NPDES VAR10Q682 · Clean Water Act
FALLS CHURCH HIGH SCHOOL- RENOVATION, Falls Church, VA: NPDES VAR10Q682 discharge permit, effluent exceedances, inspections, penalties
FALLS CHURCH HIGH SCHOOL- RENOVATION, Falls Church, Virginia: General permit coverage VAR10Q682, held by Grunley Construction Company; Construction stormwater; Administratively continued; issued July 1, 2019, term to June 30, 2024, by VA DEQ; discharges to Cameron Run.
Virginia holds 6,257 Construction stormwater coverages of this permit type in EPA’s file; 4 were issued before VAR10Q682.
Coverages issued nearest VAR10Q682
- 2019-07-01: FAIRLAWN SOLID WASTE CONVENIENCE CENTER, Fairlawn: VAR10Q661, held by Pulaski County Public Service Authority
- 2019-07-01: WAKEMAN SUBSTATION & TRANSMISSION TAP LINE, Manassas: VAR10Q663, held by Virginia Electric and Power Co d/b/a Dominion Ener
- 2019-07-01: CHARLES CITY COUNTY SCHOOL COMPLEX SOLAR, Charles City: VAR10Q667, held by Gregory Electric Co Inc
- 2019-07-01: COSTELLO DRIVE SELF STORAGE FACILITY, Winchester: VAR10Q669, held by H and W Construction Company, Inc.
- 2019-07-01: STATION 180 ERP PROJECT, Unionville: VAR10Q674, held by Transcontinental Gas Pipe Line Co LLC
- 2019-07-01: FELLOWSHIP CHAPEL CHURCH, Bristol: VAR10Q683, held by True Line Construction Company Inc
- 2019-07-01: COLONIAL CIRCLE: 200 LOT FOR SALE RESIDENTIAL SUB, Palmyra: VAR10Q687, held by Stanley Martin Homes LLC
- 2019-07-01: FFX CO STORMWATER WASTEWATER FACILITY, Burke: VAR10Q689, held by Manhattan Construction
- 2019-07-01: THE ROSE GAMING RESORT, Dumfries: VAR10Q692, held by Colonial Downs Group
- 2019-07-01: APAH BRADDOCK ROAD, WOODLEIGH CHASE 1B-2, Fairfax: VAR10Q693, held by Braddock Nine Limited Partnership
FALLS CHURCH HIGH SCHOOL- RENOVATION among its neighbors
91 discharge permits are in the Cameron Run subwatershed (HUC 020700100302); VAR10Q682 is one. Its county: 74, 2 major; VAR10Q682 is minor permit.
Other permits in the Cameron Run subwatershed (HUC 020700100302)
- 2990 TELESTAR COURT, Falls Church: VAR10U977, minor, term to 2029-06-30
- 5001 EISENHOWER CONVERSION, Alexandria: VAR10V453, minor, term to 2029-06-30
- 6125 & 6101 STEVENSON AVENUE, Alexandria: VAR10V826, minor, term to 2029-06-30
- ALEXANDRIA CITY HIGH SCHOOL MINNIE HOWARD CAMPUS, Alexandria: VAR10Q842, minor, term to 2024-06-30
- ALEXANDRIA CITY SANITARY AUTHO, Alexandria: VAL025160, minor, term to 2025-12-31
- ALEXANDRIA CROSSING, Alexandria: VAR10W424, minor, term to 2029-06-30
- ALEXANDRIA CROSSING, Alexandria: VAR10W425, minor, term to 2029-06-30
- ALEXANDRIA CROSSING - SEWER LINE IMPROVEMENT, Alexandria: VAG830659, minor, term to 2028-02-29
- ALEXANDRIA RENEW ENTERPRISES WRRF, Alexandria: VAN010059, minor, term to 2021-12-31
- ALEXANDRIA UNION STATION IMPROVEMENTS, Alexandria: VAR10R486, minor, term to 2029-06-30
What stands out
- Its term runs 4 years and 365 days, July 1, 2019 to June 30, 2024; the term ended 807 days before EPA's file was loaded on September 15, 2026, and the file lists the permit as administratively continued.
- No dated event in the 365 days to September 15, 2026.
- It is one of 13,137 discharge permits on the register in Virginia; 6,257 of them (48%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | FALLS CHURCH HIGH SCHOOL- RENOVATION |
|---|---|
| Permittee | Grunley Construction Company |
| NPDES ID | VAR10Q682 |
| Status | Administratively continued |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | July 1, 2019 |
| Expires | June 30, 2024 |
| Agency | VA DEQ |
| Address | Falls Church, VA 22042 |
| Receiving water | Cameron Run |
| Subwatershed | Cameron Run (HUC 020700100302) |
| Other EPA IDs (FRS) | RCRA handler VAD988225686; ICIS-AIR source VA0000005105900120 |
NPDES VAR10Q682: effluent limits and exceedances
FALLS CHURCH HIGH SCHOOL- RENOVATION (NPDES VAR10Q682): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES VAR10Q682: no pollutant row on file.
NPDES VAR10Q682: inspections, violations and enforcement
NPDES VAR10Q682 (FALLS CHURCH HIGH SCHOOL- RENOVATION): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES VAR10Q682
NPDES VAR10Q682: one email when its EPA record changes — $99/month.
Permits near NPDES VAR10Q682
NPDES VAR10Q682: 0 pollutant rows, 0 dated events; ICIS-NPDES download, loaded September 15, 2026.