DEMOLISH AND CONSTRUCT CRESCENT HARBOR ELEMENTARY SCHOOL, held by Tiger Construction Ltd, holds NPDES permit WAR10F09N. EPA’s file records it issued July 25, 2024 and expiring February 16, 2027. The status and dates are as EPA’s permit file stood when Velarion loaded it (September 15, 2026); EPA’s free Detailed Facility Report on ECHO carries the permit’s current standing.
What the register holds for DEMOLISH AND CONSTRUCT CRESCENT HARBOR ELEMENTARY SCHOOL: its NPDES ID, its permit type and status, its dates, its address in Oak Harbor, Washington. EPA’s effluent violation file and its single-event violation file hold no violation for NPDES WAR10F09N.
What stands out
- Its term runs 2 years and 206 days, July 25, 2024 to February 16, 2027.
- No dated event in the 365 days to September 15, 2026.
- It is one of 8,573 discharge permits on the register in Washington; 4,744 of them (55%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility as filed | DEMOLISH AND CONSTRUCT CRESCENT HARBOR ELEMENTARY SCHOOL |
|---|---|
| Permittee as filed | Tiger Construction Ltd |
| NPDES ID | WAR10F09N |
| Permit status | Effective |
| Permit type | Coverage under a general permit |
| Discharger class | Minor discharger |
| Facility type | Not a publicly owned treatment works |
| Program | Construction stormwater |
| Issued | July 25, 2024 |
| Expiration date | February 16, 2027 |
| Issuing agency | U.S. EPA |
| Address | Oak Harbor, WA 98277 |
| Subwatershed | Whidbey Island-Saratoga Passage (HUC 171100190103) |
Cited to the EPA ICIS-NPDES permit file (ECHO download).
Effluent limits and exceedances
- 0Pollutants on file
- 0Under a numeric limit
- 0With a violation of any kind
- 0With an effluent exceedance
EPA’s limits and effluent violation files hold no pollutant row for NPDES WAR10F09N.
Cited to the EPA ICIS-NPDES limits and effluent violations files (ECHO download); up to 60 rows shown, most exceedances first.
Inspections, violations and enforcement
- 0Single-event violations
EPA’s single-event violation file, as loaded, holds no violation for NPDES WAR10F09N.
Inspections
EPA’s inspection file holds no inspection for NPDES WAR10F09N.
Formal enforcement and penalties
0 formal actions, 0 of them with a penalty assessed. Federal and state penalties are separate figures from separate authorities and are shown as each was filed, never added together.
Informal enforcement
EPA’s informal enforcement file holds no action for NPDES WAR10F09N.
Cited to the EPA ICIS-NPDES violation, inspection and enforcement files (ECHO download); up to 50 rows of each shown, newest first.
Watch this permit
One permit holder, $99/month. Watch the register for one permit holder and the places and receiving waters tied to its permits. Choose “One permit holder” and enter this permit’s NPDES ID, WAR10F09N.
Start the watch
- One permit holder — $99/month
- One watershed — $2,990/year
- One state — $4,990/year
- The whole register — $18,000/year
How we handle your data → Privacy
EPA publishes a free Detailed Facility Report for every permit on ECHO: its compliance status quarter by quarter, its inspections, and its enforcement actions and penalties. EPA also sends free notices of new inspections and enforcement actions through ECHO Notify; enter NPDES ID WAR10F09N there.
DEMOLISH AND CONSTRUCT CRESCENT HARBOR ELEMENTARY SCHOOL, Oak Harbor, Washington: Coverage under a general permit WAR10F09N, held by Tiger Construction Ltd; Construction stormwater; Effective; issued July 25, 2024, term to February 16, 2027, by U.S. EPA.
Washington holds 4,744 Construction stormwater coverages of this permit type in EPA’s file; 3,844 were issued before WAR10F09N. Tiger Construction Ltd holds 2 permits in Washington.
Other permits held by Tiger Construction Ltd
- ORCAS ISLAND SCHOOL DISTRICT, Eastsound: WAR315672, issued 2025-11-19
Coverages issued nearest WAR10F09N
- 2024-05-02: AMPERE DEMOLITION AND SITE PREPARATION, Vancouver: WAR10F099, held by Bonneville Power Administration Sean Joyce Director of Facilities Services
- 2024-05-24: US 101 / QUINAULT RESERVATION - REMOVE FISH BARRIERS, Queets: WAR10I039, held by Kiewit Infrastructure Co.
- 2024-06-04: MOUNT SAINT HELENS SPIRIT LAKE TUNNEL INTAKE, Cougar: WAR10F09F, held by Advanced American Construction
- 2024-07-16: FY24 MDTF DOUBLE BARRACKS, Jblm: WAR10F09M, held by Absher Construction
- 2024-07-22: SR 105 / GRAVEYARD SPIT DYNAMIC REVETMENT AND DUNE RESTORATION, Tokeland: WAR10I03B, held by Washington State Department of Transportation
- 2024-07-29: STREAMBANK STABILIZATION FOR 45PO412, Usk: WAR10I03D, held by Kalispel Indian Community of the Kalispel Reservation
- 2024-07-31: DEMOLISH AND CONSTRUCT CRESCENT HARBOR ELEMENTARY SCHOOL, Oak Harbor: WAR10F09S, held by NAS Whidbey Island
- 2024-08-14: REPAIR PERIMETER ROAD BRIDGE, Mcchord Afb: WAR10F09U, held by Tribal One Technology
- 2024-08-21: DOMERIE BAY, Cle Elum: WAR10I03H, held by Gibson and Son Roadbuilding
- 2024-08-21: TIMBER COVE, Cle Elum: WAR10I03I, held by Gibson and Son Roadbuilding
DEMOLISH AND CONSTRUCT CRESCENT HARBOR ELEMENTARY SCHOOL among its neighbors
25 discharge permits are in the Whidbey Island-Saratoga Passage subwatershed (HUC 171100190103); WAR10F09N is one.
Other permits in the Whidbey Island-Saratoga Passage subwatershed (HUC 171100190103)
- BAYVIEW VISTA, Oak Harbor: WAR312213, minor, term to 2025-12-31
- CAMAS FLATS, Oak Harbor: WAR313688, minor, term to 2025-12-31
- CENTRAL WHIDBEY S&G, Coupeville: WAG503073, minor, term to 2026-03-31
- DEMOLISH AND CONSTRUCT CRESCENT HARBOR ELEMENTARY SCHOOL, Oak Harbor: WAR10F09S, minor, term to 2027-02-16
- F 1 SAND & GRAVEL, Oak Harbor: WAG503153, minor, term to 2026-03-31
- GREENBANK CONCRETE AND AGGREGATES, Coupeville: WAG503367, minor, term to 2026-03-31
- HAND IN HAND, Oak Harbor: WAR10F0A4, minor, term to 2027-02-16
- HAND IN HAND, Oak Harbor: WAR10F0A6, minor, term to 2027-02-16
- HILLSIDE, Oak Harbor: WAR309045, minor, term to 2025-12-31
- HILLSIDE DEVELOPMENT CENTER, Oak Harbor: WAR308587, minor, term to 2025-12-31
Nearby on the register
- Discharge permits in Oak Harbor
- Every permit record in Oak Harbor, A to Z
- Discharge permits in Washington
- Every permit record in Washington, A to Z
Figures from EPA’s ICIS-NPDES download, loaded September 15, 2026.
What this page shows
Among the 21 storm water construction permits in Oak Harbor, this one, filed as DEMOLISH AND CONSTRUCT CRESCENT HARBOR ELEMENTARY SCHOOL, is one of 25 NPDES permits in the Whidbey Island-Saratoga Passage subwatershed, and 66.7% of the Oak Harbor storm water construction permits were issued earlier than its July 25, 2024 issue date. The permit records no pollutants under a numeric limit and no effluent exceedances, which is a zero count for both measures.