NPDES VAR10R014 · Clean Water Act
LINE 100 HARROWGATE LOCKS 115 KV TRANSMISSION LINE, Colonial Heights, VA: NPDES VAR10R014 discharge permit, effluent exceedances, inspections, penalties
LINE 100 HARROWGATE LOCKS 115 KV TRANSMISSION LINE, Colonial Heights, Virginia: General permit coverage VAR10R014, held by Virginia Electric and Power Co d/b/a Dominion Ener; Construction stormwater; Administratively continued; issued July 1, 2019, term to June 30, 2024, by VA DEQ; discharges to Appomattox River-Oldtown Creek.
- May 5, 2026: Evaluation (S).
Virginia holds 6,257 Construction stormwater coverages of this permit type in EPA’s file; 4 were issued before VAR10R014. Virginia Electric and Power Co d/b/a Dominion Ener holds 68 permits in Virginia.
Other permits held by Virginia Electric and Power Co d/b/a Dominion Ener
- FLAT CREEK SUBSTATION, Burkeville: VAR10O915, issued 2019-07-01
- VARINA SUBSTATION ON FERGUS BLVD, Henrico: VAR10P021, issued 2019-07-01
- CRYSTAL SUBSTATION EXPANSION & MODERNIZATION, Arlington: VAR10P445, issued 2019-07-01
- GLEBE SUBSTATION TO POTOMAC YARD LINE #2023 & #248, Arlington: VAR10Q369, issued 2019-07-01
- LINES 53 AND 72 TRANSMISSION LINE REBUILD, Richmond: VAR10Q530, issued 2019-07-01
- MOUNT STORM TO VALLEY 500 KV TRANSMISSION LINE 550, Fulks Run: VAR10Q549, issued 2019-07-01
- WAKEMAN SUBSTATION & TRANSMISSION TAP LINE, Manassas: VAR10Q663, issued 2019-07-01
- SEBERA RD SOLAR, Prince George County: VAR10Q791, issued 2019-07-01
- WALNUT SOLAR - PART 2, Saluda: VAR10R081, issued 2019-07-01
- GRAPE VINE SUBSTATION, Palmyra: VAR10R292, issued 2019-07-01
Coverages issued nearest VAR10R014
- 2019-07-01: WAKEFIELD FOREST ELEMENTARY SCHOOL RENOVATION & AD, Fairfax: VAR10Q996, held by Fairfax County Public Schools
- 2019-07-01: LOT 9 SPEC BUILDING AT PORT LOGISTICS PARK, Suffolk: VAR10Q997, held by Monroe Lot 8 Owner, LLC
- 2019-07-01: REHAB POTOMAC INT AT MH31 190010, Great Falls: VAR10R011, held by Ulliman Schutte Construction, LLC
- 2019-07-01: LEGACY OF POQUOSON PHASE 2 & 3, Poquoson: VAR10R012, held by The Big Woods Development Company LLC
- 2019-07-01: PROFFIT ROAD TOWNHOMES NORTH, Charlottesville: VAR10R013, held by Ryan Homes
- 2019-07-01: SUBDIVISION PLAN FOR SHILLELAGH ROAD SUBDIVISION, Chesapeake: VAR10R015, held by Back Bay Construction Inc
- 2019-07-01: OTTER CREEK SOLAR PHASE II, Mecklenburg: VAR10R016, held by Virginia Electric and Power Company dba Dominion E
- 2019-07-01: LANDMARK MALL, Alexandria: VAR10R021, held by Landmark Land Holdings, LLC
- 2019-07-01: SWING SPACE BARRACKS, Fort Myer: VAR10R024, held by Teya Enterprises LLC
- 2019-07-01: O'REILLY & STARBUCK, Powhatan: VAR10R026, held by VA Powhatan 60 LLC
LINE 100 HARROWGATE LOCKS 115 KV TRANSMISSION LINE among its neighbors
22 discharge permits are in the Franks Branch-Swift Creek subwatershed (HUC 020802070904); VAR10R014 is one.
Other permits in the Franks Branch-Swift Creek subwatershed (HUC 020802070904)
- 7-ELEVEN CONVENIENCE STORE WITH GAS, Colonial Heights: VAR10N754, minor, term to 2024-06-30
- CHESTER SOLAR PARK SWITCHYARD, Chesterfield: VAR10W713, minor, term to 2029-06-30
- CHURCH AND DWIGHT COMPANY INCORPORATED, Colonial Heights: VAR051125, minor, term to 2024-06-30
- HARROWGATE PARK PH III, Chester: VAR10S127, minor, term to 2024-06-30
- HILL PHOENIX (PLANT I), Colonial Heights: VAR051687, minor, term to 2024-06-30
- LAKEVIEW AVENUE MODERNIZATION FROM BRIJIDAN LANE T, Colonial Heights: VAR10P487, minor, term to 2024-06-30
- LAKEVIEW HYDROELECTRIC PROJECT, Colonial Heights: VAG250131, minor, term to 2023-03-01
- MATOACA FIRE STATION, Chesterfield: VAG404378, minor, term to 2026-07-31
- MATOACA FIRE STATION, Chesterfield: VAG750274, minor, term to 2022-10-15
- MATOACA HIGH SCHOOL, Chesterfield: VA0090344, minor, term to 2026-05-31
What stands out
- Its term runs 4 years and 365 days, July 1, 2019 to June 30, 2024; the term ended 807 days before EPA's file was loaded on September 15, 2026, and the file lists the permit as administratively continued.
- Its newest dated event on file is an inspection on May 5, 2026, 133 days before EPA's file was loaded.
- In the 365 days to September 15, 2026, it was dated 1 inspection.
- EPA's file dates 1 event for it, all in 2026.
- It is one of 13,137 discharge permits on the register in Virginia; 6,257 of them (48%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | LINE 100 HARROWGATE LOCKS 115 KV TRANSMISSION LINE |
|---|---|
| Permittee | Virginia Electric and Power Co d/b/a Dominion Ener |
| NPDES ID | VAR10R014 |
| Status | Administratively continued |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | July 1, 2019 |
| Expires | June 30, 2024 |
| Agency | VA DEQ |
| Address | Colonial Heights, VA 23834 |
| Receiving water | Appomattox River-Oldtown Creek |
| Subwatershed | Franks Branch-Swift Creek (HUC 020802070904) |
NPDES VAR10R014: effluent limits and exceedances
LINE 100 HARROWGATE LOCKS 115 KV TRANSMISSION LINE (NPDES VAR10R014): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES VAR10R014: no pollutant row on file.
NPDES VAR10R014: inspections, violations and enforcement
NPDES VAR10R014: 1 inspection
| Date | What EPA recorded | Agency |
|---|---|---|
| May 5, 2026 | Evaluation | S |
NPDES VAR10R014 (LINE 100 HARROWGATE LOCKS 115 KV TRANSMISSION LINE): no single-event violation, formal enforcement action and informal enforcement action on file.
Watch NPDES VAR10R014
NPDES VAR10R014: one email when its EPA record changes — $99/month.
Permits near NPDES VAR10R014
NPDES VAR10R014: 0 pollutant rows, 1 dated events; ICIS-NPDES download, loaded September 15, 2026.