Velarion Records

The 340B register and hospital finances — joined, watched daily, delivered.

EPA Air · stack tests by county and year

Air-emissions stack tests in St. Clair County, Michigan, 2025

A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row below is one stack test recorded against a source in St. Clair County, Michigan during 2025. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the St. Clair County facility page.

St. Clair County, Michigan, 2025

Air-emissions stack tests in St. Clair County, other years

Air-emissions stack tests recorded in St. Clair County, Michigan, 2025

DateFacilityKindAgency
2025-10-16DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on filePassState
2025-10-07DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on filePassState
2025-10-02DTE GAS COMPANY - BELLE RIVER MILLS COMPRESSOR STATIONPassState
2025-09-30DTE ELECTRIC COMPANY - GREENWOOD ENERGY CENTERPassState
2025-09-24DTE ELECTRIC COMPANY - GREENWOOD ENERGY CENTERPassState
2025-09-18PREGISPassState
2025-09-09BLUEWATER GAS STORAGE FACILITY - COLUMBUSPassState
2025-09-04DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on filePassState
2025-09-02DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on filePassState
2025-08-20DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on filePassState
2025-08-19DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on filePassState
2025-08-06DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on filePassState
2025-08-06DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on filePassState
2025-07-10DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on filePassState
2025-06-27DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on filePassState
2025-06-17DTE ELECTRIC COMPANY - GREENWOOD ENERGY CENTERPassState
2025-06-11DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on filePassState
2025-05-22DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on filePassState
2025-05-14DTE GAS COMPANY - COLUMBUS COMPRESSOR STATION — high-priority violation on filePassState
2025-04-16DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on filePassState
2025-04-15DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on filePassState
2025-04-10BLUE WATER RENEWABLES — high-priority violation on filePassState
2025-04-03DTE ELECTRIC COMPANY - GREENWOOD ENERGY CENTERPassState
2025-02-27DTE GAS COMPANY - BELLE RIVER MILLS COMPRESSOR STATIONPassState
2025-02-27DTE GAS COMPANY - BELLE RIVER MILLS COMPRESSOR STATIONPassState
2025-02-26DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on filePassState
2025-02-18MARYSVILLE ETHANOL, LLCPassState
2025-01-28DTE ELECTRIC COMPANY - GREENWOOD ENERGY CENTERPassState
2025-01-16DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on filePassState
2025-01-09DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on filePassState

Dates as filed by the agency that recorded the stack test. Figures from EPA’s ICIS-AIR download.