NPDES SDR10P5OK · Clean Water Act
DGR ENGINEERING SIOUX FALLS OFFICE EXPANSION, Sioux Falls, SD: NPDES SDR10P5OK discharge permit, effluent exceedances, inspections, penalties
DGR ENGINEERING SIOUX FALLS OFFICE EXPANSION, Sioux Falls, South Dakota: General permit coverage SDR10P5OK, held by DGR Engineering; Construction stormwater; Effective; issued August 4, 2025, term to October 31, 2028, by SDDANR.
- September 24, 2026: Evaluation (S).
South Dakota holds 1,358 Construction stormwater coverages of this permit type in EPA’s file; 918 were issued before SDR10P5OK. DGR Engineering holds 3 permits in South Dakota.
Other permits held by DGR Engineering
- IRENE WATER STORAGE IMPROVEMENTS, Irene: SDR10P506, issued 2023-11-14
- STREET & UTILITY IMPROVEMENTS - PHASE 3, Chancellor: SDR10P51K, issued 2024-01-10
Coverages issued nearest SDR10P5OK
- 2025-08-01: VIBORG - DAKOTA AVE & JORGENSEN ST IMPROVEMENTS, Viborg: SDR10P5NZ, held by City of Viborg
- 2025-08-01: WONDERLAND DRIVE AREA STREET & UTILITY RECONSTRUCTION - PH 1 (2609), Rapid City: SDR10P5O0, held by City of Rapid City
- 2025-08-01: SOUTH DEUEL WIND, Brandt: SDR10P5OG, held by Rachel Contracting
- 2025-08-01: CLEAR LAKE PHASE 1 WATERMAIN & STORM SEWER, Clear Lake: SDR10P5OH, held by City of Clear Lake
- 2025-08-02: PCN 08WE, Salem: SDR10P5OE, held by SD Department of Transportation
- 2025-08-18: SWO LAW ENFORCEMENT CENTER, Agency Village: SDR10I046, held by Comstock Construction, Inc.
- 2025-08-22: CHEYENNE BLVD / WEST GATE ROAD SEWER EXTENSION, Box Elder: SDR10P5NK, held by Mainline Contracting
- 2025-08-22: CIRCLE K STORES LLC - SIOUX FALLS, Sioux Falls: SDR10P5O6, held by Holiday StationStores Inc
- 2025-08-22: WINDRIVER, Piedmont: SDR10P5O9, held by HD Enterprises LLC
- 2025-08-22: LAKE NORDEN CUL-DE-SAC IMPROVEMENTS, Lake Norden: SDR10P5OC, held by City of Lake Norden
DGR ENGINEERING SIOUX FALLS OFFICE EXPANSION among its neighbors
97 discharge permits are in the Cactus Hills-Big Sioux River subwatershed (HUC 101702031705); SDR10P5OK is one.
Other permits in the Cactus Hills-Big Sioux River subwatershed (HUC 101702031705)
- 2025 CINDER AND LIME SLURRY PONDS CLOSURE BY REMOVAL, Sioux Falls: SDR10P5PU, minor, term to 2028-10-31
- ALIBI BAR, Sioux Falls: SDR10K703, minor, term to 2023-03-31
- ARROWHEAD PARKWAY PHASE 2B @ VETERANS PARKWAY, Sioux Falls: SDR10P5ET, minor, term to 2028-10-31
- ASPEN HARBOR ADDITION, Brandon: SDR10I075, minor, term to 2023-03-31
- BIG SIOUX RECREATION OUTLET IMPROVEMENT, Brandon: SDR10P5A4, minor, term to 2028-10-31
- BRANDON CORE AREA RECONSTRUCTION, PHASE 2B, Brandon: SDR10P5A2, minor, term to 2028-10-31
- BRANDON WTP EXPANSION, Brandon: SDR10K836, minor, term to 2023-03-31
- BRANDON, CITY OF (WTP), Brandon: SDG860074, minor, term to 2021-09-30
- BURNSFIELD ADDITION, Sioux Falls: SDR10K395, minor, term to 2023-03-31
- BURWELL SITE, Sioux Falls: SDR10K864, minor, term to 2023-03-31
What stands out
- Its term runs 3 years and 88 days, August 4, 2025 to October 31, 2028.
- Its newest dated event on file is an inspection on September 24, 2026.
- No dated event in the 365 days to September 15, 2026.
- EPA's file dates 1 event for it, all in 2026.
- It is one of 2,151 discharge permits on the register in South Dakota; 1,370 of them (64%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | DGR ENGINEERING SIOUX FALLS OFFICE EXPANSION |
|---|---|
| Permittee | DGR Engineering |
| NPDES ID | SDR10P5OK |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | August 4, 2025 |
| Expires | October 31, 2028 |
| Agency | SDDANR |
| Address | Sioux Falls, SD 57110 |
| Subwatershed | Cactus Hills-Big Sioux River (HUC 101702031705) |
NPDES SDR10P5OK: effluent limits and exceedances
DGR ENGINEERING SIOUX FALLS OFFICE EXPANSION (NPDES SDR10P5OK): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES SDR10P5OK: no pollutant row on file.
NPDES SDR10P5OK: inspections, violations and enforcement
NPDES SDR10P5OK: 1 inspection
| Date | What EPA recorded | Agency |
|---|---|---|
| September 24, 2026 | Evaluation | S |
NPDES SDR10P5OK (DGR ENGINEERING SIOUX FALLS OFFICE EXPANSION): no single-event violation, formal enforcement action and informal enforcement action on file.
Watch NPDES SDR10P5OK
NPDES SDR10P5OK: one email when its EPA record changes — $99/month.
Permits near NPDES SDR10P5OK
NPDES SDR10P5OK: 0 pollutant rows, 1 dated events; ICIS-NPDES download, loaded September 15, 2026.