A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row below is one stack test recorded against a source in Jones County, Mississippi during 2023. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Jones County facility page.

Jones County, Mississippi, 2023

Air-emissions stack tests in Jones County, other years

Air-emissions stack tests recorded in Jones County, Mississippi, 2023

DateFacilityKindAgency
2023-12-19COOPERATIVE ENERGY, A MISSISSIPPI ELECTRIC COOPERATIVE, MOSELLE GENERATING PLANTPassState
2023-12-19COOPERATIVE ENERGY, A MISSISSIPPI ELECTRIC COOPERATIVE, MOSELLE GENERATING PLANTPassState
2023-12-19COOPERATIVE ENERGY, A MISSISSIPPI ELECTRIC COOPERATIVE, MOSELLE GENERATING PLANTPassState
2023-12-12MASONITE CORPORATION — high-priority violation on filePassState
2023-09-28COOPERATIVE ENERGY, A MISSISSIPPI ELECTRIC COOPERATIVE, MOSELLE GENERATING PLANTPassState
2023-09-28COOPERATIVE ENERGY, A MISSISSIPPI ELECTRIC COOPERATIVE, MOSELLE GENERATING PLANTPassState
2023-09-28COOPERATIVE ENERGY, A MISSISSIPPI ELECTRIC COOPERATIVE, MOSELLE GENERATING PLANTPassState
2023-09-27MASONITE CORPORATION — high-priority violation on filePassState
2023-09-27MASONITE CORPORATION — high-priority violation on filePassState
2023-09-27COOPERATIVE ENERGY, A MISSISSIPPI ELECTRIC COOPERATIVE, MOSELLE GENERATING PLANTPassState
2023-09-27COOPERATIVE ENERGY, A MISSISSIPPI ELECTRIC COOPERATIVE, MOSELLE GENERATING PLANTPassState
2023-09-27COOPERATIVE ENERGY, A MISSISSIPPI ELECTRIC COOPERATIVE, MOSELLE GENERATING PLANTPassState
2023-09-26MASONITE CORPORATION — high-priority violation on filePassState
2023-09-26MASONITE CORPORATION — high-priority violation on filePassState
2023-09-26MASONITE CORPORATION — high-priority violation on filePassState
2023-09-26COOPERATIVE ENERGY, A MISSISSIPPI ELECTRIC COOPERATIVE, MOSELLE GENERATING PLANTPassState
2023-09-26COOPERATIVE ENERGY, A MISSISSIPPI ELECTRIC COOPERATIVE, MOSELLE GENERATING PLANTPassState
2023-09-26COOPERATIVE ENERGY, A MISSISSIPPI ELECTRIC COOPERATIVE, MOSELLE GENERATING PLANTPassState
2023-09-20COOPERATIVE ENERGY, A MISSISSIPPI ELECTRIC COOPERATIVE, MOSELLE GENERATING PLANTPassState
2023-06-29MASONITE CORPORATION — high-priority violation on filePassState
2023-06-29MASONITE CORPORATION — high-priority violation on filePassState
2023-06-29MASONITE CORPORATION — high-priority violation on filePassState
2023-04-04COOPERATIVE ENERGY, A MISSISSIPPI ELECTRIC COOPERATIVE, MOSELLE GENERATING PLANTPassState
2023-03-21COOPERATIVE ENERGY, A MISSISSIPPI ELECTRIC COOPERATIVE, MOSELLE GENERATING PLANTPassState
2023-03-16HUNT SOUTHLAND REFINING COMPANY LLCPassState
2023-03-15HUNT SOUTHLAND REFINING COMPANY LLCPassState