EPA Air · stack tests by county and year
Air-emissions stack tests in Shelby County, Indiana, 2017
- 18Stack tests
A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row below is one stack test recorded against a source in Shelby County, Indiana during 2017. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Shelby County facility page.
Shelby County, Indiana, 2017
Air-emissions stack tests in Shelby County, other years
Air-emissions stack tests recorded in Shelby County, Indiana, 2017
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2017-10-19 | JUPITER ALUMINUM CORPORATION FAIRLAND COIL COATING | Pass | State |
| 2017-09-20 | BUNGE NORTH AMERICA (EAST), LLC — high-priority violation on file | Pass | State |
| 2017-09-20 | BUNGE NORTH AMERICA (EAST), LLC — high-priority violation on file | Pass | State |
| 2017-09-20 | BUNGE NORTH AMERICA (EAST), LLC — high-priority violation on file | Pass | State |
| 2017-09-19 | BUNGE NORTH AMERICA (EAST), LLC — high-priority violation on file | Pass | State |
| 2017-09-19 | BUNGE NORTH AMERICA (EAST), LLC — high-priority violation on file | Pass | State |
| 2017-08-17 | ANR PIPELINE COMPANY SHELBYVILLE COMPRESSOR STATION | Pass | State |
| 2017-06-01 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2017-06-01 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2017-06-01 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2017-05-31 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2017-05-31 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2017-05-31 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2017-04-13 | ANR PIPELINE COMPANY SHELBYVILLE COMPRESSOR STATION | Pass | State |
| 2017-04-12 | ANR PIPELINE COMPANY SHELBYVILLE COMPRESSOR STATION | Pass | State |
| 2017-04-12 | ANR PIPELINE COMPANY SHELBYVILLE COMPRESSOR STATION | Pass | State |
| 2017-04-11 | ANR PIPELINE COMPANY SHELBYVILLE COMPRESSOR STATION | Pass | State |
| 2017-02-23 | JUPITER ALUMINUM CORPORATION FAIRLAND COIL COATING | Pass | State |
Dates as filed by the agency that recorded the stack test. Figures from EPA’s ICIS-AIR download.