EPA Air · stack tests by county and year
Air-emissions stack tests in Santa Rosa County, Florida, 2020
- 30Stack tests
A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row below is one stack test recorded against a source in Santa Rosa County, Florida during 2020. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Santa Rosa County facility page.
Santa Rosa County, Florida, 2020
- Inspections 11
Air-emissions stack tests in Santa Rosa County, other years
Air-emissions stack tests recorded in Santa Rosa County, Florida, 2020
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2020-12-08 | BREITBURN OPERATING LP — high-priority violation on file | Pass | State |
| 2020-12-08 | FLORIDA POWER & LIGHT COMPANY | Pass | State |
| 2020-08-26 | SANTA ROSA ENERGY CTR, LLC | Pass | State |
| 2020-08-26 | SANTA ROSA ENERGY CTR, LLC | Pass | State |
| 2020-07-09 | BREITBURN OPERATING LP — high-priority violation on file | Pass | State |
| 2020-07-09 | BREITBURN OPERATING LP — high-priority violation on file | Pass | State |
| 2020-07-08 | BREITBURN OPERATING LP — high-priority violation on file | Pass | State |
| 2020-07-08 | BREITBURN OPERATING LP — high-priority violation on file | Pass | State |
| 2020-07-06 | BREITBURN OPERATING LP — high-priority violation on file | Pass | State |
| 2020-07-06 | BREITBURN OPERATING LP — high-priority violation on file | Pass | State |
| 2020-05-08 | FLORIDA GAS TRANSMISSION COMPANY, LLC | Pass | State |
| 2020-05-08 | FLORIDA GAS TRANSMISSION COMPANY, LLC | Pass | State |
| 2020-05-08 | FLORIDA GAS TRANSMISSION COMPANY, LLC | Pass | State |
| 2020-05-08 | FLORIDA GAS TRANSMISSION COMPANY, LLC | Pass | State |
| 2020-05-08 | FLORIDA GAS TRANSMISSION COMPANY, LLC | Pass | State |
| 2020-05-08 | FLORIDA GAS TRANSMISSION COMPANY, LLC | Pass | State |
| 2020-05-07 | FLORIDA GAS TRANSMISSION COMPANY, LLC | Pass | State |
| 2020-05-07 | FLORIDA GAS TRANSMISSION COMPANY, LLC | Pass | State |
| 2020-05-07 | FLORIDA GAS TRANSMISSION COMPANY, LLC | Pass | State |
| 2020-05-07 | FLORIDA GAS TRANSMISSION COMPANY, LLC | Pass | State |
| 2020-05-07 | FLORIDA GAS TRANSMISSION COMPANY, LLC | Pass | State |
| 2020-05-07 | FLORIDA GAS TRANSMISSION COMPANY, LLC | Pass | State |
| 2020-05-06 | FLORIDA GAS TRANSMISSION COMPANY, LLC | Pass | State |
| 2020-05-06 | FLORIDA GAS TRANSMISSION COMPANY, LLC | Pass | State |
| 2020-05-06 | FLORIDA GAS TRANSMISSION COMPANY, LLC | Pass | State |
| 2020-05-06 | FLORIDA GAS TRANSMISSION COMPANY, LLC | Pass | State |
| 2020-05-06 | FLORIDA GAS TRANSMISSION COMPANY, LLC | Pass | State |
| 2020-05-06 | FLORIDA GAS TRANSMISSION COMPANY, LLC | Pass | State |
| 2020-03-11 | FLORIDA POWER & LIGHT COMPANY | Pass | State |
| 2020-01-29 | QUIKRETE OF PENSACOLA — high-priority violation on file | Pass | State |
Dates as filed by the agency that recorded the stack test. Figures from EPA’s ICIS-AIR download.