EPA Air · stack tests by state, industry and year
Utilities (NAICS 2211): stack tests in South Carolina, 2023
- 54Stack tests
A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row is one stack test recorded during 2023 at a South Carolina source whose primary industry code is NAICS 2211. A facility filing more than one industry code is counted under the first one on its record.
Utilities (NAICS 2211) in South Carolina, other years
Other industries in South Carolina, 2023
- Paper manufacturing (NAICS 3221) 33
- Petroleum and coal products manufacturing (NAICS 3241) 23
- Chemical manufacturing (NAICS 3251) 12
- Wood product manufacturing (NAICS 3212) 11
- Wood product manufacturing (NAICS 3219) 8
- Mining and quarrying (NAICS 2123) 7
- Primary metal manufacturing (NAICS 3311) 7
- Nonmetallic mineral product manufacturing (NAICS 3273) 7
- Primary metal manufacturing (NAICS 3313) 6
- Nonmetallic mineral product manufacturing (NAICS 3272) 5
- Waste management and remediation (NAICS 5622) 5
- Pipeline transportation (NAICS 4862) 4
- Transportation equipment manufacturing (NAICS 3361) 4
- Utilities (NAICS 2213) 3
- Chemical manufacturing (NAICS 3252) 3
- Textile mills (NAICS 3133) 3
Air-emissions stack tests recorded in South Carolina, 2023
| Date | Facility | Where | Kind | Agency |
|---|---|---|---|---|
| 2023-12-14 | COPE STATION | COPE, Orangeburg, SC | Pass | State |
| 2023-12-14 | COPE STATION | COPE, Orangeburg, SC | Pass | State |
| 2023-12-06 | AMERESCO FEDERAL SOLUTIONS | AIKEN, Aiken, SC | Pass | State |
| 2023-11-30 | SANTEE COOPER WINYAH GENERATING STATION | GEORGETOWN, Georgetown, SC | Pass | State |
| 2023-11-30 | SANTEE COOPER WINYAH GENERATING STATION | GEORGETOWN, Georgetown, SC | Pass | State |
| 2023-11-09 | ALLENDALE BIOMASS LLC | FAIRFAX, Allendale, SC | Pass | State |
| 2023-11-09 | SANTEE COOPER CROSS GENERATING STATION — high-priority violation on file | PINEVILLE, Berkeley, SC | Pass | State |
| 2023-11-07 | SANTEE COOPER CROSS GENERATING STATION — high-priority violation on file | PINEVILLE, Berkeley, SC | Pass | State |
| 2023-11-07 | DORCHESTER BIOMASS LLC | HARLEYVILLE, Dorchester, SC | Pass | State |
| 2023-11-03 | SANTEE COOPER CROSS GENERATING STATION — high-priority violation on file | PINEVILLE, Berkeley, SC | Pass | State |
| 2023-09-26 | SANTEE COOPER CROSS GENERATING STATION — high-priority violation on file | PINEVILLE, Berkeley, SC | Pass | State |
| 2023-09-20 | WATEREE STATION | EASTOVER, Richland, SC | Pass | State |
| 2023-09-16 | SANTEE COOPER WINYAH GENERATING STATION | GEORGETOWN, Georgetown, SC | Pass | State |
| 2023-09-12 | SANTEE COOPER CROSS GENERATING STATION — high-priority violation on file | PINEVILLE, Berkeley, SC | Pass | State |
| 2023-09-12 | SANTEE COOPER CROSS GENERATING STATION — high-priority violation on file | PINEVILLE, Berkeley, SC | Pass | State |
| 2023-09-12 | COPE STATION | COPE, Orangeburg, SC | Pass | State |
| 2023-08-15 | SANTEE COOPER WINYAH GENERATING STATION | GEORGETOWN, Georgetown, SC | Pass | State |
| 2023-08-12 | COPE STATION | COPE, Orangeburg, SC | Pass | State |
| 2023-08-09 | SANTEE COOPER CROSS GENERATING STATION — high-priority violation on file | PINEVILLE, Berkeley, SC | Pass | State |
| 2023-08-08 | SANTEE COOPER CROSS GENERATING STATION — high-priority violation on file | PINEVILLE, Berkeley, SC | Pass | State |
| 2023-08-05 | A M WILLIAMS STATION | GOOSE CREEK, Berkeley, SC | Pass | State |
| 2023-07-21 | DUKE ENERGY PROGRESS LLC - HB ROBINSON DARLINGTON ELECTRIC POWER PLANT | HARTSVILLE, Darlington, SC | Pass | State |
| 2023-07-19 | DUKE ENERGY PROGRESS LLC - HB ROBINSON DARLINGTON ELECTRIC POWER PLANT | HARTSVILLE, Darlington, SC | Pass | State |
| 2023-07-12 | SANTEE COOPER WINYAH GENERATING STATION | GEORGETOWN, Georgetown, SC | Pass | State |
| 2023-07-11 | SANTEE COOPER WINYAH GENERATING STATION | GEORGETOWN, Georgetown, SC | Pass | State |
| 2023-06-29 | COPE STATION | COPE, Orangeburg, SC | Pass | State |
| 2023-06-29 | COPE STATION | COPE, Orangeburg, SC | Pass | State |
| 2023-06-15 | SANTEE COOPER WINYAH GENERATING STATION | GEORGETOWN, Georgetown, SC | Pass | State |
| 2023-06-13 | SANTEE COOPER WINYAH GENERATING STATION | GEORGETOWN, Georgetown, SC | Pass | State |
| 2023-06-07 | DUKE ENERGY CAROLINAS LLC W S LEE STEAM STATION — high-priority violation on file | BELTON, Anderson, SC | Pass | State |
| 2023-06-07 | SANTEE COOPER WINYAH GENERATING STATION | GEORGETOWN, Georgetown, SC | Pass | State |
| 2023-05-24 | SANTEE COOPER CROSS GENERATING STATION — high-priority violation on file | PINEVILLE, Berkeley, SC | Pass | State |
| 2023-05-09 | SANTEE COOPER WINYAH GENERATING STATION | GEORGETOWN, Georgetown, SC | Pass | State |
| 2023-05-05 | LOCKHART POWER COMPANY PACOLET | PACOLET, Spartanburg, SC | Pass | State |
| 2023-05-04 | LOCKHART POWER CITY WEST DIESEL GENERATING FACILITY | UNION, Union, SC | Pass | State |
| 2023-05-03 | LOCKHART POWER COMPANY | WELLFORD, Spartanburg, SC | Pass | State |
| 2023-05-02 | UNION RENEWABLE ENERGY FACILITY | ENOREE, Union, SC | Pass | State |
| 2023-04-27 | SANTEE COOPER CROSS GENERATING STATION — high-priority violation on file | PINEVILLE, Berkeley, SC | Pass | State |
| 2023-03-24 | AMERESCO FEDERAL SOLUTIONS | AIKEN, Aiken, SC | Pass | State |
| 2023-03-15 | SANTEE COOPER CROSS GENERATING STATION — high-priority violation on file | PINEVILLE, Berkeley, SC | Fail | State |
| 2023-03-15 | SANTEE COOPER CROSS GENERATING STATION — high-priority violation on file | PINEVILLE, Berkeley, SC | Pass | State |
| 2023-03-01 | DUKE ENERGY CAROLINAS LLC W S LEE STEAM STATION — high-priority violation on file | BELTON, Anderson, SC | Pass | State |
| 2023-02-16 | HONEA PATH GENERATING FACILITY | HONEA PATH, Abbeville, SC | Pass | State |
| 2023-02-15 | VALENITE GENERATING FACILITY | WESTMINSTER, Oconee, SC | Pass | State |
| 2023-02-14 | COPE STATION | COPE, Orangeburg, SC | Pass | State |
| 2023-02-14 | COPE STATION | COPE, Orangeburg, SC | Pass | State |
| 2023-02-14 | COPE STATION | COPE, Orangeburg, SC | Pass | State |
| 2023-02-08 | EASLEY COMBINED UTILITIES | EASLEY, Pickens, SC | Pass | State |
| 2023-02-07 | HAGOOD STATION | CHARLESTON, Charleston, SC | Pass | State |
| 2023-02-07 | WATEREE STATION | EASTOVER, Richland, SC | Pass | State |
| 2023-01-31 | WATEREE STATION | EASTOVER, Richland, SC | Pass | State |
| 2023-01-20 | WATEREE STATION | EASTOVER, Richland, SC | Pass | State |
| 2023-01-12 | A M WILLIAMS STATION | GOOSE CREEK, Berkeley, SC | Pass | State |
| 2023-01-05 | SANTEE COOPER CROSS GENERATING STATION — high-priority violation on file | PINEVILLE, Berkeley, SC | Pass | State |
Primary NAICS code as filed on the facility record; dates as filed by the agency that recorded the stack test. Figures from EPA’s ICIS-AIR download.