Air-emissions stack tests in Orange County, Florida, 2023
- 32Stack tests
A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row below is one stack test recorded against a source in Orange County, Florida during 2023. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Orange County facility page.
Orange County, Florida, 2023
Air-emissions stack tests in Orange County, other years
Air-emissions stack tests recorded in Orange County, Florida, 2023
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2023-12-04 | ORLANDO UTILITIES COMMISSION | Pass | State |
| 2023-10-17 | ORLANDO UTILITIES COMMISSION | Pass | State |
| 2023-08-02 | ORLANDO UTILITIES COMMISSION | Pass | State |
| 2023-08-01 | ORLANDO UTILITIES COMMISSION | Pass | State |
| 2023-07-25 | MIDDLESEX ASPHALT LLC | Pass | State |
| 2023-07-20 | FLORIDA GAS TRANSMISSION COMPANY | Pass | State |
| 2023-07-20 | FLORIDA GAS TRANSMISSION COMPANY | Pass | State |
| 2023-07-20 | FLORIDA GAS TRANSMISSION COMPANY | Pass | State |
| 2023-07-20 | FLORIDA GAS TRANSMISSION COMPANY | Pass | State |
| 2023-07-20 | FLORIDA GAS TRANSMISSION COMPANY | Pass | State |
| 2023-07-20 | FLORIDA GAS TRANSMISSION COMPANY | Pass | State |
| 2023-06-27 | ORLANDO UTILITIES COMMISSION | Pass | State |
| 2023-06-01 | INDUSTRIAL CONTAINER SERVICES - FL, LLC | Pass | State |
| 2023-05-12 | ORLANDO UTILITIES COMMISSION | Pass | State |
| 2023-05-12 | ORLANDO UTILITIES COMMISSION | Pass | State |
| 2023-05-11 | ORLANDO UTILITIES COMMISSION | Pass | State |
| 2023-05-11 | ORLANDO UTILITIES COMMISSION | Pass | State |
| 2023-05-11 | FLORIDA MUNICIPAL POWER AGENCY — high-priority violation on file | Pass | State |
| 2023-05-11 | FLORIDA MUNICIPAL POWER AGENCY — high-priority violation on file | Pass | State |
| 2023-04-19 | NEXTERA ENERGY | Pass | State |
| 2023-04-18 | NEXTERA ENERGY | Pass | State |
| 2023-02-14 | ORLANDO UTILITIES COMMISSION | Pass | State |
| 2023-02-14 | STERICYCLE, INC | Pass | State |
| 2023-02-14 | STERICYCLE, INC | Pass | State |
| 2023-02-14 | STERICYCLE, INC | Pass | State |
| 2023-02-14 | STERICYCLE, INC | Pass | State |
| 2023-02-14 | STERICYCLE, INC | Pass | State |
| 2023-01-31 | ORLANDO PAVING COMPANY | Pass | State |
| 2023-01-17 | UNIVERSITY OF CENTRAL FLORIDA | Pass | State |
| 2023-01-17 | UNIVERSITY OF CENTRAL FLORIDA | Pass | State |
| 2023-01-17 | UNIVERSITY OF CENTRAL FLORIDA | Pass | State |
| 2023-01-13 | ORLANDO UTILITIES COMMISSION | Pass | State |
Dates as filed by the agency that recorded the stack test. Figures from EPA’s ICIS-AIR download.