NPDES SDR10K520 · Clean Water Act
2021 DOUGLAS/WASHINGTON STREETS PROJECT, Elk Point, SD: NPDES SDR10K520 discharge permit, effluent exceedances, inspections, penalties
2021 DOUGLAS/WASHINGTON STREETS PROJECT, Elk Point, South Dakota: General permit coverage SDR10K520, held by 2021 Douglas/Washington Streets Project; Construction stormwater; Administratively continued; issued March 15, 2021, term to March 31, 2023, by State; discharges to natural drainageways.
South Dakota holds 1,358 Construction stormwater coverages of this permit type in EPA’s file; 179 were issued before SDR10K520.
Coverages issued nearest SDR10K520
- 2021-02-15: HOLIDAY STATION STORES, Rapid City: SDR10K139, held by Holiday Station Stores
- 2021-02-16: SANITARY SEWER SYSTEM IMPROVEMENTS, Sioux Falls: SDR10K140, held by Sanitary Sewer System Improvements
- 2021-03-03: BIA ROUTE 7 TO US HWY 83 IMPROVEMENT PROJECT, PH1, Rosebud: SDR10I01K, held by Rosebud Sioux Tribe Map-21 Program
- 2021-03-03: DOVE RIDGE ADDITION, Sioux Falls: SDR10K147, held by Dove Ridge Addition
- 2021-03-10: GRASSLANDS ADDITION - PHASE 3, Sioux Falls: SDR10K166, held by Grasslands Addition - Phase 3
- 2021-03-22: BOX ELDER BATCH PLANT SITE GRADING, Box Elder: SDR10K203, held by Box Elder Batch Plant Site Grading
- 2021-03-29: PRAIRIE HAVEN SUBDIVISION - PHASE III, Piedmont: SDR10K548, held by Prairie Haven Subdivision - Phase III
- 2021-04-07: BRANDON 90 PLAZA, Brandon: SDR10K222, held by Brandon 90 Plaza
- 2021-04-08: HUSETS SPEEDWAY CAMPGROUND, Brandon: SDR10K216, held by Husets Speedway Campground
- 2021-04-09: TENCATE ADDITION, Sioux Falls: SDR10K186, held by Tencate Addition
2021 DOUGLAS/WASHINGTON STREETS PROJECT among its neighbors
19 discharge permits are in the Walnut Creek-Missouri River subwatershed (HUC 101701011504); SDR10K520 is one.
Other permits in the Walnut Creek-Missouri River subwatershed (HUC 101701011504)
- CLAY RURAL WATER SYSTEM - WYNSTONE, North Sioux City: SD0028011, minor, term to 2018-03-31
- DAKOTA DUNES (WTP), Dakota Dunes: SDG860014, minor, term to 2021-09-30
- DAKOTA DUNES SUBSTATION EXPANSION, North Sioux City: SDR10P5TD, minor, term to 2028-10-31
- FLOOD PROPERTY GRADING - 93-85 NORTHSHORE DRIVE, North Sioux City: SDR10P5VH, minor, term to 2028-10-31
- MCCOOK LAKE CANAL, North Sioux City: SDR10K811, minor, term to 2023-03-31
- MCCOOK LAKE REHABILITATION, North Sioux City: SDR10P5HE, minor, term to 2028-10-31
- NORTH SIOUX CITY, CITY OF, North Sioux City: SD0020567, minor, term to 2024-09-30
- NORTHSHORE DRIVE RECONSTRUCTION, North Sioux City: SDR10P5U8, minor, term to 2028-10-31
- PCN 065L, Elk Point: SDR10P425
- PCN 08W4, North Sioux City: SDR10P5MC, minor, term to 2028-10-31
Identity
| Facility | 2021 DOUGLAS/WASHINGTON STREETS PROJECT |
|---|---|
| Permittee | 2021 Douglas/Washington Streets Project |
| NPDES ID | SDR10K520 |
| Status | Administratively continued |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | March 15, 2021 |
| Expires | March 31, 2023 |
| Agency | State |
| Address | Elk Point, SD 57025 |
| Receiving water | natural drainageways |
| Subwatershed | Walnut Creek-Missouri River (HUC 101701011504) |
NPDES SDR10K520: effluent limits and exceedances
2021 DOUGLAS/WASHINGTON STREETS PROJECT (NPDES SDR10K520): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES SDR10K520: no pollutant row on file.
NPDES SDR10K520: inspections, violations and enforcement
NPDES SDR10K520 (2021 DOUGLAS/WASHINGTON STREETS PROJECT): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES SDR10K520
NPDES SDR10K520: one email when its EPA record changes — $99/month.
Permits near NPDES SDR10K520
NPDES SDR10K520: 0 pollutant rows, 0 dated events; ICIS-NPDES download, loaded September 15, 2026.