Air-emissions stack tests in New Haven County, Connecticut, 2018

A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row below is one stack test recorded against a source in New Haven County, Connecticut during 2018. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the New Haven County facility page.

New Haven County, Connecticut, 2018

Air-emissions stack tests in New Haven County, other years

Air-emissions stack tests recorded in New Haven County, Connecticut, 2018

DateFacilityKindAgency
2018-12-18NAUGATUCK WPCA/POTWPendingU.S. EPA
2018-12-18PHOENIX SOIL, LLCPassState
2018-12-12ALGONQUIN GAS TRANSMISSION LLC - OXFORD COMPRESSOR STATIONPassState
2018-12-12ALGONQUIN GAS TRANSMISSION LLC - OXFORD COMPRESSOR STATIONPassState
2018-12-05LEED HIMMEL INDUSTRIES, INCPassState
2018-11-30EAST SHORE WATER POLL ABATEMENT FACILITYPassState
2018-11-28SYNAGRO RESIDUALS MANAGEMENT COPassState
2018-11-28CITY OF WATERBURY WPCFPendingU.S. EPA
2018-11-27NAUGATUCK WPCA/POTWPassState
2018-09-25CURRENT, INCPassState
2018-09-13YALE UNIVERSITY, SCHOOL OF MEDICINE PREMISESPassState
2018-09-12YALE UNIVERSITY, SCHOOL OF MEDICINE PREMISESPassState
2018-09-12YALE UNIVERSITY, SCHOOL OF MEDICINE PREMISESPassState
2018-08-28COVIDIEN LPPassState
2018-08-28COVIDIEN LPPassState
2018-07-26BRISTOL-MYERS SQUIBB COPassState
2018-06-12CPV TOWANTIC, LLCPassState
2018-06-12CPV TOWANTIC, LLCPassState
2018-05-23O&G INDUSTRIES, INC. - SOUTHBURY QUARRYPassState
2018-03-29ALGONQUIN GAS TRANSMISSION LLC - OXFORD COMPRESSOR STATIONPassState
2018-03-28ALGONQUIN GAS TRANSMISSION LLC - OXFORD COMPRESSOR STATIONPassState
2018-03-27CPV TOWANTIC, LLCPassState
2018-02-23ROEHM AMERICA, LLC — high-priority violation on filePassState
2018-01-30YALE UNIVERSITY / CENTRAL POWER PLANTPassState
2018-01-30YALE UNIVERSITY / CENTRAL POWER PLANTPassState
2018-01-30YALE UNIVERSITY / CENTRAL POWER PLANTPassState

Dates as filed by the agency that recorded the stack test. Figures from EPA’s ICIS-AIR download.