Follow this watershed Velarion Records emails you this watershed’s record, cited to the public filing, and tells you when the register changes it. Free.One more press on the next page sends it; there is no link to click in an email. The continuous daily watch on every change is the paid alert. Unsubscribe any time.
EPA · discharge permits by watershed
Yellow Creek-Etowah River (subwatershed 031501040303)
- 22Current permits
- 2States
A subwatershed is a unit of the national Watershed Boundary Dataset, and water crosses state lines: this one carries permits in Georgia, Florida. Each permit is placed by the outfall EPA names as its representative discharge point.
This subwatershed carries permits in 2 states. The table below is a sample of the 22 current permits recorded here
By state
Other subwatersheds
- Yellow Creek 16
- Brewton Creek 47
- Upper Settingdown Creek 255
- Lower Settingdown Creek 152
- Board Tree Creek-Etowah River 58
Permits discharging here
| Permit holder | NPDES ID | City | State | Program | Discharger | Receiving water | Status and term |
|---|---|---|---|---|---|---|---|
| 221 ETOWAH | GAR18ACE6 | BALL GROUND | GA | Construction stormwater | Minor | Yellow Creek-Etowah River | Effective, 2023-08-01 to 2028-07-31 |
| CLEAN EAGLE RENEWABLE NATURAL GAS FACILITY | GAR153E52 | BALL GROUND | GA | Construction stormwater | Minor | Yellow Creek-Etowah River | Administratively continued, 2013-09-24 to 2018-07-31 |
| EAGLE POINT BORROW AREA | GAIS12652 | BALL GROUND | GA | Industrial stormwater | Minor | Yellow Creek-Etowah River | Administratively continued, 2012-06-01 to 2017-05-31 |
| EAGLE POINT LANDFILL - CONSTRUCTION OF CELL NO. 13 | GAR149238 | PONTE VERDA | FL | Construction stormwater | Minor | Yellow Creek-Etowah River | Effective, 2013-09-23 to 2018-07-31 |
| EAGLE POINT LANDFILL - CONSTRUCTION OF CELL NO. 15 | GAR153C1A | BALL GROUND | GA | Construction stormwater | Minor | Yellow Creek-Etowah River | Administratively continued, 2013-09-24 to 2018-07-31 |
| EAGLE POINT LANDFILL- MAINT SHOP | GAIS03923 | BALL GROUND | GA | Industrial stormwater | Minor | Yellow Creek-Etowah River | Administratively continued, 2012-06-01 to 2017-05-31 |
| EAGLES BEAK PARK | GAR152085 | BALL GROUND | GA | Construction stormwater | Minor | Yellow Creek-Etowah River | Effective, 2013-09-23 to 2018-07-31 |
| ETOWAH LANDING PHASE 1 | GAR396609 | BALL GROUND | GA | Construction stormwater | Minor | Yellow Creek-Etowah River | Effective, 2023-08-01 to 2028-07-31 |
| ETOWAH LANDING PHASE 2 | GAR39660A | BALL GROUND | GA | Construction stormwater | Minor | Yellow Creek-Etowah River | Effective, 2023-08-01 to 2028-07-31 |
| ETOWAH LANDING ROAD WORK | GAR3966A4 | BALL GROUND | GA | Construction stormwater | Minor | Yellow Creek-Etowah River | Effective, 2023-08-01 to 2028-07-31 |
| FIRST BAPTIST CHURCH OF TOCCOA - 475 E. TUGALO STREET | GAR148475 | TOCCOA | GA | Construction stormwater | Minor | Yellow Creek-Etowah River | Effective, 2013-09-23 to 2018-07-31 |
| HVC LAND LLC PHASE II FKA PHASE I | GAR149156 | CUMMING | GA | Construction stormwater | Minor | Yellow Creek-Etowah River | Effective, 2013-09-23 to 2018-07-31 |
| LOT 25A - WOODHAVEN BEND SUBDIVISION | GAR396F4E | BALL GROUND | GA | Construction stormwater | Minor | Yellow Creek-Etowah River | Effective, 2023-08-01 to 2028-07-31 |
| RIVER ROCK LOT 23 | GAR371162 | BALL GROUND | GA | Construction stormwater | Minor | Yellow Creek-Etowah River | Administratively continued, 2013-09-23 to 2018-07-31 |
| RIVER ROCK LOT 25 | GAR371157 | BALL GROUND | GA | Construction stormwater | Minor | Yellow Creek-Etowah River | Administratively continued, 2013-09-23 to 2018-07-31 |
| RIVER ROCK LOT 4 | GAR371159 | BALL GROUND | GA | Construction stormwater | Minor | Yellow Creek-Etowah River | Effective, 2013-09-23 to 2018-07-31 |
| RIVER ROCK LOT 77 | GAR371156 | BALL GROUND | GA | Construction stormwater | Minor | Yellow Creek-Etowah River | Effective, 2013-09-23 to 2018-07-31 |
| RIVER ROCK LOT 79 | GAR371155 | BALL GROUND | GA | Construction stormwater | Minor | Yellow Creek-Etowah River | Effective, 2013-09-23 to 2018-07-31 |
| RIVER ROCK; HWY. 369 - PHASE IB, LOT 20 | GAR362935 | UNKNOWN | GA | Construction stormwater | Minor | Yellow Creek-Etowah River | Effective, 2013-09-23 to 2018-07-31 |
| RIVERBEND GUN CLUB - THE .22 CAL. RIMFIRE RIFLE RANGE | GAR148225 | DAWSONVILLE | GA | Construction stormwater | Minor | Yellow Creek-Etowah River | Effective, 2013-09-23 to 2018-07-31 |
| STEVEN WHITECROSS | GAR3968CC | ELLIJAY | GA | Construction stormwater | Minor | Yellow Creek-Etowah River | Effective, 2023-08-01 to 2028-07-31 |
| WOODHAVEN BEND - LOT 11 | GAR18B8C0 | BALL GROUND | GA | Construction stormwater | Minor | Yellow Creek-Etowah River | Effective, 2023-08-01 to 2028-07-31 |
What this page shows
This page covers Clean Water Act discharge permits in the Yellow Creek-Etowah River watershed, code 031501040303. It lists 22 permits on this page, with 21 permits in the whole watershed located in GA and 1 in FL.