EPA Air · stack tests by county and year
Air-emissions stack tests in Allen County, Indiana, 2021
- 41Stack tests
A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row below is one stack test recorded against a source in Allen County, Indiana during 2021. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Allen County facility page.
Allen County, Indiana, 2021
Air-emissions stack tests in Allen County, other years
Air-emissions stack tests recorded in Allen County, Indiana, 2021
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2021-11-18 | WAYNE ASPHALT & CONSTRUCTION CO INC | Pass | State |
| 2021-11-18 | WAYNE ASPHALT & CONSTRUCTION CO INC | Pass | State |
| 2021-11-18 | WAYNE ASPHALT & CONSTRUCTION CO INC | Pass | State |
| 2021-11-18 | WAYNE ASPHALT & CONSTRUCTION CO INC | Pass | State |
| 2021-08-24 | HEIDELBERG MATERIALS MIDWEST AGG INCORPORATED | Pass | State |
| 2021-08-24 | HEIDELBERG MATERIALS MIDWEST AGG INCORPORATED | Pass | State |
| 2021-08-24 | HEIDELBERG MATERIALS MIDWEST AGG INCORPORATED | Pass | State |
| 2021-08-24 | HEIDELBERG MATERIALS MIDWEST AGG INCORPORATED | Pass | State |
| 2021-08-24 | HEIDELBERG MATERIALS MIDWEST AGG INCORPORATED | Pass | State |
| 2021-08-23 | HEIDELBERG MATERIALS MIDWEST AGG INCORPORATED | Pass | State |
| 2021-08-23 | HEIDELBERG MATERIALS MIDWEST AGG INCORPORATED | Pass | State |
| 2021-08-23 | HEIDELBERG MATERIALS MIDWEST AGG INCORPORATED | Pass | State |
| 2021-08-23 | HEIDELBERG MATERIALS MIDWEST AGG INCORPORATED | Pass | State |
| 2021-08-23 | HEIDELBERG MATERIALS MIDWEST AGG INCORPORATED | Pass | State |
| 2021-08-23 | HEIDELBERG MATERIALS MIDWEST AGG INCORPORATED | Pass | State |
| 2021-08-23 | HEIDELBERG MATERIALS MIDWEST AGG INCORPORATED | Pass | State |
| 2021-08-23 | HEIDELBERG MATERIALS MIDWEST AGG INCORPORATED | Pass | State |
| 2021-08-23 | HEIDELBERG MATERIALS MIDWEST AGG INCORPORATED | Pass | State |
| 2021-08-23 | HEIDELBERG MATERIALS MIDWEST AGG INCORPORATED | Pass | State |
| 2021-05-11 | SDI LAFARGA, LLC | Pass | State |
| 2021-05-06 | SUPERIOR ALUMINUM ALLOYS LLC — high-priority violation on file | Pass | State |
| 2021-05-06 | SUPERIOR ALUMINUM ALLOYS LLC — high-priority violation on file | Pass | State |
| 2021-05-06 | SUPERIOR ALUMINUM ALLOYS LLC — high-priority violation on file | Pass | State |
| 2021-05-06 | SUPERIOR ALUMINUM ALLOYS LLC — high-priority violation on file | Pass | State |
| 2021-05-06 | SUPERIOR ALUMINUM ALLOYS LLC — high-priority violation on file | Pass | State |
| 2021-05-06 | SUPERIOR ALUMINUM ALLOYS LLC — high-priority violation on file | Pass | State |
| 2021-05-06 | SUPERIOR ALUMINUM ALLOYS LLC — high-priority violation on file | Pass | State |
| 2021-05-05 | SUPERIOR ALUMINUM ALLOYS LLC — high-priority violation on file | Pass | State |
| 2021-05-05 | SUPERIOR ALUMINUM ALLOYS LLC — high-priority violation on file | Pass | State |
| 2021-05-05 | SUPERIOR ALUMINUM ALLOYS LLC — high-priority violation on file | Pass | State |
| 2021-05-05 | SUPERIOR ALUMINUM ALLOYS LLC — high-priority violation on file | Pass | State |
| 2021-05-05 | SUPERIOR ALUMINUM ALLOYS LLC — high-priority violation on file | Pass | State |
| 2021-05-05 | SUPERIOR ALUMINUM ALLOYS LLC — high-priority violation on file | Pass | State |
| 2021-05-05 | SUPERIOR ALUMINUM ALLOYS LLC — high-priority violation on file | Pass | State |
| 2021-04-28 | REA MAGNET WIRE COMPANY INCORPORATED | Pass | State |
| 2021-04-27 | REA MAGNET WIRE COMPANY INCORPORATED | Pass | State |
| 2021-02-18 | SDI LAFARGA, LLC | Pass | State |
| 2021-02-18 | SDI LAFARGA, LLC | Pass | State |
| 2021-02-16 | SDI LAFARGA, LLC | Pass | State |
| 2021-02-16 | SDI LAFARGA, LLC | Pass | State |
| 2021-02-16 | SDI LAFARGA, LLC | Pass | State |
Dates as filed by the agency that recorded the stack test. Figures from EPA’s ICIS-AIR download.