Velarion Records

EPA Air · stack tests by county and year

Air-emissions stack tests in Warrick County, Indiana, 2026

A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row below is one stack test recorded against a source in Warrick County, Indiana during 2026. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Warrick County facility page.

Warrick County, Indiana, 2026

Air-emissions stack tests in Warrick County, other years

Air-emissions stack tests recorded in Warrick County, Indiana, 2026

DateFacilityKindAgency
2026-07-31SIGECO - FB CULLEY GENERATING STATIONPassState
2026-06-26ALCOA POWER GENERATING INC WARRICK POWER PLANT — high-priority violation on filePassState
2026-06-26ALCOA POWER GENERATING INC WARRICK POWER PLANT — high-priority violation on filePassState
2026-06-26WARRICK NEWCO LLC — high-priority violation on fileFailState
2026-06-26WARRICK NEWCO LLC — high-priority violation on filePassState
2026-06-26WARRICK NEWCO LLC — high-priority violation on fileFailState
2026-06-25ALCOA POWER GENERATING INC WARRICK POWER PLANT — high-priority violation on fileFailState
2026-06-25ALCOA POWER GENERATING INC WARRICK POWER PLANT — high-priority violation on filePassState
2026-06-24WARRICK NEWCO LLC — high-priority violation on fileFailState
2026-06-24WARRICK NEWCO LLC — high-priority violation on filePassState
2026-06-24WARRICK NEWCO LLC — high-priority violation on fileFailState
2026-06-17SIGECO - FB CULLEY GENERATING STATIONPassState
2026-05-20WARRICK NEWCO LLC — high-priority violation on filePassState
2026-05-20WARRICK NEWCO LLC — high-priority violation on filePassState
2026-05-18SIGECO - FB CULLEY GENERATING STATIONPassState
2026-05-14WARRICK NEWCO LLC — high-priority violation on fileFailState
2026-05-14WARRICK NEWCO LLC — high-priority violation on filePassState
2026-05-14WARRICK NEWCO LLC — high-priority violation on fileFailState
2026-04-21METZGER CONSTRUCTION COMPANY INCORPORATEDPassState
2026-04-21METZGER CONSTRUCTION COMPANY INCORPORATEDPassState
2026-04-21METZGER CONSTRUCTION COMPANY INCORPORATEDPassState
2026-04-21METZGER CONSTRUCTION COMPANY INCORPORATEDPassState
2026-04-07ALCOA POWER GENERATING INC WARRICK POWER PLANT — high-priority violation on filePassState
2026-03-25ALCOA POWER GENERATING INC WARRICK POWER PLANT — high-priority violation on fileFailState
2026-03-25ALCOA POWER GENERATING INC WARRICK POWER PLANT — high-priority violation on fileFailState
2026-03-25ALCOA POWER GENERATING INC WARRICK POWER PLANT — high-priority violation on fileFailState
2026-03-25ALCOA POWER GENERATING INC WARRICK POWER PLANT — high-priority violation on filePassState
2026-03-24ALCOA POWER GENERATING INC WARRICK POWER PLANT — high-priority violation on fileFailState
2026-03-24ALCOA POWER GENERATING INC WARRICK POWER PLANT — high-priority violation on filePassState
2026-03-20SIGECO - FB CULLEY GENERATING STATIONPassState
2026-02-12WARRICK NEWCO LLC — high-priority violation on filePassState
2026-02-12WARRICK NEWCO LLC — high-priority violation on filePassState
2026-02-12WARRICK NEWCO LLC — high-priority violation on filePassState
2026-02-12WARRICK NEWCO LLC — high-priority violation on filePassState
2026-02-12WARRICK NEWCO LLC — high-priority violation on fileFailState
2026-02-12WARRICK NEWCO LLC — high-priority violation on filePassState
2026-02-04ALCOA POWER GENERATING INC WARRICK POWER PLANT — high-priority violation on filePassState
2026-02-02ALCOA POWER GENERATING INC WARRICK POWER PLANT — high-priority violation on filePassState
2026-02-02KAISER ALUMINUM WARRICK LLC — high-priority violation on filePassState
2026-02-02KAISER ALUMINUM WARRICK LLC — high-priority violation on filePassState
2026-01-16SIGECO - FB CULLEY GENERATING STATIONPassState
2026-01-06ALCOA POWER GENERATING INC WARRICK POWER PLANT — high-priority violation on filePassState

Dates as filed by the agency that recorded the stack test. Figures from EPA’s ICIS-AIR download.

What this page shows

This page covers Clean Air Act facilities in the EPA air register with stack tests in Warrick county, IN, in 2026. The stack tests recorded in 2026 total 42.