EPA Air · stack tests by county and year
Air-emissions stack tests in Rush County, Indiana, 2025
- 44Stack tests
A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row below is one stack test recorded against a source in Rush County, Indiana during 2025. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Rush County facility page.
Rush County, Indiana, 2025
Air-emissions stack tests in Rush County, other years
Air-emissions stack tests recorded in Rush County, Indiana, 2025
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2025-11-18 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-11-18 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-06-30 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-06-30 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-06-30 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-06-30 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-06-30 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-06-30 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-06-30 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-06-30 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-06-11 | INTAT PRECISION INCORPORATED — high-priority violation on file | Fail | State |
| 2025-06-11 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-06-11 | INTAT PRECISION INCORPORATED — high-priority violation on file | Fail | State |
| 2025-06-11 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-06-05 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-06-05 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-04-25 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-04-25 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-04-25 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-04-25 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-04-25 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-04-23 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-04-23 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-04-23 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-04-23 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-04-23 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-04-23 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-04-23 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-04-23 | INTAT PRECISION INCORPORATED — high-priority violation on file | Fail | State |
| 2025-04-22 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-04-22 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-04-22 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-04-22 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-04-22 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-04-22 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-04-22 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-04-22 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-04-22 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-04-22 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-04-22 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-04-22 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-04-22 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-04-22 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
| 2025-04-22 | INTAT PRECISION INCORPORATED — high-priority violation on file | Pass | State |
Dates as filed by the agency that recorded the stack test. Figures from EPA’s ICIS-AIR download.
What this page shows
This page covers Clean Air Act facilities in the EPA air register, with stack tests in Rush county, IN, for 2025. It lists 44 stack tests recorded in 2025.