Clean Water Act discharge permit · NPDES TXR1518RG
CONCRETE BATCH PLANT SUPPORTING MEADOWS PH 1 4388P, Ponder, TX: NPDES TXR1518RG discharge permit, effluent exceedances, inspections, penalties
- EffectivePermit status
- MinorDischarger class
- 0Pollutants under a numeric limit
- 0Pollutants with an effluent exceedance
- 0Inspections on file
- 0Formal enforcement actions
CONCRETE BATCH PLANT SUPPORTING MEADOWS PH 1 4388P, held by RPM xConstruction, LLC, holds NPDES permit TXR1518RG, which discharges to South Hickory Creek. EPA’s file records it issued June 21, 2024 and expiring March 4, 2028. The status and dates are as EPA’s permit file stood when Velarion loaded it (September 15, 2026); EPA’s free Detailed Facility Report on ECHO carries the permit’s current standing.
What the register holds for CONCRETE BATCH PLANT SUPPORTING MEADOWS PH 1 4388P: its NPDES ID, its permit type and status, its dates, its address in Ponder, Texas, its receiving water. EPA’s effluent violation file and its single-event violation file hold no violation for NPDES TXR1518RG.
What stands out
- Its term runs 3 years and 257 days, June 21, 2024 to March 4, 2028.
- No dated event in the 365 days to September 15, 2026.
- It is one of 39,714 discharge permits on the register in Texas; 23,986 of them (60%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility as filed | CONCRETE BATCH PLANT SUPPORTING MEADOWS PH 1 4388P |
|---|---|
| Permittee as filed | RPM xConstruction, LLC |
| NPDES ID | TXR1518RG |
| Permit status | Effective |
| Permit type | Coverage under a general permit |
| Discharger class | Minor discharger |
| Facility type | Not a publicly owned treatment works |
| Program | Construction stormwater |
| Issued | June 21, 2024 |
| Expiration date | March 4, 2028 |
| Address | Ponder, TX 76259 |
| Receiving water | SOUTH HICKORY CREEK |
| Subwatershed | South Hickory Creek (HUC 120301030802) |
Cited to the EPA ICIS-NPDES permit file (ECHO download).
Effluent limits and exceedances
- 0Pollutants on file
- 0Under a numeric limit
- 0With a violation of any kind
- 0With an effluent exceedance
EPA’s limits and effluent violation files hold no pollutant row for NPDES TXR1518RG.
Cited to the EPA ICIS-NPDES limits and effluent violations files (ECHO download); up to 60 rows shown, most exceedances first.
Inspections, violations and enforcement
- 0Single-event violations
EPA’s single-event violation file, as loaded, holds no violation for NPDES TXR1518RG.
Inspections
EPA’s inspection file holds no inspection for NPDES TXR1518RG.
Formal enforcement and penalties
0 formal actions, 0 of them with a penalty assessed. Federal and state penalties are separate figures from separate authorities and are shown as each was filed, never added together.
Informal enforcement
EPA’s informal enforcement file holds no action for NPDES TXR1518RG.
Cited to the EPA ICIS-NPDES violation, inspection and enforcement files (ECHO download); up to 50 rows of each shown, newest first.
Watch this permit
One permit holder, $99/month. Watch the register for one permit holder and the places and receiving waters tied to its permits. Choose “One permit holder” and enter this permit’s NPDES ID, TXR1518RG.
Start the watch
- One permit holder — $99/month
- One watershed — $2,990/year
- One state — $4,990/year
- The whole register — $18,000/year
How we handle your data → Privacy
EPA publishes a free Detailed Facility Report for every permit on ECHO: its compliance status quarter by quarter, its inspections, and its enforcement actions and penalties. EPA also sends free notices of new inspections and enforcement actions through ECHO Notify; enter NPDES ID TXR1518RG there.
CONCRETE BATCH PLANT SUPPORTING MEADOWS PH 1 4388P, Ponder, Texas: Coverage under a general permit TXR1518RG, held by RPM xConstruction, LLC; Construction stormwater; Effective; issued June 21, 2024, term to March 4, 2028; discharges to SOUTH HICKORY CREEK.
Texas holds 23,986 Construction stormwater coverages of this permit type in EPA’s file; 7,831 were issued before TXR1518RG. RPM xConstruction, LLC holds 169 permits in Texas.
Other permits held by RPM xConstruction, LLC
- HARLINGEN DATA CENTER BP, Harlingen: TXG114193, issued 2026-07-31
- HUNTER RANCH, Denton: TXR1502SC, issued 2024-09-11
- THE VINES AT LEGACY PHASES 1 AND 2, Celina: TXR1503QB, issued 2024-02-27
- VALLEY BROOKE, Mesquite: TXR1506SC, issued 2024-09-11
- CONCRETE BATCH PLANT SUPPORTING LAPRELLE, Haslet: TXR1506UY, issued 2025-06-16
- CHISHOLM TRAIL PARKWAY, Joshua: TXR1506VZ, issued 2025-09-26
- BRIDGEWATER PHASE 2A, Midlothian: TXR1507SC, issued 2024-09-11
- CONCRETE BATCH PLANT SUPPORTING 4442P MEADOW LAKES, Fort Worth: TXR1507UY, issued 2025-06-16
- PROJECT SPITFIRE, Terrell: TXR1507UZ, issued 2025-06-19
- CONCRETE BATCH PLANT SUPPORTING RIVERSTONE ESTATES, Anna: TXR1507ZC, issued 2026-08-07
Coverages issued nearest TXR1518RG
- 2024-06-21: PAVING OPERATIONS FOR MEADOW RIDGE ESTATES, Josephine: TXR1511RG, held by Chris Harp Construction Limited Liability Company
- 2024-06-21: FULSHEAR LAKES LAKESIDE PARK - HOME BUILDING, Fulshear: TXR1514RG, held by Perry Homes, LLC
- 2024-06-21: PARK TRAILS, Forney: TXR1515RG, held by Grand Texas Homes, Inc.
- 2024-06-21: CENTER AT PALM VALLEY SITE DEVELOPMENT IMPROVEMENTS, Round Rock: TXR1516RG, held by Gulf Rc Ventures LLC
- 2024-06-21: SWIFTEX TO SIM GIDEON OVERHAUL PROJECT, Bastrop: TXR1517RG, held by LCRA Transmission Services Corporation
- 2024-06-21: CONCRETE BATCH PLANT SUPPORTING MCKINNEY CRUSHER, Mckinney: TXR1519RG, held by RPM xConstruction, LLC
- 2024-06-21: HEATH HORIZON MOB, Heath: TXR1521RG, held by Triton Gc, LLC
- 2024-06-21: WATER & WASTE WATER IMPROVEMENTS FOR WINDING TRAIL WEST, Austin: TXR1524RG, held by Wpm Construction Services, Inc.
- 2024-06-21: EAST BRAKER LANE MULTI-FAMILY PROJECT, Austin: TXR1527RG, held by Shreve Land Constructors, LLC
- 2024-06-21: THE RANCH AT CALITERRA, Dripping Springs: TXR1530RG, held by DNT Construction, LLC
CONCRETE BATCH PLANT SUPPORTING MEADOWS PH 1 4388P among its neighbors
41 discharge permits are in the South Hickory Creek subwatershed (HUC 120301030802); TXR1518RG is one. Its county: 1,238, 16 major; TXR1518RG is minor permit.
Other permits in the South Hickory Creek subwatershed (HUC 120301030802)
- CASTLEROCK COMMUNITIES- TABOR RANCH, Ponder: TXR1542XX, minor, term to 2028-03-04
- CBP NO 4, Ponder: TXG113846, minor, term to 2026-11-06
- CBP NO 4, Ponder: TXR1579TP, minor, term to 2028-03-04
- CHURCHILL, Denton: TXR1552VZ, minor, term to 2028-03-04
- CLEARWATER RANCH - LAND DEVELOPMENT, Krum: TXR1588UX, minor, term to 2028-03-04
- CLEARWATER RANCH - OFFSITE, Krum: TXR1505UI, minor, term to 2028-03-04
- CLEARWATER RANCH OFFSITE, Krum: TXR1515WU, minor, term to 2028-03-04
- CLEARWATER RANCH OFFSITE, Krum: TXR1545YL, minor, term to 2028-03-04
- CLEARWATER RANCH PHS 2, Denton: TXR1544YM, minor, term to 2028-03-04
- CLEARWATER RANCH PHS 2, Denton: TXR1545YM, minor, term to 2028-03-04
Nearby on the register
- Discharge permits in Ponder
- Every permit record in Ponder, A to Z
- Discharge permits in Texas
- Every permit record in Texas, A to Z
Figures from EPA’s ICIS-NPDES download, loaded September 15, 2026.
What this page shows
CONCRETE BATCH PLANT SUPPORTING MEADOWS PH 1 4388P is one of 1,007 storm water construction permits on EPA's NPDES register in Denton County. It is also one of 41 NPDES permits in the South Hickory Creek subwatershed, and 19.6% of the 1,007 storm water construction permits in Denton County have an earlier issue date than this permit.