Velarion Records

EPA Air · stack tests by state, industry and year

Utilities (NAICS 2211): stack tests in Alabama, 2018

A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row is one stack test recorded during 2018 at a Alabama source whose primary industry code is NAICS 2211. A facility filing more than one industry code is counted under the first one on its record.

Utilities (NAICS 2211) in Alabama, other years

Other industries in Alabama, 2018

Air-emissions stack tests recorded in Alabama, 2018

DateFacilityWhereKindAgency
2018-11-15CER GENERATION LLCALEXANDER CITY, Tallapoosa, ALPassState
2018-11-07ALABAMA MUNICIPAL ELECTRIC AUTHORITYSYLACAUGA, Talladega, ALPassState
2018-10-30POWERSOUTH ENERGY COOPERATIVE INCLEROY, Washington, ALPassState
2018-10-02ALABAMA POWER COMPANYBUCKS, Mobile, ALPassState
2018-10-02ALABAMA POWER COMPANYPARRISH, Walker, ALPassState
2018-09-18ALABAMA POWER COMPANY (MILLER POWER PLANT)QUINTON, Jefferson, ALPassLocal
2018-09-13POWERSOUTH ENERGY COOPERATIVE INCMCINTOSH, Washington, ALPassState
2018-09-13POWERSOUTH ENERGY COOPERATIVE INCMCINTOSH, Washington, ALPassState
2018-09-12POWERSOUTH ENERGY COOPERATIVE INCMCINTOSH, Washington, ALPassState
2018-09-12POWERSOUTH ENERGY COOPERATIVE INCMCINTOSH, Washington, ALPassState
2018-09-11ALABAMA POWER COMPANY (MILLER POWER PLANT)QUINTON, Jefferson, ALPassLocal
2018-09-06ALABAMA POWER COMPANY (MILLER POWER PLANT)QUINTON, Jefferson, ALPassLocal
2018-09-05ALABAMA POWER COMPANY (MILLER POWER PLANT)QUINTON, Jefferson, ALPassLocal
2018-08-28POWERSOUTH ENERGY COOPERATIVE INCLEROY, Washington, ALPassState
2018-08-15POWERSOUTH ENERGY COOPERATIVE INCLEROY, Washington, ALPassState
2018-08-14POWERSOUTH ENERGY COOPERATIVE INCLEROY, Washington, ALPassState
2018-08-07ALABAMA POWER COMPANYBUCKS, Mobile, ALPassState
2018-08-06ALABAMA POWER COMPANYBUCKS, Mobile, ALPassState
2018-07-26ALABAMA POWER COMPANYPARRISH, Walker, ALPassState
2018-07-23ALABAMA POWER COMPANYBUCKS, Mobile, ALPassState
2018-07-17ALABAMA POWER COMPANYBUCKS, Mobile, ALPassState
2018-07-12ALABAMA POWER COMPANYWILSONVILLE, Shelby, ALPassState
2018-07-10POWERSOUTH ENERGY COOPERATIVE INCLEROY, Washington, ALPassState
2018-06-26ALABAMA POWER COMPANYBUCKS, Mobile, ALPassState
2018-06-26POWERSOUTH ENERGY COOPERATIVE INCLEROY, Washington, ALPassState
2018-06-26POWERSOUTH ENERGY COOPERATIVE INCLEROY, Washington, ALPassState
2018-06-19POWERSOUTH ENERGY COOPERATIVE INCLEROY, Washington, ALPassState
2018-06-06ALABAMA POWER COMPANYBUCKS, Mobile, ALPassState
2018-05-10ALABAMA POWER COMPANYBUCKS, Mobile, ALPassState
2018-05-09ALABAMA POWER COMPANYBUCKS, Mobile, ALPassState
2018-04-24ALABAMA POWER COMPANYPARRISH, Walker, ALPassState
2018-04-19ALABAMA POWER COMPANYWILSONVILLE, Shelby, ALPassState
2018-04-18ALABAMA POWER COMPANYBUCKS, Mobile, ALPassState
2018-03-14POWERSOUTH ENERGY COOPERATIVE INCLEROY, Washington, ALPassState
2018-02-21ALABAMA POWER COMPANY (MILLER POWER PLANT)QUINTON, Jefferson, ALPassLocal
2018-02-15ALABAMA POWER COMPANYBUCKS, Mobile, ALPassState
2018-02-14ALABAMA POWER COMPANYBUCKS, Mobile, ALPassState
2018-02-13ALABAMA POWER COMPANYWILSONVILLE, Shelby, ALPassState
2018-01-24ALABAMA POWER COMPANYPARRISH, Walker, ALPassState
2018-01-20ALABAMA POWER COMPANYWILSONVILLE, Shelby, ALPassState
2018-01-19ALABAMA POWER COMPANYWILSONVILLE, Shelby, ALPassState
2018-01-19POWERSOUTH ENERGY COOPERATIVE INCLEROY, Washington, ALPassState
2018-01-18ALABAMA POWER COMPANYWILSONVILLE, Shelby, ALPassState
2018-01-11ALABAMA POWER COMPANYWILSONVILLE, Shelby, ALPassState

Primary NAICS code as filed on the facility record; dates as filed by the agency that recorded the stack test. Figures from EPA’s ICIS-AIR download.

What this page shows

The page covers Clean Air Act facilities in the EPA air register with stack tests in state AL for NAICS industry 2211 in 2018. Stack tests recorded in 2018: 44.