Air-emissions inspections in Freestone County, Texas, 2017
- 12Inspections
A compliance evaluation is the on-site or file review a state, local or federal air agency records against a permitted source. Each row below is one inspection recorded against a source in Freestone County, Texas during 2017. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Freestone County facility page.
Freestone County, Texas, 2017
- Stack tests 17
Air-emissions inspections in Freestone County, other years
Air-emissions inspections recorded in Freestone County, Texas, 2017
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2017-12-19 | TEAGUE PLANT | FCE Off-Site | State |
| 2017-12-19 | TEAGUE SWEET AND SOUR COMPRESSOR STATION | FCE Off-Site | State |
| 2017-11-14 | AKER PLANT | FCE Off-Site | State |
| 2017-09-27 | PLUM CREEK TREATING FACILITY | FCE Off-Site | State |
| 2017-06-22 | DEW CENTRAL GATHERING FACILITY | FCE On-Site | State |
| 2017-06-14 | DOWDY RANCH CENTRAL GATHERING FACILITY | FCE Off-Site | State |
| 2017-06-14 | BUFFALO CENTRAL GATHERING FACILITY | FCE Off-Site | State |
| 2017-06-05 | TEAGUE SWEET AND SOUR COMPRESSOR STATION | FCE On-Site | State |
| 2017-05-23 | BIG BROWN STEAM ELECTRIC STATION — high-priority violation on file | FCE On-Site | State |
| 2017-05-23 | FREESTONE POWER GENERATION | FCE On-Site | State |
| 2017-04-04 | ENERGY TRANSFER FUEL REED COMPRESSOR STATION | FCE Off-Site | State |
| 2017-02-01 | TEAGUE PLANT | FCE On-Site | State |
Dates as filed by the agency that recorded the inspection. Figures from EPA’s ICIS-AIR download.
What this page shows
This page covers Clean Air Act facilities in the EPA air register, inspections and evaluations in Freestone county, TX, for 2017. Inspections and evaluations recorded in 2017: 12.