A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row below is one stack test recorded against a source in Houston County, Georgia during 2022. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Houston County facility page.
Houston County, Georgia, 2022
- Inspections 49
Air-emissions stack tests in Houston County, other years
Air-emissions stack tests recorded in Houston County, Georgia, 2022
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2022-12-13 | CEMEX SOUTHEAST, LLC | Pass | State |
| 2022-10-19 | REAMES CONCRETE COMPANY - PERRY PLANT | Pass | State |
| 2022-10-19 | REAMES CONCRETE COMPANY - PERRY PLANT | Pass | State |
| 2022-09-28 | ANCHOR GLASS CONTAINER CORPORATION - WARNER ROBINS PLANT — high-priority violation on file | Pass | State |
| 2022-09-28 | ANCHOR GLASS CONTAINER CORPORATION - WARNER ROBINS PLANT — high-priority violation on file | Pass | State |
| 2022-09-28 | ANCHOR GLASS CONTAINER CORPORATION - WARNER ROBINS PLANT — high-priority violation on file | Pass | State |
| 2022-09-09 | CEMEX SOUTHEAST, LLC | Pass | State |
| 2022-09-09 | CEMEX SOUTHEAST, LLC | Pass | State |
| 2022-09-07 | CEMEX SOUTHEAST, LLC | Pass | State |
| 2022-09-07 | CEMEX SOUTHEAST, LLC | Pass | State |
| 2022-09-07 | CEMEX SOUTHEAST, LLC | Pass | State |
| 2022-09-07 | CEMEX SOUTHEAST, LLC | Pass | State |
| 2022-09-07 | CEMEX SOUTHEAST, LLC | Pass | State |
| 2022-09-07 | CEMEX SOUTHEAST, LLC | Pass | State |
| 2022-09-07 | CEMEX SOUTHEAST, LLC | Pass | State |
| 2022-09-07 | CEMEX SOUTHEAST, LLC | Pass | State |
| 2022-09-07 | CEMEX SOUTHEAST, LLC | Pass | State |
| 2022-08-09 | CEMEX SOUTHEAST, LLC | Pass | State |
| 2022-08-03 | MID-GEORGIA COGEN LP | Pass | State |
| 2022-08-02 | MID-GEORGIA COGEN LP | Pass | State |
| 2022-08-02 | MID-GEORGIA COGEN LP | Pass | State |
| 2022-05-12 | CG PS HOUSTON, LLC | Pass | State |
| 2022-05-12 | CG PS HOUSTON, LLC | Pass | State |
| 2022-05-12 | CG PS HOUSTON, LLC | Pass | State |
| 2022-05-12 | CG PS HOUSTON, LLC | Pass | State |
| 2022-05-12 | CG PS HOUSTON, LLC | Pass | State |
| 2022-05-12 | CG PS HOUSTON, LLC | Pass | State |
| 2022-04-20 | INTERFOR U.S. INC. - PERRY MILL — high-priority violation on file | Pass | State |
| 2022-04-20 | INTERFOR U.S. INC. - PERRY MILL — high-priority violation on file | Pass | State |
| 2022-04-20 | INTERFOR U.S. INC. - PERRY MILL — high-priority violation on file | Pass | State |
| 2022-04-20 | INTERFOR U.S. INC. - PERRY MILL — high-priority violation on file | Pass | State |
| 2022-04-19 | INTERFOR U.S. INC. - PERRY MILL — high-priority violation on file | Pass | State |
| 2022-04-19 | INTERFOR U.S. INC. - PERRY MILL — high-priority violation on file | Pass | State |
| 2022-04-19 | INTERFOR U.S. INC. - PERRY MILL — high-priority violation on file | Pass | State |
| 2022-04-19 | INTERFOR U.S. INC. - PERRY MILL — high-priority violation on file | Pass | State |
| 2022-04-19 | INTERFOR U.S. INC. - PERRY MILL — high-priority violation on file | Pass | State |
| 2022-04-19 | INTERFOR U.S. INC. - PERRY MILL — high-priority violation on file | Pass | State |
| 2022-04-19 | INTERFOR U.S. INC. - PERRY MILL — high-priority violation on file | Pass | State |
| 2022-04-19 | INTERFOR U.S. INC. - PERRY MILL — high-priority violation on file | Pass | State |
| 2022-03-18 | CEMEX SOUTHEAST, LLC | Pass | State |
| 2022-03-18 | CEMEX SOUTHEAST, LLC | Pass | State |