EPA Air · stack tests by county and year
Air-emissions stack tests in Placer County, California, 2018
- 14Stack tests
A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row below is one stack test recorded against a source in Placer County, California during 2018. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Placer County facility page.
Placer County, California, 2018
- Inspections 25
Air-emissions stack tests in Placer County, other years
Air-emissions stack tests recorded in Placer County, California, 2018
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2018-12-10 | WESTERN REGIONAL LANDFILL | Pass | Local |
| 2018-11-29 | ENERGY 2001 | Pass | Local |
| 2018-10-10 | CITY OF ROSEVILLE POWER PLANT#2 | Pass | Local |
| 2018-09-18 | WESTERN REGIONAL LANDFILL | Pass | Local |
| 2018-08-28 | ROSEVILLE ELECTRIC, ENERGY PARK | Pass | Local |
| 2018-07-26 | SPI - LINCOLN — high-priority violation on file | Pass | Local |
| 2018-06-13 | RIO BRAVO - ROCKLIN | Pass | Local |
| 2018-06-01 | WESTERN REGIONAL LANDFILL | Pass | Local |
| 2018-05-09 | ENERGY 2001 | Pass | Local |
| 2018-05-08 | WESTERN REGIONAL LANDFILL | Pass | Local |
| 2018-03-30 | GLADDING MCBEAN CO. (PABCO) | Pending | Local |
| 2018-03-19 | WESTERN REGIONAL LANDFILL | Pass | Local |
| 2018-02-06 | WESTERN REGIONAL LANDFILL | Pass | Local |
| 2018-01-30 | SPI - LINCOLN — high-priority violation on file | Pass | Local |
Dates as filed by the agency that recorded the stack test. Figures from EPA’s ICIS-AIR download.