A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row below is one stack test recorded against a source in Cobb County, Georgia during 2021. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Cobb County facility page.
Cobb County, Georgia, 2021
- Inspections 62
Air-emissions stack tests in Cobb County, other years
Air-emissions stack tests recorded in Cobb County, Georgia, 2021
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2021-11-23 | CARAUSTAR INDUSTRIES, INC. | Pass | State |
| 2021-11-23 | CARAUSTAR INDUSTRIES, INC. | Pass | State |
| 2021-11-23 | CARAUSTAR INDUSTRIES, INC. | Pass | State |
| 2021-11-23 | CARAUSTAR INDUSTRIES, INC. | Pass | State |
| 2021-10-26 | GEORGIA POWER CO. - PLANT MCDONOUGH- ATKINSON | Pass | State |
| 2021-10-25 | GEORGIA POWER CO. - PLANT MCDONOUGH- ATKINSON | Pass | State |
| 2021-10-22 | GEORGIA POWER CO. - PLANT MCDONOUGH- ATKINSON | Pass | State |
| 2021-10-21 | GEORGIA POWER CO. - PLANT MCDONOUGH- ATKINSON | Pass | State |
| 2021-10-20 | GEORGIA POWER CO. - PLANT MCDONOUGH- ATKINSON | Pass | State |
| 2021-10-20 | GEORGIA POWER CO. - PLANT MCDONOUGH- ATKINSON | Pass | State |
| 2021-10-20 | GEORGIA POWER CO. - PLANT MCDONOUGH- ATKINSON | Pass | State |
| 2021-10-20 | GEORGIA POWER CO. - PLANT MCDONOUGH- ATKINSON | Pass | State |
| 2021-10-19 | GEORGIA POWER CO. - PLANT MCDONOUGH- ATKINSON | Pass | State |
| 2021-10-18 | GEORGIA POWER CO. - PLANT MCDONOUGH- ATKINSON | Pass | State |
| 2021-10-13 | GEORGIA POWER CO. - PLANT MCDONOUGH- ATKINSON | Pass | State |
| 2021-10-13 | GEORGIA POWER CO. - PLANT MCDONOUGH- ATKINSON | Pass | State |
| 2021-10-13 | GEORGIA POWER CO. - PLANT MCDONOUGH- ATKINSON | Pass | State |
| 2021-10-13 | GEORGIA POWER CO. - PLANT MCDONOUGH- ATKINSON | Pass | State |
| 2021-10-11 | GEORGIA POWER CO. - PLANT MCDONOUGH- ATKINSON | Pass | State |
| 2021-10-11 | GEORGIA POWER CO. - PLANT MCDONOUGH- ATKINSON | Pass | State |
| 2021-10-11 | GEORGIA POWER CO. - PLANT MCDONOUGH- ATKINSON | Pass | State |
| 2021-10-11 | GEORGIA POWER CO. - PLANT MCDONOUGH- ATKINSON | Pass | State |
| 2021-04-14 | GEORGIA POWER CO. - PLANT MCDONOUGH- ATKINSON | Pass | State |
| 2021-04-14 | GEORGIA POWER CO. - PLANT MCDONOUGH- ATKINSON | Pass | State |
| 2021-04-14 | GEORGIA POWER CO. - PLANT MCDONOUGH- ATKINSON | Pass | State |
| 2021-04-14 | GEORGIA POWER CO. - PLANT MCDONOUGH- ATKINSON | Pass | State |
| 2021-03-25 | LOCKHEED MARTIN AERONAUTICS CO. | Pass | State |
| 2021-03-24 | LOCKHEED MARTIN AERONAUTICS CO. | Pass | State |
| 2021-03-24 | LOCKHEED MARTIN AERONAUTICS CO. | Pass | State |
| 2021-03-23 | LOCKHEED MARTIN AERONAUTICS CO. | Pass | State |
| 2021-03-23 | LOCKHEED MARTIN AERONAUTICS CO. | Pass | State |
| 2021-03-22 | LOCKHEED MARTIN AERONAUTICS CO. | Pass | State |
| 2021-03-22 | LOCKHEED MARTIN AERONAUTICS CO. | Pass | State |
| 2021-03-19 | LOCKHEED MARTIN AERONAUTICS CO. | Pass | State |
| 2021-03-18 | LOCKHEED MARTIN AERONAUTICS CO. | Pass | State |
| 2021-03-17 | LOCKHEED MARTIN AERONAUTICS CO. | Pass | State |
| 2021-03-16 | LOCKHEED MARTIN AERONAUTICS CO. | Pass | State |
| 2021-01-14 | CONCORDE/INTERSPACE BATTERY GEORGIA CORPORATION | Pass | State |
| 2021-01-13 | CONCORDE/INTERSPACE BATTERY GEORGIA CORPORATION | Pass | State |
| 2021-01-12 | CONCORDE/INTERSPACE BATTERY GEORGIA CORPORATION | Pass | State |
| 2021-01-12 | CONCORDE/INTERSPACE BATTERY GEORGIA CORPORATION | Pass | State |