EPA Air · stack tests by county and year
Air-emissions stack tests in New Haven County, Connecticut, 2024
- 29Stack tests
A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row below is one stack test recorded against a source in New Haven County, Connecticut during 2024. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the New Haven County facility page.
New Haven County, Connecticut, 2024
Air-emissions stack tests in New Haven County, other years
Air-emissions stack tests recorded in New Haven County, Connecticut, 2024
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2024-12-05 | COVIDIEN LP | Pass | State |
| 2024-11-25 | YALE UNIVERSITY WEST CAMPUS | Pass | State |
| 2024-11-14 | SYNAGRO RESIDUALS MANAGEMENT CO | Pass | State |
| 2024-11-13 | CHEMICAL EQUIPMENT LABS OF DE, INC. | Pass | State |
| 2024-11-13 | SYNAGRO RESIDUALS MANAGEMENT CO | Pass | U.S. EPA |
| 2024-10-29 | ALGONQUIN GAS TRANSMISSION LLC - OXFORD COMPRESSOR STATION | Pass | State |
| 2024-10-25 | NEW HAVEN /DPW (LANDFILL) | Pass | State |
| 2024-09-19 | NAUGATUCK WPCA/POTW | Pass | State |
| 2024-09-18 | EAST SHORE WATER POLL ABATEMENT FACILITY | Pass | State |
| 2024-09-08 | WATERBURY GENERATION, LLC | Pass | State |
| 2024-07-17 | H & T WATERBURY, INC. | Pass | State |
| 2024-06-13 | GB II NEW HAVEN, LLC - NEW HAVEN HARBOR STATION | Pass | State |
| 2024-06-13 | MILFORD POWER COMPANY, LLC | Pass | State |
| 2024-06-12 | GB II NEW HAVEN, LLC - NEW HAVEN HARBOR STATION | Pass | State |
| 2024-06-12 | MILFORD POWER COMPANY, LLC | Pass | State |
| 2024-06-11 | GB II NEW HAVEN, LLC - NEW HAVEN HARBOR STATION | Pass | State |
| 2024-05-30 | CPV TOWANTIC, LLC | Pass | State |
| 2024-05-29 | CPV TOWANTIC, LLC | Pass | State |
| 2024-05-28 | CPV TOWANTIC, LLC | Pass | State |
| 2024-05-28 | CPV TOWANTIC, LLC | Pass | State |
| 2024-04-24 | AMERICAN GREENFUELS, LLC | Pass | U.S. EPA |
| 2024-04-04 | ALGONQUIN GAS TRANSMISSION LLC - OXFORD COMPRESSOR STATION | Pass | State |
| 2024-03-20 | AMERICAN GREENFUELS, LLC | Incomplete | U.S. EPA |
| 2024-03-13 | YALE UNIVERSITY, SCHOOL OF MEDICINE PREMISES | Pass | State |
| 2024-03-13 | YALE UNIVERSITY, SCHOOL OF MEDICINE PREMISES | Pass | State |
| 2024-03-13 | YALE UNIVERSITY, SCHOOL OF MEDICINE PREMISES | Pass | State |
| 2024-03-12 | YALE UNIVERSITY, SCHOOL OF MEDICINE PREMISES | Pass | State |
| 2024-02-07 | YALE UNIVERSITY / CENTRAL POWER PLANT | Pass | State |
| 2024-02-07 | YALE UNIVERSITY / CENTRAL POWER PLANT | Pass | State |
Dates as filed by the agency that recorded the stack test. Figures from EPA’s ICIS-AIR download.