EPA Air · stack tests by county and year
Air-emissions stack tests in St. Clair County, Michigan, 2022
- 38Stack tests
A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row below is one stack test recorded against a source in St. Clair County, Michigan during 2022. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the St. Clair County facility page.
St. Clair County, Michigan, 2022
Air-emissions stack tests in St. Clair County, other years
Air-emissions stack tests recorded in St. Clair County, Michigan, 2022
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2022-12-08 | INTERTAPE POLYMER GROUP | Pending | State |
| 2022-11-16 | DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on file | Pass | State |
| 2022-11-16 | SMITHS CREEK LANDFILL | Pass | State |
| 2022-11-09 | DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on file | Pass | State |
| 2022-09-22 | DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on file | Pending | State |
| 2022-09-14 | DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on file | Pending | State |
| 2022-09-13 | BLUEWATER GAS STORAGE FACILITY - COLUMBUS | Pass | State |
| 2022-09-08 | DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on file | Pass | State |
| 2022-09-07 | DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on file | Pass | State |
| 2022-08-30 | DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on file | Pending | State |
| 2022-08-30 | DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on file | Pass | State |
| 2022-08-23 | DTE GAS COMPANY - BELLE RIVER MILLS COMPRESSOR STATION | Pass | State |
| 2022-08-17 | INTERTAPE POLYMER GROUP | Pending | State |
| 2022-08-04 | DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on file | Pass | State |
| 2022-07-20 | DTE ELECTRIC COMPANY - GREENWOOD ENERGY CENTER | Pass | State |
| 2022-07-15 | DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on file | Pending | State |
| 2022-07-12 | DTE ELECTRIC COMPANY - GREENWOOD ENERGY CENTER | Pass | State |
| 2022-07-12 | DTE GAS COMPANY - BELLE RIVER MILLS COMPRESSOR STATION | Pass | State |
| 2022-06-15 | DTE GAS COMPANY - COLUMBUS COMPRESSOR STATION — high-priority violation on file | Pass | State |
| 2022-06-01 | DTE GAS COMPANY - BELLE RIVER MILLS COMPRESSOR STATION | Pass | State |
| 2022-05-23 | DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on file | Pass | State |
| 2022-05-18 | DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on file | Pass | State |
| 2022-05-17 | DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on file | Pass | State |
| 2022-05-16 | DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on file | Pass | State |
| 2022-04-19 | DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on file | Pass | State |
| 2022-04-19 | DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on file | Pass | State |
| 2022-04-15 | DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on file | Pass | State |
| 2022-04-14 | DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on file | Pass | State |
| 2022-04-13 | DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on file | Pass | State |
| 2022-04-12 | DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on file | Pass | State |
| 2022-03-24 | DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on file | Pending | State |
| 2022-03-15 | DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on file | Pass | State |
| 2022-03-11 | DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on file | Pass | State |
| 2022-02-24 | SMITHS CREEK LANDFILL | Pass | State |
| 2022-02-17 | DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on file | Pass | State |
| 2022-01-26 | DTE GAS COMPANY - COLUMBUS COMPRESSOR STATION — high-priority violation on file | Pass | State |
| 2022-01-21 | DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on file | Pass | State |
| 2022-01-05 | DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on file | Pass | State |
Dates as filed by the agency that recorded the stack test. Figures from EPA’s ICIS-AIR download.