EPA Air · stack tests by county and year
Air-emissions stack tests in Wilkinson County, Georgia, 2021
- 22Stack tests
A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row below is one stack test recorded against a source in Wilkinson County, Georgia during 2021. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Wilkinson County facility page.
Wilkinson County, Georgia, 2021
Air-emissions stack tests in Wilkinson County, other years
Air-emissions stack tests recorded in Wilkinson County, Georgia, 2021
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2021-12-03 | CARBO CERAMICS, INC. - MCINTYRE PLANT — high-priority violation on file | Pass | State |
| 2021-12-03 | CARBO CERAMICS, INC. - MCINTYRE PLANT — high-priority violation on file | Pass | State |
| 2021-12-03 | CARBO CERAMICS, INC. - MCINTYRE PLANT — high-priority violation on file | Pass | State |
| 2021-12-03 | CARBO CERAMICS, INC. - MCINTYRE PLANT — high-priority violation on file | Pass | State |
| 2021-12-01 | CARBO CERAMICS, INC. - MCINTYRE PLANT — high-priority violation on file | Pass | State |
| 2021-12-01 | CARBO CERAMICS, INC. - MCINTYRE PLANT — high-priority violation on file | Pass | State |
| 2021-12-01 | CARBO CERAMICS, INC. - MCINTYRE PLANT — high-priority violation on file | Pass | State |
| 2021-12-01 | CARBO CERAMICS, INC. - MCINTYRE PLANT — high-priority violation on file | Pass | State |
| 2021-11-30 | CARBO CERAMICS, INC. - MCINTYRE PLANT — high-priority violation on file | Pass | State |
| 2021-11-30 | CARBO CERAMICS, INC. - MCINTYRE PLANT — high-priority violation on file | Pass | State |
| 2021-11-30 | CARBO CERAMICS, INC. - MCINTYRE PLANT — high-priority violation on file | Pass | State |
| 2021-05-25 | BASF CORPORATION, EDGAR PLANT | Pass | State |
| 2021-05-25 | BASF CORPORATION, EDGAR PLANT | Pass | State |
| 2021-05-12 | CARBO CERAMICS, INC. - MCINTYRE PLANT — high-priority violation on file | Pass | State |
| 2021-05-12 | CARBO CERAMICS, INC. - MCINTYRE PLANT — high-priority violation on file | Pass | State |
| 2021-05-12 | CARBO CERAMICS, INC. - MCINTYRE PLANT — high-priority violation on file | Pass | State |
| 2021-05-12 | CARBO CERAMICS, INC. - MCINTYRE PLANT — high-priority violation on file | Pass | State |
| 2021-05-11 | CARBO CERAMICS, INC. - MCINTYRE PLANT — high-priority violation on file | Pass | State |
| 2021-05-11 | CARBO CERAMICS, INC. - MCINTYRE PLANT — high-priority violation on file | Pass | State |
| 2021-05-11 | CARBO CERAMICS, INC. - MCINTYRE PLANT — high-priority violation on file | Pass | State |
| 2021-05-11 | CARBO CERAMICS, INC. - MCINTYRE PLANT — high-priority violation on file | Pass | State |
| 2021-05-11 | CARBO CERAMICS, INC. - MCINTYRE PLANT — high-priority violation on file | Pass | State |
Dates as filed by the agency that recorded the stack test. Figures from EPA’s ICIS-AIR download.