EPA Air · inspections by county and year
Air-emissions inspections in North Slope County, Alaska, 2018
- 171Inspections
A compliance evaluation is the on-site or file review a state, local or federal air agency records against a permitted source. Each row below is one inspection recorded against a source in North Slope County, Alaska during 2018. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the North Slope County facility page.
North Slope County, Alaska, 2018
Air-emissions inspections in North Slope County, other years
Air-emissions inspections recorded in North Slope County, Alaska, 2018
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2018-05-31 | CONOCOPHILLIPS ALASKA, INC. / CPF 2, KUPARUK CENTRAL PRODUCTION FACIL | PCE Off-Site | State |
| 2018-05-17 | HILCORP ALASKA, LLC / GATHERING CENTER #3 (GC 3) | PCE Off-Site | State |
| 2018-05-16 | HILCORP ALASKA, LLC / GATHERING CENTER #2 (GC 2) | PCE Off-Site | State |
| 2018-05-11 | HILCORP ALASKA, LLC / CENTRAL COMPRESSOR PLANT (CCP) | PCE Off-Site | State |
| 2018-05-11 | TDX NORTH SLOPE GENERATING, LLC / TNSG SOUTH PLANT | PCE Off-Site | State |
| 2018-05-11 | TDX NORTH SLOPE GENERATING, LLC / TNSG SOUTH PLANT | PCE Off-Site | State |
| 2018-05-10 | CONOCOPHILLIPS ALASKA, INC. / CPF 1, KUPARUK CENTRAL PRODUCTION FACIL | PCE Off-Site | State |
| 2018-05-10 | CONOCOPHILLIPS ALASKA, INC. / KUPARUK RIVER UNIT TRANSPORTABLE DRILLI | PCE Off-Site | State |
| 2018-05-10 | TDX POWER, LLC / TNSG NORTH POWER PLANT — high-priority violation on file | PCE Off-Site | State |
| 2018-05-10 | TDX POWER, LLC / TNSG NORTH POWER PLANT — high-priority violation on file | PCE Off-Site | State |
| 2018-05-08 | CONOCOPHILLIPS ALASKA, INC. / CPF 3, KUPARUK CENTRAL PRODUCTION FACIL | PCE Off-Site | State |
| 2018-05-08 | CONOCOPHILLIPS ALASKA, INC. / KUPARUK SEAWATER TREATMENT PLANT (STP) | PCE Off-Site | State |
| 2018-05-04 | CONOCOPHILLIPS ALASKA, INC. / ALPINE SATELLITE DRILL PAD CD5 | PCE Off-Site | State |
| 2018-05-04 | CONOCOPHILLIPS ALASKA, INC. / ALPINE SATELLITE DRILL PAD CD5 | PCE Off-Site | State |
| 2018-05-02 | HILCORP ALASKA, LLC / TRANSPORTABLE DRILLING RIGS (DRILL RIGS | PCE Off-Site | State |
| 2018-05-02 | HILCORP ALASKA, LLC / TRANSPORTABLE DRILLING RIGS (DRILL RIGS | PCE Off-Site | State |
| 2018-04-19 | HILCORP ALASKA, LLC / CENTRAL GAS FACILITY (CGF) — high-priority violation on file | PCE Off-Site | State |
| 2018-04-17 | HILCORP ALASKA, LLC / LISBURNE PRODUCTION CENTER (LPC) | PCE Off-Site | State |
| 2018-04-10 | SAVANT ALASKA LLC / BADAMI DEVELOPMENT FACILITY — high-priority violation on file | PCE Off-Site | State |
| 2018-04-09 | HILCORP ALASKA, LLC / NORTHSTAR PRODUCTION FACILITY (NOR) | PCE Off-Site | State |
| 2018-04-05 | ALYESKA PIPELINE SERVICE COMPANY / PS #04, TAPS PUMP STATION | PCE Off-Site | State |
| 2018-04-04 | NORTH SLOPE BOROUGH / POINT HOPE POWER PLANT | PCE Off-Site | State |
| 2018-03-29 | HILCORP ALASKA, LLC / FLOW STATION #1 (FS 1) — high-priority violation on file | PCE Off-Site | State |
| 2018-03-28 | HILCORP ALASKA, LLC / CENTRAL GAS FACILITY (CGF) — high-priority violation on file | PCE Off-Site | State |
| 2018-03-28 | HILCORP ALASKA, LLC / GATHERING CENTER #1 (GC 1) | PCE Off-Site | State |
| 2018-03-27 | ALYESKA PIPELINE SERVICE COMPANY / PS #01, TAPS PUMP STATION | PCE Off-Site | State |
| 2018-03-27 | BARROW UTILITIES & ELECTRIC COOPERATIV / BARROW POWER PLANT | PCE Off-Site | State |
| 2018-03-23 | NORTH SLOPE BOROUGH / NUIQSUT POWER PLANT — high-priority violation on file | PCE Off-Site | State |
| 2018-03-23 | NORTH SLOPE BOROUGH / KAKTOVIK POWER PLANT | PCE Off-Site | State |
| 2018-03-23 | HILCORP ALASKA, LLC / NORTHSTAR PRODUCTION FACILITY (NOR) | PCE Off-Site | State |
| 2018-03-21 | HILCORP ALASKA, LLC / NORTHSTAR PRODUCTION FACILITY (NOR) | PCE Off-Site | State |
| 2018-03-21 | NORTH SLOPE BOROUGH / BARROW TOS FACILITY | PCE Off-Site | State |
| 2018-03-20 | HILCORP ALASKA, LLC / PRUDHOE SEAWATER TREATMENT PLANT | PCE Off-Site | State |
| 2018-03-20 | HILCORP ALASKA, LLC / GRIND AND INJECT FACILITY (G & I) | PCE Off-Site | State |
| 2018-03-20 | HILCORP ALASKA, LLC / CRUDE OIL TOPPING UNIT (COTU) | PCE Off-Site | State |
| 2018-03-19 | HILCORP ALASKA, LLC / SEAWATER INJECTION PLANT EAST (SIPE) | PCE Off-Site | State |
| 2018-03-19 | HILCORP ALASKA, LLC / MILNE POINT PRODUCTION FACILITY (MPU) | PCE Off-Site | State |
| 2018-03-16 | HILCORP ALASKA, LLC / ENDICOTT PRODUCTION FACILITY (END) | FCE On-Site | State |
| 2018-03-15 | HILCORP ALASKA, LLC / NIKAITCHUQ DEVELOPMENT | FCE On-Site | State |
| 2018-03-13 | HILCORP ALASKA, LLC / CENTRAL COMPRESSOR PLANT (CCP) | PCE Off-Site | State |
| 2018-03-13 | NORTH SLOPE BOROUGH / WAINWRIGHT POWER PLANT | PCE Off-Site | State |
| 2018-03-12 | CONOCOPHILLIPS ALASKA, INC. / ALPINE CENTRAL PROCESSING FACILITY | PCE Off-Site | State |
| 2018-03-06 | NANUQ INC. / ARCTIC WOLF CAMP | PCE Off-Site | State |
| 2018-03-06 | ALASKA FRONTIER CONSTRUCTORS INC. / 24 MAN SKID CAMP | PCE Off-Site | State |
| 2018-03-05 | HILCORP ALASKA, LLC / GATHERING CENTER #2 (GC 2) | PCE Off-Site | State |
| 2018-03-05 | HILCORP ALASKA, LLC / GATHERING CENTER #3 (GC 3) | PCE Off-Site | State |
| 2018-03-02 | HILCORP ALASKA, LLC / ENDICOTT PRODUCTION FACILITY (END) | PCE Off-Site | State |
| 2018-03-01 | HILCORP ALASKA, LLC / ENDICOTT PRODUCTION FACILITY (END) | PCE Off-Site | State |
| 2018-02-27 | ALYESKA PIPELINE SERVICE COMPANY / PS #03, TAPS PUMP STATION | PCE Off-Site | State |
| 2018-02-26 | NORTH SLOPE BOROUGH / ANAKTUVUK PASS POWER PLANT — high-priority violation on file | PCE Off-Site | State |
| 2018-02-26 | NORTH SLOPE BOROUGH / ATQASUK POWER PLANT | PCE Off-Site | State |
| 2018-02-23 | NORTH SLOPE BOROUGH / POINT LAY POWER PLANT | PCE Off-Site | State |
| 2018-02-23 | BAROID DRILLING FLUIDS (HALLIBURTON) / PRUDHOE BAY MUD PLANT | PCE Off-Site | State |
| 2018-02-23 | HILCORP ALASKA, LLC / OOOGURUK DEVELOPMENT PROJECT | FCE On-Site | State |
| 2018-02-20 | NORTH SLOPE BOROUGH / WAINWRIGHT POWER PLANT | FCE On-Site | State |
| 2018-02-13 | HILCORP ALASKA, LLC / FLOW STATION #2 (FS 2) | PCE Off-Site | State |
| 2018-02-12 | HILCORP ALASKA, LLC / FLOW STATION #3 (FS 3) — high-priority violation on file | PCE Off-Site | State |
| 2018-02-12 | HILCORP ALASKA, LLC / FLOW STATION #3 (FS 3) — high-priority violation on file | PCE Off-Site | State |
| 2018-02-09 | HILCORP ALASKA, LLC / NIKAITCHUQ DEVELOPMENT | PCE Off-Site | State |
| 2018-02-08 | MUSTANG HOLDING LLC / MUSTANG PAD | PCE Off-Site | State |
| 2018-02-05 | HILCORP ALASKA, LLC / OOOGURUK DEVELOPMENT PROJECT | PCE Off-Site | State |
| 2018-01-31 | US AIR FORCE, PACAF REGIONAL SUPPORT C / BARTER ISLAND LRRS | PCE Off-Site | State |
| 2018-01-31 | US AIR FORCE, PACAF REGIONAL SUPPORT C / CAPE LISBURNE LRRS | PCE Off-Site | State |
| 2018-01-31 | US AIR FORCE, PACAF REGIONAL SUPPORT C / OLIKTOK LRRS | PCE Off-Site | State |
| 2018-01-31 | US AIR FORCE, PACAF REGIONAL SUPPORT C / POINT BARROW LRRS | PCE Off-Site | State |
| 2018-01-19 | NORTH SLOPE BOROUGH / SERVICE AREA TEN HOTEL | PCE Off-Site | State |
| 2018-01-10 | MUSTANG HOLDING LLC / MUSTANG PAD | FCE Off-Site | State |
| 2018-01-08 | CONOCOPHILLIPS ALASKA, INC. / ALPINE CENTRAL PROCESSING FACILITY | PCE Off-Site | State |
| 2018-01-08 | CONOCOPHILLIPS ALASKA, INC. / KUPARUK RIVER UNIT TRANSPORTABLE DRILLI | PCE Off-Site | State |
| 2018-01-08 | CONOCOPHILLIPS ALASKA, INC. / ALPINE SATELLITE DRILL PAD CD5 | PCE Off-Site | State |
| 2018-01-08 | CONOCOPHILLIPS ALASKA, INC. / ALPINE SATELLITE DRILL PAD CD5 | PCE Off-Site | State |
PreviousPage 1Page 2 of 2
Dates as filed by the agency that recorded the inspection. Figures from EPA’s ICIS-AIR download.