSION, Newnan: GAR254491, held by Coweta Hollz Ventures LLC
- 2023-08-01: BEECHTREE CREEK P79476, Tucker: GAR254492, held by Georgia Transmission Corp.
BIG TAZEWELL SUBSTATION among its neighbors
1 discharge permits are in the Gin Creek subwatershed (HUC 031300060203); GAR25448D is one.
What stands out
- Its term runs 4 years and 365 days, August 1, 2023 to July 31, 2028.
- Its newest dated event on file is an informal enforcement action on August 11, 2026, 35 days before EPA's file was loaded.
- In the 365 days to September 15, 2026, it was dated 2 inspections, 1 informal enforcement action.
- EPA's file dates 3 events for it, all in 2026.
- It is one of 45,725 discharge permits on the register in Georgia; 40,604 of them (89%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | BIG TAZEWELL SUBSTATION |
|---|---|
| Permittee | Georgia Power Company |
| NPDES ID | GAR25448D |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | August 1, 2023 |
| Expires | July 31, 2028 |
| Address | Buena Vista, GA 31803 |
| Subwatershed | Gin Creek (HUC 031300060203) |
NPDES GAR25448D: effluent limits and exceedances
BIG TAZEWELL SUBSTATION (NPDES GAR25448D): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES GAR25448D: no pollutant row on file.
NPDES GAR25448D: inspections, violations and enforcement
NPDES GAR25448D: 2 inspections
| Date | What EPA recorded | Agency |
|---|---|---|
| August 5, 2026 | Evaluation | S |
| April 29, 2026 | Evaluation | S |
NPDES GAR25448D: 1 informal enforcement action
| Date | What EPA recorded | Agency |
|---|---|---|
| August 11, 2026 | Notice of Noncompliance Issued | State |
NPDES GAR25448D (BIG TAZEWELL SUBSTATION): no single-event violation and formal enforcement action on file.
Watch NPDES GAR25448D
NPDES GAR25448D: one email when its EPA record changes — $99/month.
Permits near NPDES GAR25448D
NPDES GAR25448D: 0 pollutant rows, 3 dated events; ICIS-NPDES download, loaded September 15, 2026.