Velarion Records
Free: one email when NPDES IDR10C1QT changes. Unsubscribe any time.

NPDES IDR10C1QT · Clean Water Act

DAWSON TRAILS (OPERATOR), Mccall, ID: NPDES IDR10C1QT discharge permit, effluent exceedances, inspections, penalties

DAWSON TRAILS (OPERATOR), Mccall, Idaho: General permit coverage IDR10C1QT, held by Nick Louie; Construction stormwater; Effective; issued January 10, 2022, term to February 9, 2027; discharges to Payette Lake.

  • April 13, 2026: WW Storm Water Construction - Failure to develop any or adequate SWPPP/SWMP (ST6).
  • April 13, 2026: WW Storm Water Construction - Failure to Maintain Records (ST6).
  • April 13, 2026: WW Storm Water Construction - Failure to properly install/implement BMPs (ST6).
  • April 13, 2026: Evaluation (S).
  • April 11, 2026: WW Storm Water Construction - Failure to Conduct Inspections (ST6).
  • April 10, 2026: WW Storm Water Construction - Failure to Conduct Inspections (ST6).
  • April 9, 2026: WW Storm Water Construction - Failure to Conduct Inspections (ST6).
  • April 8, 2026: WW Storm Water Construction - Failure to Conduct Inspections (ST6).

Idaho holds 3,630 Construction stormwater coverages of this permit type in EPA’s file; 576 were issued before IDR10C1QT.

Coverages issued nearest IDR10C1QT

DAWSON TRAILS (OPERATOR) among its neighbors

21 discharge permits are in the Payette Lake subwatershed (HUC 170501230106); IDR10C1QT is one. Its county: 78, 0 major; IDR10C1QT is minor permit.

Other permits in the Payette Lake subwatershed (HUC 170501230106)

What stands out

  • Its term runs 5 years and 30 days, January 10, 2022 to February 9, 2027.
  • Its newest dated event on file is single-event violation and inspection on April 13, 2026, 155 days before EPA's file was loaded.
  • In the 365 days to September 15, 2026, it was dated 7 single-event violations, 1 inspection.
  • EPA's file dates 8 events for it, all in 2026.
  • It is one of 4,607 discharge permits on the register in Idaho; 3,631 of them (79%) are in its program, Construction stormwater, and it is a minor discharger.

Identity

FacilityDAWSON TRAILS (OPERATOR)
PermitteeNick Louie
NPDES IDIDR10C1QT
StatusEffective
TypeGeneral permit coverage
ClassMinor
Facility typeNon-POTW
ProgramConstruction stormwater
IssuedJanuary 10, 2022
ExpiresFebruary 9, 2027
AddressMccall, ID 83638
Receiving waterPayette Lake
Receiving water impaired303(D) Listed
SubwatershedPayette Lake (HUC 170501230106)

NPDES IDR10C1QT: effluent limits and exceedances

DAWSON TRAILS (OPERATOR) (NPDES IDR10C1QT): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.

NPDES IDR10C1QT: no pollutant row on file.

NPDES IDR10C1QT: inspections, violations and enforcement

NPDES IDR10C1QT: 7 single-event violations

DateWhat EPA recordedAgency
April 13, 2026WW Storm Water Construction - Failure to develop any or adequate SWPPP/SWMPST6
April 13, 2026WW Storm Water Construction - Failure to Maintain RecordsST6
April 13, 2026WW Storm Water Construction - Failure to properly install/implement BMPsST6
April 11, 2026WW Storm Water Construction - Failure to Conduct InspectionsST6
April 10, 2026WW Storm Water Construction - Failure to Conduct InspectionsST6
April 9, 2026WW Storm Water Construction - Failure to Conduct InspectionsST6
April 8, 2026WW Storm Water Construction - Failure to Conduct InspectionsST6

NPDES IDR10C1QT: 1 inspection

DateWhat EPA recordedAgency
April 13, 2026EvaluationS

NPDES IDR10C1QT (DAWSON TRAILS (OPERATOR)): no formal enforcement action and informal enforcement action on file.

Watch NPDES IDR10C1QT

NPDES IDR10C1QT: one email when its EPA record changes — $99/month.

Billing

Privacy

Permits near NPDES IDR10C1QT

NPDES IDR10C1QT: 0 pollutant rows, 8 dated events; ICIS-NPDES download, loaded September 15, 2026.