EPA Air · violations by state and year
High-priority air violations in Nebraska, 2025
- 46Violations
A high-priority violation is the most serious class of Clean Air Act non-compliance an agency records against a source; a federally reportable violation is the next step down in severity. Every violation below was recorded against a source in Nebraska during 2025; one facility can appear more than once, because this is a record of what happened rather than a list of places.
Counties in Nebraska, 2025
Nebraska, other years
High-priority air violations recorded in Nebraska, 2025
| Date | Facility | Where | Kind | Agency |
|---|---|---|---|---|
| 2025-12-19 | NATURALLY RECYCLED PROTEINS — high-priority violation on file | WAKEFIELD, Dixon, NE | Earliest FRV determination | State |
| 2025-12-16 | NOSWETT FENCING — high-priority violation on file | RICHLAND, Colfax, NE | Earliest FRV determination | State |
| 2025-11-18 | VALERO RENEWABLE FUELS COMPANY — high-priority violation on file | ALBION, Boone, NE | Earliest FRV determination | State |
| 2025-11-18 | CITY OF CHADRON BURN SITE — high-priority violation on file | CHADRON, Dawes, NE | Earliest FRV determination | State |
| 2025-11-17 | MARTIN MARIETTA MATERIALS INC — high-priority violation on file | WEEPING WATER, Cass, NE | Earliest FRV determination | State |
| 2025-11-14 | M MART — high-priority violation on file | MONROE, Platte, NE | Earliest FRV determination | State |
| 2025-11-13 | DUTTON-LAINSON COMPANY — high-priority violation on file | HASTINGS, Adams, NE | Earliest FRV determination | State |
| 2025-11-06 | ADM CORN PROCESSING — high-priority violation on file | COLUMBUS, Platte, NE | Earliest FRV determination | State |
| 2025-10-31 | FRENCHMAN VALLEY FARMERS CO-OP — high-priority violation on file | CHAPPELL, Deuel, NE | Earliest FRV determination | State |
| 2025-10-24 | CARGILL INC — high-priority violation on file | BLAIR, Washington, NE | Earliest FRV determination | State |
| 2025-10-16 | HUSKER STEEL — high-priority violation on file | COLUMBUS, Platte, NE | Earliest FRV determination | State |
| 2025-09-10 | OMAHA STEEL CASTINGS CO — high-priority violation on file | WAHOO, Saunders, NE | Earliest FRV determination | State |
| 2025-08-01 | GARLAND BURN SITE | GARLAND, Seward, NE | Earliest FRV determination | State |
| 2025-08-01 | SEWARD BURN SITE | SEWARD, Seward, NE | Earliest FRV determination | State |
| 2025-08-01 | PURAC AMERICA INC | BLAIR, Washington, NE | Earliest FRV determination | State |
| 2025-07-31 | TIMPTE INC | DAVID CITY, Butler, NE | Earliest FRV determination | State |
| 2025-07-03 | FARMERS UNION CO-OP ASSN | PRAGUE, Saunders, NE | Earliest FRV determination | State |
| 2025-06-26 | HOWELLS BURN SITE | HOWELLS, Colfax, NE | Earliest FRV determination | State |
| 2025-06-26 | PLATTE CENTER BURN SITE | PLATTE CENTER, Platte, NE | Earliest FRV determination | State |
| 2025-06-24 | SIDNEY POWER PLANT | SIDNEY, Cheyenne, NE | Earliest FRV determination | State |
| 2025-06-24 | SWIFT BEEF COMPANY — high-priority violation on file | GRAND ISLAND, Hall, NE | Earliest FRV determination | State |
| 2025-06-24 | CARGILL INC — high-priority violation on file | BLAIR, Washington, NE | Earliest FRV determination | State |
| 2025-06-23 | AUBURN BURN SITE | AUBURN, Nemaha, NE | Earliest FRV determination | State |
| 2025-06-23 | PERU BURN SITE | PERU, Nemaha, NE | Earliest FRV determination | State |
| 2025-06-06 | STEELE CITY BURN SITE | STEELE CITY, Jefferson, NE | Earliest FRV determination | State |
| 2025-06-06 | ALEXANDRIA BURN SITE | ALEXANDRIA, Thayer, NE | Earliest FRV determination | State |
| 2025-06-02 | DAYKIN BURN SITE | DAYKIN, Jefferson, NE | Earliest FRV determination | State |
| 2025-05-14 | BLUE SPRINGS BURN SITE | BLUE SPRINGS, Gage, NE | Earliest FRV determination | State |
| 2025-05-13 | SUNRISE COMPOSITES INC | HASTINGS, Adams, NE | Earliest FRV determination | State |
| 2025-04-02 | BRIDGEPORT ETHANOL LLC | BRIDGEPORT, Morrill, NE | Earliest FRV determination | State |
| 2025-03-27 | BD MEDICAL SYSTEMS | COLUMBUS, Platte, NE | Earliest FRV determination | State |
| 2025-03-21 | FRENCHMAN VALLEY FARMERS CO-OP — high-priority violation on file | CHAPPELL, Deuel, NE | Earliest FRV determination | State |
| 2025-03-12 | US MEAT ANIMAL RESEARCH CENTER — high-priority violation on file | CLAY CENTER, Clay, NE | Earliest FRV determination | State |
| 2025-03-12 | OMAHA PAPILLION CREEK WASTE | LA PLATTE, Sarpy, NE | Earliest FRV determination | State |
| 2025-03-07 | COLFAX COUNTY SHOP | SCHUYLER, Colfax, NE | Earliest FRV determination | State |
| 2025-02-27 | INDIANOLA TRAILER PARK | INDIANOLA, Red Willow, NE | Earliest FRV determination | State |
| 2025-02-18 | TIGT HUNTSMAN STATION 01 | SIDNEY, Cheyenne, NE | Earliest FRV determination | State |
| 2025-02-17 | KAAPA PARTNERS AURORA LLC — high-priority violation on file | AURORA, Hamilton, NE | Earliest FRV determination | State |
| 2025-02-07 | OMAHA PAPILLION CREEK WASTE | LA PLATTE, Sarpy, NE | Earliest FRV determination | State |
| 2025-02-04 | RIVERFRONT WWTF — high-priority violation on file | SOUTH SIOUX CITY, Dakota, NE | Earliest FRV determination | State |
| 2025-01-31 | DUO LIFT MANUFACTURING CO INC | COLUMBUS, Platte, NE | Earliest FRV determination | State |
| 2025-01-27 | ALLIANCE CODY SUBSTATION PLANT | ALLIANCE, Box Butte, NE | Earliest FRV determination | State |
| 2025-01-23 | US MEAT ANIMAL RESEARCH CENTER — high-priority violation on file | CLAY CENTER, Clay, NE | Earliest FRV determination | State |
| 2025-01-17 | CARGILL AGHORIZONS | ORD, Valley, NE | Earliest FRV determination | State |
| 2025-01-13 | HORNADY MANUFACTURING COMPANY | GRAND ISLAND, Hall, NE | Earliest FRV determination | State |
| 2025-01-10 | OPPD NEBRASKA CITY STATION | NEBRASKA CITY, Otoe, NE | Earliest FRV determination | State |
Dates as filed by the agency that recorded the violation. Figures from EPA’s ICIS-AIR download.
What this page shows
This page covers Clean Air Act facilities in the EPA air register with violations in state NE in 2025. It lists 46 violations recorded in 2025.