EPA Air · stack tests by county and year
Air-emissions stack tests in Jackson County, Mississippi, 2019
- 37Stack tests
A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row below is one stack test recorded against a source in Jackson County, Mississippi during 2019. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Jackson County facility page.
Jackson County, Mississippi, 2019
- Inspections 10
Air-emissions stack tests in Jackson County, other years
Air-emissions stack tests recorded in Jackson County, Mississippi, 2019
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2019-12-04 | CHEVRON USA INC, CHEVRON PRODUCTS COMPANY, PASCAGOULA REFINERY | Pass | State |
| 2019-12-04 | CHEVRON USA INC, CHEVRON PRODUCTS COMPANY, PASCAGOULA REFINERY | Pass | State |
| 2019-12-03 | CHEVRON USA INC, CHEVRON PRODUCTS COMPANY, PASCAGOULA REFINERY | Pass | State |
| 2019-12-03 | DESTIN PIPELINE COMPANY LLC, PASCAGOULA COMPRESSOR STATION | Pass | State |
| 2019-09-10 | MISSISSIPPI POWER COMPANY, CHEVRON COGENERATING PLANT | Pass | State |
| 2019-08-20 | CHEVRON USA INC, CHEVRON PRODUCTS COMPANY, PASCAGOULA REFINERY | Pass | State |
| 2019-07-16 | CHEVRON USA INC, CHEVRON PRODUCTS COMPANY, PASCAGOULA REFINERY | Pass | State |
| 2019-06-27 | MISSISSIPPI POWER COMPANY, PLANT VICTOR J DANIEL | Pass | State |
| 2019-06-14 | MISSISSIPPI POWER COMPANY, PLANT VICTOR J DANIEL | Pass | State |
| 2019-06-14 | MISSISSIPPI POWER COMPANY, PLANT VICTOR J DANIEL | Pass | State |
| 2019-06-14 | MISSISSIPPI POWER COMPANY, PLANT VICTOR J DANIEL | Pass | State |
| 2019-06-13 | MISSISSIPPI POWER COMPANY, PLANT VICTOR J DANIEL | Pass | State |
| 2019-06-13 | MISSISSIPPI POWER COMPANY, PLANT VICTOR J DANIEL | Pass | State |
| 2019-06-13 | MISSISSIPPI POWER COMPANY, PLANT VICTOR J DANIEL | Pass | State |
| 2019-06-12 | MISSISSIPPI POWER COMPANY, PLANT VICTOR J DANIEL | Pass | State |
| 2019-06-12 | MISSISSIPPI POWER COMPANY, PLANT VICTOR J DANIEL | Pass | State |
| 2019-06-12 | MISSISSIPPI POWER COMPANY, PLANT VICTOR J DANIEL | Pass | State |
| 2019-06-11 | MISSISSIPPI POWER COMPANY, PLANT VICTOR J DANIEL | Pass | State |
| 2019-06-11 | MISSISSIPPI POWER COMPANY, PLANT VICTOR J DANIEL | Pass | State |
| 2019-06-11 | MISSISSIPPI POWER COMPANY, PLANT VICTOR J DANIEL | Pass | State |
| 2019-05-31 | MISSISSIPPI POWER COMPANY, PLANT VICTOR J DANIEL | Pass | State |
| 2019-04-23 | CHEVRON USA INC, CHEVRON PRODUCTS COMPANY, PASCAGOULA REFINERY | Pass | State |
| 2019-04-23 | CHEVRON USA INC, CHEVRON PRODUCTS COMPANY, PASCAGOULA REFINERY | Pass | State |
| 2019-04-11 | FIRST CHEMICAL CORPORATION | Pass | State |
| 2019-04-11 | FIRST CHEMICAL CORPORATION | Pass | State |
| 2019-04-11 | FIRST CHEMICAL CORPORATION | Pass | State |
| 2019-04-10 | FIRST CHEMICAL CORPORATION | Pass | State |
| 2019-04-10 | FIRST CHEMICAL CORPORATION | Pass | State |
| 2019-04-09 | FIRST CHEMICAL CORPORATION | Pass | State |
| 2019-03-27 | MISSISSIPPI POWER COMPANY, PLANT VICTOR J DANIEL | Pass | State |
| 2019-03-07 | MISSISSIPPI POWER COMPANY, PLANT VICTOR J DANIEL | Pass | State |
| 2019-02-28 | GULF SOUTH PIPELINE COMPANY LLC, MOSS POINT COMPRESSOR STATION | Pass | State |
| 2019-02-28 | GULF SOUTH PIPELINE COMPANY LLC, MOSS POINT COMPRESSOR STATION | Pass | State |
| 2019-02-28 | GULF SOUTH PIPELINE COMPANY LLC, MOSS POINT COMPRESSOR STATION | Pass | State |
| 2019-01-24 | CHEVRON USA INC, CHEVRON PRODUCTS COMPANY, PASCAGOULA REFINERY | Pass | State |
| 2019-01-24 | CHEVRON USA INC, CHEVRON PRODUCTS COMPANY, PASCAGOULA REFINERY | Pass | State |
| 2019-01-24 | CHEVRON USA INC, CHEVRON PRODUCTS COMPANY, PASCAGOULA REFINERY | Pass | State |
Dates as filed by the agency that recorded the stack test. Figures from EPA’s ICIS-AIR download.