| Permit holder | NPDES ID | City | State | Program | Discharger | Receiving water |
|---|---|---|---|---|---|---|
| 171 HARRISON ROAD | GAR18C0CD | MONROE | GA | Construction stormwater | Minor | Upper Hard Labor Creek |
| 189 HARRISON ROAD | GAR18C0EE | MONROE | GA | Construction stormwater | Minor | Upper Hard Labor Creek |
| EASTSIDE WALK AKA SUGAR MILL CREEK | GAR341951 | ATLANTA | GA | Construction stormwater | Minor | Upper Hard Labor Creek |
| GLENAIRE SUBDIVISION | GAR342907 | ATLANTA | GA | Construction stormwater | Minor | Upper Hard Labor Creek |
| HARD LABOR CREEK WATER TRANSMISSION MAIN - PHASE 1 | GAR2544BC | SOCIAL CIRCLE | GA | Construction stormwater | Minor | Upper Hard Labor Creek |
| HARD LABOR CREEK WATER TRANSMISSION MAIN - PHASE 2 | GAR254512 | MONROE | GA | Construction stormwater | Minor | Upper Hard Labor Creek |
| HARD LABOR CREEK WATER TREATMENT FACILITY | GAR18B447 | SOCIAL CIRCLE | GA | Construction stormwater | Minor | Upper Hard Labor Creek |
| MAHLON SMITH CONTRACTOR STORAGE | GAR18B48B | SOCIAL CIRLCE | GA | Construction stormwater | Minor | Upper Hard Labor Creek |
| MIDDLE SCHOOL #1 | GAU030776 | MONROE | GA | Minor | Upper Hard Labor Creek | |
| PROPOSED WORSHIP FACILITY FOR THE GREATER PINEY GROVE BAPTIST CHURCH | GAR142974 | ATLANTA | GA | Construction stormwater | Minor | Upper Hard Labor Creek |
| SPRINGS AT WALTON | GAR3974B6 | MONROE | GA | Construction stormwater | Minor | Upper Hard Labor Creek |
| TILSON FOREST SUBDIVISION | GAR106525 | DECATUR | GA | Construction stormwater | Minor | Upper Hard Labor Creek |