NPDES TXR1594VT · Clean Water Act
EAST INDUSTRIAL PARKWAY PHASE 2, New Caney, TX: NPDES TXR1594VT discharge permit, effluent exceedances, inspections, penalties
EAST INDUSTRIAL PARKWAY PHASE 2, New Caney, Texas: General permit coverage TXR1594VT, held by Principal Services, Ltd.; Construction stormwater; Effective; issued September 8, 2025, term to March 4, 2028; discharges to WHITE OAK CREEK.
Texas holds 23,986 Construction stormwater coverages of this permit type in EPA’s file; 15,682 were issued before TXR1594VT. Principal Services, Ltd. holds 76 permits in Texas.
Other permits held by Principal Services, Ltd.
- JUBILEE SECTIONS 2 9 & BETKA ROAD STREET DED SECTION 1, Hockley: TXR1502QB, issued 2024-02-27
- PROSPER AT FIREFLY SECTION 2, Splendora: TXR1502YS, issued 2026-06-29
- CIELO SECTIONS 5 & 6 AND PH 2A, Conroe: TXR1507TL, issued 2025-01-29
- SAMARA SECTION 13, League City: TXR1509WX, issued 2026-01-06
- SUNTERRA SECTION 59, Katy: TXR1514PZ, issued 2024-02-20
- MILLER WILSON ROAD, Crosby: TXR1514QH, issued 2024-03-19
- WOODHAVEN, Magnolia: TXR1515XS, issued 2026-03-23
- WYNSERRA, Iowa Colony: TXR1515YZ, issued 2026-07-28
- SUNTERRA SECTIONS 65 & 66, Katy: TXR1516QH, issued 2024-03-19
- CHAMBERS CREEK SECTION 11, Willis: TXR1516UV, issued 2025-06-05
Coverages issued nearest TXR1594VT
- 2025-09-08: MADRONE CANYON HOMEBUILDING, Austin: TXR1527VU, held by Czam Holdings LLC
- 2025-09-08: PEDEN CROSSING, Fort Worth: TXR1529VU, held by Adg-Osw Services LLC
- 2025-09-08: ALEDO ROAD INFRASTRUCTURE, Fort Worth: TXR1590VT, held by Acadia Services, LLC
- 2025-09-08: BLOSSOM RANCH - UNIT 1B, San Antonio: TXR1591VT, held by DNT Construction, LLC
- 2025-09-08: BRE PHASE 2 COLLECTOR, San Antonio: TXR1593VT, held by DNT Construction, LLC
- 2025-09-08: 10021 KENDALL CYN, San Antonio: TXR1595VT, held by Shuvra Kanta Paladhi
- 2025-09-08: H-E-B SAN MARCOS 03, San Marcos: TXR1596VT, held by DNT Construction, LLC
- 2025-09-08: BRIDGELAND CREEKLAND VILLAGE SECTION 17, Cypress: TXR1598VT, held by Principal Services, Ltd.
- 2025-09-09: SUNSET OAKS SECTION VI PHASE 1A, Maxwell: TXR1530VU, held by KB Home Lone Star Inc.
- 2025-09-09: URBAN AIR - DENTON, Denton: TXR1531VU, held by Hba Design Build, LLC
EAST INDUSTRIAL PARKWAY PHASE 2 among its neighbors
61 discharge permits are in the Dry Creek-Caney Creek subwatershed (HUC 120401030105); TXR1594VT is one. Its county: 1,439, 16 major; TXR1594VT is minor permit.
Other permits in the Dry Creek-Caney Creek subwatershed (HUC 120401030105)
- 59 FRONTAGE ROAD TO SERVE TAVOLA DEVELOPMENT, New Caney: TXR1519OD, minor, term to 2028-03-04
- ASM - NEW CANEY, New Caney: TXR05GQ76, minor, term to 2026-08-13
- BERTRAND WWTF, Conroe: TX0144061, minor, term to 2028-09-20
- CANEY CROSSING NORTH, New Caney: TXR1564OS, minor, term to 2028-03-04
- CLEARING & GRUBBING OF 37.4 ACRES OF LAND WITHIN EIPN, New Caney: TXR1509SZ, minor, term to 2028-03-04
- CONROE READY MIX, Conroe: TXG111221, minor, term to 2021-11-07
- CROWN CORK & SEAL, Conroe: TXR05HC98, minor, term to 2031-08-13
- E MONTGOMERY CNTY MUD 3 WWTP, New Caney: TX0125300, minor, term to 2022-06-01
- EAST DRAINAGE CHANNELS PHASE 2 FOR ARTAVIA DEVELOPMENT, Conroe: TXR1568MG, minor, term to 2028-03-04
- EAST MONTGOMERY COUNTY MUD 5, New Caney: TXR15413W, minor, term to 2023-03-04
What stands out
- Its term runs 2 years and 178 days, September 8, 2025 to March 4, 2028.
- No dated event in the 365 days to September 15, 2026.
- It is one of 39,714 discharge permits on the register in Texas; 23,986 of them (60%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | EAST INDUSTRIAL PARKWAY PHASE 2 |
|---|---|
| Permittee | Principal Services, Ltd. |
| NPDES ID | TXR1594VT |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | September 8, 2025 |
| Expires | March 4, 2028 |
| Address | New Caney, TX 77357 |
| Receiving water | WHITE OAK CREEK |
| Subwatershed | Dry Creek-Caney Creek (HUC 120401030105) |
NPDES TXR1594VT: effluent limits and exceedances
EAST INDUSTRIAL PARKWAY PHASE 2 (NPDES TXR1594VT): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES TXR1594VT: no pollutant row on file.
NPDES TXR1594VT: inspections, violations and enforcement
NPDES TXR1594VT (EAST INDUSTRIAL PARKWAY PHASE 2): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES TXR1594VT
NPDES TXR1594VT: one email when its EPA record changes — $99/month.
Permits near NPDES TXR1594VT
NPDES TXR1594VT: 0 pollutant rows, 0 dated events; ICIS-NPDES download, loaded September 15, 2026.