Velarion Records
Follow this watershed Velarion Records emails you this watershed’s record, cited to the public filing, and tells you when the register changes it. Free.
One more press on the next page sends it; there is no link to click in an email. The continuous daily watch on every change is the paid alert. Unsubscribe any time.
Also free: The Pay Desk, the weekly executive pay briefing.

EPA · Virginia · discharge permits by watershed

Watershed 0301010206 in Virginia

A watershed is a unit of the national Watershed Boundary Dataset, and water crosses state lines: this page holds only the permits placed in Virginia. Each permit is placed by the outfall EPA names as its representative discharge point.

Permits

Permit holderNPDES IDCityProgramDischargerReceiving waterStatus and term
ABBEYVILLE FARMSVAG407231RED OAKMinorRoanoke River/John H Kerr Reservoir-Cargills CreekAdministratively continued, 2021-08-02 to 2026-07-31
BROOKS KRISTINA RESIDENCEVAG407346SOUTH BOSTONMinorDifficult Creek-Ashcake CreekAdministratively continued, 2021-08-02 to 2026-07-31
CLOVER – BUTLER 230 KV LINE PHASE 1VAR10V670CHARLOTTE AND HALIFAX COUNTIESConstruction stormwaterMinorRoanoke River-John H Kerr Reservoir-Buffalo CreekEffective, 2024-07-01 to 2029-06-30
CLOVER CREEK SOLARVAR10U364SCOTTSBURGConstruction stormwaterMinorRoanoke River-John H Kerr Reservoir-Buffalo CreekEffective, 2024-07-01 to 2029-06-30
CLOVER POWER STATION-MUD MOUNTAIN STOCKPILE PROJECVAR10U709CLOVERConstruction stormwaterMinorRoanoke River-John H Kerr Reservoir-Buffalo CreekEffective, 2024-07-01 to 2029-06-30
CLOVER WWTPVA0073733CLOVERPublicly owned treatment worksMinorRoanoke River/Sandy CreekAdministratively continued, 2016-12-22 to 2021-12-31
CONSTRUCTION TRAILER PARKING AND ACCESS ROADVAR10W063SAXEConstruction stormwaterMinorRoanoke River-John H Kerr Reservoir-Buffalo CreekEffective, 2024-07-01 to 2029-06-30
COVINGTON MATTHEW AND ANNA MURRAY RESIDENCEVAG407357WYLIESBURGMinorRoanoke River-John H Kerr Reservoir-Buffalo CreekAdministratively continued, 2021-08-02 to 2026-07-31
CREWS ALVIN L AND ROSA LEE RESIDENCEVAG404021CLOVERMinorDifficult Creek-Piney CreekAdministratively continued, 2021-08-02 to 2026-07-31
DICKSON ALEXANDER RESIDENCEVAG402393SCOTTSBURGMinorDifficult Creek-Ashcake CreekAdministratively continued, 2021-08-02 to 2026-07-31
DIFFICULT CREEK LUMBERVAR051284SCOTTSBURGIndustrial stormwaterMinorDifficult Creek-Piney CreekAdministratively continued, 2019-07-01 to 2024-06-30
HALIFAX COUNTY SCHOOLS CLAYS MILL ELEMENTARYVA0022748SCOTTSBURGPublicly owned treatment worksMinorDifficult Creek-Piney CreekAdministratively continued, 2021-07-26 to 2026-07-31
HAYES WALTER W RESIDENCEVAG404106SCOTTSBURGMinorDifficult Creek-Ashcake CreekAdministratively continued, 2021-08-02 to 2026-07-31
LINE #235 230 KV REBUILD FROM CLOVER SUBSTATION TOVAR10V241HALIFAXConstruction stormwaterMinorRoanoke River-John H Kerr Reservoir-Buffalo CreekEffective, 2024-07-01 to 2029-06-30
LONG RESIDENCE AND MOBILE HOMEVAG404412CLARKSVILLEMinorRoanoke River/John H Kerr Reservoir-Cargills CreekEffective, 2026-07-13 to 2031-07-31
MARTIN TRAIL SOLARVAR10T685CLOVERConstruction stormwaterMinorDifficult Creek-Piney CreekAdministratively continued, 2019-07-01 to 2024-06-30
MORGAN LUMBER COMPANY INCVAR051165RED OAKIndustrial stormwaterMinorRoanoke River-John H Kerr Reservoir-Buffalo CreekAdministratively continued, 2019-07-01 to 2024-06-30
MORGAN LUMBER FACILITY EXPANSIONVAR10S820RED OAKConstruction stormwaterMinorRoanoke River-John H Kerr Reservoir-Buffalo CreekAdministratively continued, 2019-07-01 to 2024-06-30
REGIONAL SOLAR OFF-SITE LAYDOWN SUPPORTVAR10W547SCOTTSBURGConstruction stormwaterMinorRoanoke River-John H Kerr Reservoir-Buffalo CreekEffective, 2024-07-01 to 2029-06-30
ROE PARENT RESIDENCEVAG407304WYLESBURGMinorRoanoke River-John H Kerr Reservoir-Buffalo CreekAdministratively continued, 2021-08-02 to 2026-07-31
ROUTE 360 SOLARVAR10T851HALIFAXConstruction stormwaterMinorDifficult Creek-Piney CreekAdministratively continued, 2019-07-01 to 2024-06-30
RUTLEDGE LINDA T RESIDENCEVAG404081RED OAKMinorRoanoke River-John H Kerr Reservoir-Buffalo CreekAdministratively continued, 2021-08-02 to 2026-07-31
STAUNTON SOLARVAR10V919HALIFAXConstruction stormwaterMinorDifficult Creek-Ashcake CreekEffective, 2024-07-01 to 2029-06-30
TANYARD BRANCH SWINGING STATION INTERCONNECT PROJEVAR10W701HALIFAXConstruction stormwaterMinorRoanoke River-John H Kerr Reservoir-Buffalo CreekEffective, 2024-07-01 to 2029-06-30
VDOT CHARLOTTE - 0092-019-860 - UPC 111280VAR10U406CHARLOTTE COUNTYConstruction stormwaterMinorRoanoke River-John H Kerr Reservoir-Buffalo CreekEffective, 2024-07-01 to 2029-06-30
WILLIAMS AND LIFE PROPERTYVAG404194RED OAKMinorRoanoke River-John H Kerr Reservoir-Buffalo CreekAdministratively continued, 2021-08-02 to 2026-07-31