EPA Air · stack tests by county and year
Air-emissions stack tests in Warrick County, Indiana, 2018
- 46Stack tests
A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row below is one stack test recorded against a source in Warrick County, Indiana during 2018. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Warrick County facility page.
Warrick County, Indiana, 2018
Air-emissions stack tests in Warrick County, other years
Air-emissions stack tests recorded in Warrick County, Indiana, 2018
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2018-11-30 | ALCOA POWER GENERATING INC WARRICK POWER PLANT — high-priority violation on file | Pass | State |
| 2018-11-30 | ALCOA POWER GENERATING INC WARRICK POWER PLANT — high-priority violation on file | Pass | State |
| 2018-11-30 | ALCOA POWER GENERATING INC WARRICK POWER PLANT — high-priority violation on file | Pass | State |
| 2018-11-30 | ALCOA POWER GENERATING INC WARRICK POWER PLANT — high-priority violation on file | Pass | State |
| 2018-11-16 | ALCOA POWER GENERATING INC WARRICK POWER PLANT — high-priority violation on file | Pass | State |
| 2018-11-06 | SIGECO - FB CULLEY GENERATING STATION | Pass | State |
| 2018-11-01 | WARRICK NEWCO LLC — high-priority violation on file | Pass | State |
| 2018-11-01 | WARRICK NEWCO LLC — high-priority violation on file | Pass | State |
| 2018-11-01 | WARRICK NEWCO LLC — high-priority violation on file | Pass | State |
| 2018-10-15 | WARRICK NEWCO LLC — high-priority violation on file | Pass | State |
| 2018-10-15 | WARRICK NEWCO LLC — high-priority violation on file | Pass | State |
| 2018-10-15 | WARRICK NEWCO LLC — high-priority violation on file | Pass | State |
| 2018-09-14 | ALCOA POWER GENERATING INC WARRICK POWER PLANT — high-priority violation on file | Pass | State |
| 2018-08-16 | ALCOA POWER GENERATING INC WARRICK POWER PLANT — high-priority violation on file | Pass | State |
| 2018-08-08 | WARRICK NEWCO LLC — high-priority violation on file | Pass | State |
| 2018-08-02 | ALCOA POWER GENERATING INC WARRICK POWER PLANT — high-priority violation on file | Pass | State |
| 2018-07-31 | SIGECO - FB CULLEY GENERATING STATION | Pass | State |
| 2018-05-17 | WARRICK NEWCO LLC — high-priority violation on file | Pass | State |
| 2018-05-17 | WARRICK NEWCO LLC — high-priority violation on file | Pass | State |
| 2018-05-17 | WARRICK NEWCO LLC — high-priority violation on file | Pass | State |
| 2018-05-17 | WARRICK NEWCO LLC — high-priority violation on file | Pass | State |
| 2018-05-16 | ALCOA POWER GENERATING INC WARRICK POWER PLANT — high-priority violation on file | Pass | State |
| 2018-05-15 | SIGECO - FB CULLEY GENERATING STATION | Pass | State |
| 2018-04-30 | WARRICK NEWCO LLC — high-priority violation on file | Pass | State |
| 2018-04-30 | WARRICK NEWCO LLC — high-priority violation on file | Pass | State |
| 2018-04-30 | WARRICK NEWCO LLC — high-priority violation on file | Pass | State |
| 2018-04-30 | WARRICK NEWCO LLC — high-priority violation on file | Pass | State |
| 2018-04-18 | WARRICK NEWCO LLC — high-priority violation on file | Pass | State |
| 2018-04-18 | WARRICK NEWCO LLC — high-priority violation on file | Pass | State |
| 2018-04-18 | WARRICK NEWCO LLC — high-priority violation on file | Pass | State |
| 2018-04-16 | WARRICK NEWCO LLC — high-priority violation on file | Pass | State |
| 2018-04-16 | WARRICK NEWCO LLC — high-priority violation on file | Pass | State |
| 2018-04-16 | WARRICK NEWCO LLC — high-priority violation on file | Pass | State |
| 2018-03-13 | WARRICK NEWCO LLC — high-priority violation on file | Pass | State |
| 2018-03-06 | WARRICK NEWCO LLC — high-priority violation on file | Pass | State |
| 2018-03-06 | WARRICK NEWCO LLC — high-priority violation on file | Pass | State |
| 2018-03-06 | WARRICK NEWCO LLC — high-priority violation on file | Pass | State |
| 2018-03-01 | WARRICK NEWCO LLC — high-priority violation on file | Pass | State |
| 2018-03-01 | WARRICK NEWCO LLC — high-priority violation on file | Pass | State |
| 2018-03-01 | WARRICK NEWCO LLC — high-priority violation on file | Pass | State |
| 2018-02-28 | WARRICK NEWCO LLC — high-priority violation on file | Pass | State |
| 2018-02-28 | WARRICK NEWCO LLC — high-priority violation on file | Pass | State |
| 2018-02-28 | WARRICK NEWCO LLC — high-priority violation on file | Pass | State |
| 2018-02-28 | WARRICK NEWCO LLC — high-priority violation on file | Pass | State |
| 2018-02-21 | ALCOA POWER GENERATING INC WARRICK POWER PLANT — high-priority violation on file | Pass | State |
| 2018-02-01 | SIGECO - FB CULLEY GENERATING STATION | Pass | State |
Dates as filed by the agency that recorded the stack test. Figures from EPA’s ICIS-AIR download.