A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row below is one stack test recorded against a source in Choctaw County, Mississippi during 2017. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Choctaw County facility page.

Air-emissions stack tests in Choctaw County, other years

Air-emissions stack tests recorded in Choctaw County, Mississippi, 2017

DateFacilityKindAgency
2017-12-13ENTERGY MISSISSIPPI LLC, CHOCTAW COUNTY GENERATING STATIONPassState
2017-12-13ENTERGY MISSISSIPPI LLC, CHOCTAW COUNTY GENERATING STATIONPassState
2017-12-13ENTERGY MISSISSIPPI LLC, CHOCTAW COUNTY GENERATING STATIONPassState
2017-12-13ENTERGY MISSISSIPPI LLC, CHOCTAW COUNTY GENERATING STATIONPassState
2017-12-13ENTERGY MISSISSIPPI LLC, CHOCTAW COUNTY GENERATING STATIONPassState
2017-12-13ENTERGY MISSISSIPPI LLC, CHOCTAW COUNTY GENERATING STATIONPassState
2017-07-15ENTERGY MISSISSIPPI LLC, CHOCTAW COUNTY GENERATING STATIONPassState
2017-07-15ENTERGY MISSISSIPPI LLC, CHOCTAW COUNTY GENERATING STATIONPassState
2017-07-15ENTERGY MISSISSIPPI LLC, CHOCTAW COUNTY GENERATING STATIONPassState
2017-07-15ENTERGY MISSISSIPPI LLC, CHOCTAW COUNTY GENERATING STATIONPassState
2017-07-15ENTERGY MISSISSIPPI LLC, CHOCTAW COUNTY GENERATING STATIONPassState
2017-07-15ENTERGY MISSISSIPPI LLC, CHOCTAW COUNTY GENERATING STATIONPassState
2017-07-15ENTERGY MISSISSIPPI LLC, CHOCTAW COUNTY GENERATING STATIONPassState
2017-07-15ENTERGY MISSISSIPPI LLC, CHOCTAW COUNTY GENERATING STATIONPassState
2017-05-23CHOCTAW GENERATION LIMITED PARTNERSHIP, RED HILLS GENERATION FACILITYPassState
2017-05-23CHOCTAW GENERATION LIMITED PARTNERSHIP, RED HILLS GENERATION FACILITYPassState
2017-04-20ENTERGY MISSISSIPPI LLC, CHOCTAW COUNTY GENERATING STATIONPassState
2017-04-18ENTERGY MISSISSIPPI LLC, CHOCTAW COUNTY GENERATING STATIONPassState
2017-02-28CHOCTAW GENERATION LIMITED PARTNERSHIP, RED HILLS GENERATION FACILITYPassState
2017-02-28CHOCTAW GENERATION LIMITED PARTNERSHIP, RED HILLS GENERATION FACILITYPassState
2017-02-01TVA ACKERMAN COMBINED CYCLEPassState
2017-01-31TVA ACKERMAN COMBINED CYCLEPassState

Dates as filed by the agency that recorded the stack test. Figures from EPA’s ICIS-AIR download.

What this page shows

This page covers Clean Air Act facilities in the EPA air register with stack tests in Choctaw county, MS, in 2017. It lists 22 stack tests recorded in 2017.