NPDES VAR10W355 · Clean Water Act
WHITE OAK 230 KV DELIVERY PROJECT PHASE 2, Sandston, VA: NPDES VAR10W355 discharge permit, effluent exceedances, inspections, penalties
WHITE OAK 230 KV DELIVERY PROJECT PHASE 2, Sandston, Virginia: General permit coverage VAR10W355, held by Virginia Electric and Power Co d/b/a Dominion Ener; Construction stormwater; Effective; issued July 1, 2024, term to June 30, 2029, by VA DEQ; discharges to Chickahominy River-Higgins Swamp.
- May 28, 2026: Evaluation (S).
Virginia holds 6,257 Construction stormwater coverages of this permit type in EPA’s file; 3,403 were issued before VAR10W355. Virginia Electric and Power Co d/b/a Dominion Ener holds 68 permits in Virginia.
Other permits held by Virginia Electric and Power Co d/b/a Dominion Ener
- FLAT CREEK SUBSTATION, Burkeville: VAR10O915, issued 2019-07-01
- VARINA SUBSTATION ON FERGUS BLVD, Henrico: VAR10P021, issued 2019-07-01
- CRYSTAL SUBSTATION EXPANSION & MODERNIZATION, Arlington: VAR10P445, issued 2019-07-01
- GLEBE SUBSTATION TO POTOMAC YARD LINE #2023 & #248, Arlington: VAR10Q369, issued 2019-07-01
- LINES 53 AND 72 TRANSMISSION LINE REBUILD, Richmond: VAR10Q530, issued 2019-07-01
- MOUNT STORM TO VALLEY 500 KV TRANSMISSION LINE 550, Fulks Run: VAR10Q549, issued 2019-07-01
- WAKEMAN SUBSTATION & TRANSMISSION TAP LINE, Manassas: VAR10Q663, issued 2019-07-01
- SEBERA RD SOLAR, Prince George County: VAR10Q791, issued 2019-07-01
- LINE 100 HARROWGATE LOCKS 115 KV TRANSMISSION LINE, Colonial Heights: VAR10R014, issued 2019-07-01
- WALNUT SOLAR - PART 2, Saluda: VAR10R081, issued 2019-07-01
Coverages issued nearest VAR10W355
- 2024-07-01: QUAIL RUN PHASE 5, Elkton: VAR10W350, held by Valley Sitework, LLC
- 2024-07-01: WATERLOO JUNCTION (VERITAS), Warrenton: VAR10W351, held by Van Metre Homes at Veritas, LLC
- 2024-07-01: SUNNY VALLEY SUBDIVISION, Bristol: VAR10W352, held by JD Watson & Associates
- 2024-07-01: SHERANDO RECREATION AREA REHABILITATION, Lyndhurst: VAR10W353, held by USDA Forest Service George Washington and Jefferso
- 2024-07-01: TUCKAHOE LIBRARY STREAM RESTORATION, Henrico: VAR10W354, held by Henrico DPW
- 2024-07-01: VFP BUILDING #1 ADDITION, Duffield: VAR10W356, held by J.A Street & Associates
- 2024-07-01: DAIKIN OFFICE UPGRADE, Verona: VAR10W357, held by Lantz Construction Company
- 2024-07-01: QUARTZ DISTRICT - EAST VILLAGE PHASE 1, Woodbridge: VAR10W359, held by STANLEY MARTIN HOMES LLC
- 2024-07-01: MOUNT ROGERS COMMUNITY SERVICES- RECOVERY CENTER, Marion: VAR10W360, held by J A Street & Associates, Inc.
- 2024-07-01: R-TEC I-64 INDUSTRIAL PARK, Oilville: VAR10W361, held by R-Tec Services, LLC
WHITE OAK 230 KV DELIVERY PROJECT PHASE 2 among its neighbors
15 discharge permits are in the Higgins Swamp-Chickahominy River subwatershed (HUC 020802060502); VAR10W355 is one.
Other permits in the Higgins Swamp-Chickahominy River subwatershed (HUC 020802060502)
- BOTTOMS BRIDGE MINI-STORAGE, Quinton: VAR10U059, minor, term to 2029-06-30
- BOTTOMS BRIDGE SHOPS, Quinton: VAR10V639, minor, term to 2029-06-30
- DUNHAM FARMS, Mechanicsville: VAR10V177, minor, term to 2029-06-30
- ESSEX CONCRETE CORPORATION - BOTTOMS BRIDGE, Quinton: VAG110398, minor, term to 2028-12-31
- FLAGSTOP CAR WASH AT BOTTOMS BRIDGE, Quinton: VAR10U099, minor, term to 2024-06-30
- IMDC-RCH1, Sandston: VAR10V888, minor, term to 2029-06-30
- JOURNEY CHURCH AND SPORTS PARK, Quinton: VAR10P804, minor, term to 2024-06-30
- LEBER ESTATES, Mechanicsville: VAR10Q628, minor, term to 2024-06-30
- NEW BRIDGE BAPTIST CHURCH - PROPOSED GYMNASIUM, Sandston: VAR10X434, minor, term to 2029-06-30
- QTS RIC5 - PHASE 1, Sandston: VAR10W432, minor, term to 2029-06-30
What stands out
- Its term runs 4 years and 364 days, July 1, 2024 to June 30, 2029.
- Its newest dated event on file is an inspection on May 28, 2026, 110 days before EPA's file was loaded.
- In the 365 days to September 15, 2026, it was dated 1 inspection.
- EPA's file dates 1 event for it, all in 2026.
- It is one of 13,137 discharge permits on the register in Virginia; 6,257 of them (48%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | WHITE OAK 230 KV DELIVERY PROJECT PHASE 2 |
|---|---|
| Permittee | Virginia Electric and Power Co d/b/a Dominion Ener |
| NPDES ID | VAR10W355 |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | July 1, 2024 |
| Expires | June 30, 2029 |
| Agency | VA DEQ |
| Address | Sandston, VA 23150 |
| Receiving water | Chickahominy River-Higgins Swamp |
| Subwatershed | Higgins Swamp-Chickahominy River (HUC 020802060502) |
NPDES VAR10W355: effluent limits and exceedances
WHITE OAK 230 KV DELIVERY PROJECT PHASE 2 (NPDES VAR10W355): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES VAR10W355: no pollutant row on file.
NPDES VAR10W355: inspections, violations and enforcement
NPDES VAR10W355: 1 inspection
| Date | What EPA recorded | Agency |
|---|---|---|
| May 28, 2026 | Evaluation | S |
NPDES VAR10W355 (WHITE OAK 230 KV DELIVERY PROJECT PHASE 2): no single-event violation, formal enforcement action and informal enforcement action on file.
Watch NPDES VAR10W355
NPDES VAR10W355: one email when its EPA record changes — $99/month.
Permits near NPDES VAR10W355
NPDES VAR10W355: 0 pollutant rows, 1 dated events; ICIS-NPDES download, loaded September 15, 2026.