Air-emissions stack tests in Sullivan County, Indiana, 2017
- 31Stack tests
A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row below is one stack test recorded against a source in Sullivan County, Indiana during 2017. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Sullivan County facility page.
Sullivan County, Indiana, 2017
Air-emissions stack tests in Sullivan County, other years
Air-emissions stack tests recorded in Sullivan County, Indiana, 2017
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2017-12-06 | HALLADOR POWER COMPANY LLC MEROM GENERATING STATION — high-priority violation on file | Pass | State |
| 2017-12-06 | HALLADOR POWER COMPANY LLC MEROM GENERATING STATION — high-priority violation on file | Pass | State |
| 2017-12-05 | HALLADOR POWER COMPANY LLC MEROM GENERATING STATION — high-priority violation on file | Pass | State |
| 2017-12-05 | HALLADOR POWER COMPANY LLC MEROM GENERATING STATION — high-priority violation on file | Pass | State |
| 2017-12-05 | HALLADOR POWER COMPANY LLC MEROM GENERATING STATION — high-priority violation on file | Pass | State |
| 2017-12-05 | HALLADOR POWER COMPANY LLC MEROM GENERATING STATION — high-priority violation on file | Pass | State |
| 2017-12-05 | HALLADOR POWER COMPANY LLC MEROM GENERATING STATION — high-priority violation on file | Pass | State |
| 2017-12-05 | HALLADOR POWER COMPANY LLC MEROM GENERATING STATION — high-priority violation on file | Pass | State |
| 2017-12-05 | HALLADOR POWER COMPANY LLC MEROM GENERATING STATION — high-priority violation on file | Pass | State |
| 2017-12-05 | HALLADOR POWER COMPANY LLC MEROM GENERATING STATION — high-priority violation on file | Pass | State |
| 2017-11-02 | RAYBESTOS POWERTRAIN LLC | Pass | State |
| 2017-10-13 | BRICKCRAFT INC — high-priority violation on file | Pass | State |
| 2017-10-13 | BRICKCRAFT INC — high-priority violation on file | Pass | State |
| 2017-10-13 | BRICKCRAFT INC — high-priority violation on file | Pass | State |
| 2017-10-12 | BRICKCRAFT INC — high-priority violation on file | Pass | State |
| 2017-10-12 | BRICKCRAFT INC — high-priority violation on file | Pass | State |
| 2017-10-12 | BRICKCRAFT INC — high-priority violation on file | Pass | State |
| 2017-10-12 | BRICKCRAFT INC — high-priority violation on file | Pass | State |
| 2017-10-12 | BRICKCRAFT INC — high-priority violation on file | Pass | State |
| 2017-08-23 | HALLADOR POWER COMPANY LLC MEROM GENERATING STATION — high-priority violation on file | Pass | State |
| 2017-08-23 | HALLADOR POWER COMPANY LLC MEROM GENERATING STATION — high-priority violation on file | Pass | State |
| 2017-08-22 | HALLADOR POWER COMPANY LLC MEROM GENERATING STATION — high-priority violation on file | Pass | State |
| 2017-08-22 | HALLADOR POWER COMPANY LLC MEROM GENERATING STATION — high-priority violation on file | Pass | State |
| 2017-06-23 | HALLADOR POWER COMPANY LLC MEROM GENERATING STATION — high-priority violation on file | Pass | State |
| 2017-06-23 | HALLADOR POWER COMPANY LLC MEROM GENERATING STATION — high-priority violation on file | Pass | State |
| 2017-04-21 | HALLADOR POWER COMPANY LLC MEROM GENERATING STATION — high-priority violation on file | Pass | State |
| 2017-04-13 | RAYBESTOS POWERTRAIN LLC | Pass | State |
| 2017-02-28 | HALLADOR POWER COMPANY LLC MEROM GENERATING STATION — high-priority violation on file | Pass | State |
| 2017-02-28 | HALLADOR POWER COMPANY LLC MEROM GENERATING STATION — high-priority violation on file | Pass | State |
| 2017-02-28 | HALLADOR POWER COMPANY LLC MEROM GENERATING STATION — high-priority violation on file | Pass | State |
| 2017-02-28 | HALLADOR POWER COMPANY LLC MEROM GENERATING STATION — high-priority violation on file | Pass | State |
Dates as filed by the agency that recorded the stack test. Figures from EPA’s ICIS-AIR download.