Air-emissions stack tests in Wayne County, Michigan, 2017
- 55Stack tests
A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row below is one stack test recorded against a source in Wayne County, Michigan during 2017. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Wayne County facility page.
Wayne County, Michigan, 2017
Air-emissions stack tests in Wayne County, other years
Air-emissions stack tests recorded in Wayne County, Michigan, 2017
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2017-12-20 | MARATHON PETROLEUM COMPANY LP — high-priority violation on file | Pass | State |
| 2017-12-14 | MARATHON PETROLEUM COMPANY LP — high-priority violation on file | Pass | State |
| 2017-12-14 | RIVERVIEW LAND PRESERVE | Pass | State |
| 2017-12-12 | MARATHON PETROLEUM COMPANY LP — high-priority violation on file | Pass | State |
| 2017-12-04 | FORD MOTOR COMPANY ROUGE COMPLEX | Pending | State |
| 2017-12-04 | DETROIT RENEWABLE POWER, LLC — high-priority violation on file | Pass | State |
| 2017-11-30 | MARATHON PETROLEUM COMPANY LP — high-priority violation on file | Pass | State |
| 2017-11-28 | FCA US LLC - TRENTON ENGINE COMPLEX | Pass | State |
| 2017-11-14 | CLEVELAND-CLIFFS STEEL CORPORATION DEARBORN WORKS | Pass | State |
| 2017-11-08 | MARATHON PETROLEUM COMPANY LP — high-priority violation on file | Pass | State |
| 2017-11-07 | CARMEUSE LIME INC, RIVER ROUGE OPERATION — high-priority violation on file | Pass | State |
| 2017-10-24 | U S STEEL GREAT LAKES WORKS — high-priority violation on file | Fail | State |
| 2017-10-19 | MARATHON PETROLEUM COMPANY LP — high-priority violation on file | Pass | State |
| 2017-10-16 | WYANDOTTE DEPT MUNICIPAL POWER PLANT — high-priority violation on file | Pass | State |
| 2017-09-27 | U S STEEL GREAT LAKES WORKS — high-priority violation on file | Pass | State |
| 2017-09-27 | GLWA WATER RESOURCE RECOVERY FACILITY | Pass | State |
| 2017-09-26 | MARATHON PETROLEUM COMPANY LP — high-priority violation on file | Pass | State |
| 2017-09-20 | FRITZ PRODUCTS | Pass | State |
| 2017-08-24 | CLEVELAND-CLIFFS STEEL CORPORATION DEARBORN WORKS | Pass | State |
| 2017-08-23 | CLEVELAND-CLIFFS STEEL CORPORATION DEARBORN WORKS | Pass | State |
| 2017-08-22 | MARATHON PETROLEUM COMPANY LP — high-priority violation on file | Pass | State |
| 2017-07-21 | MARATHON PETROLEUM COMPANY LP — high-priority violation on file | Pass | State |
| 2017-07-18 | DEARBORN INDUSTRIAL GENERATION | Pass | State |
| 2017-07-12 | US ECOLOGY MICHIGAN | Pass | State |
| 2017-06-26 | MARATHON PETROLEUM COMPANY LP — high-priority violation on file | Pass | State |
| 2017-06-24 | MARATHON PETROLEUM COMPANY LP — high-priority violation on file | Pending | State |
| 2017-06-22 | FORD MOTOR COMPANY WAYNE COMPLEX | Pending | State |
| 2017-06-22 | 3M DETROIT ABRASIVES | Pending | State |
| 2017-06-14 | 3M DETROIT ABRASIVES | Pending | State |
| 2017-06-09 | SUMPTER GENERATING PLANT | Pass | State |
| 2017-06-05 | MARATHON PETROLEUM COMPANY LP — high-priority violation on file | Fail | State |
| 2017-06-01 | VOSS INDUSTRIES | Pass | State |
| 2017-05-31 | FORD MOTOR CO AUTO TRANSMISSION NEW PRODUCT CENTER — high-priority violation on file | Pending | State |
| 2017-05-24 | FCA US LLC - TRENTON ENGINE COMPLEX | Pass | State |
| 2017-05-22 | MARATHON PETROLEUM COMPANY LP — high-priority violation on file | Pass | State |
| 2017-05-22 | GLWA WATER RESOURCE RECOVERY FACILITY | Pass | State |
| 2017-05-17 | GLWA WATER RESOURCE RECOVERY FACILITY | Pass | State |
| 2017-05-16 | MARATHON PETROLEUM COMPANY LP — high-priority violation on file | Pass | State |
| 2017-05-10 | BUCKEYE TERMINALS, LLC - WOODHAVEN TERMINAL | Pass | State |
| 2017-04-25 | GLWA WATER RESOURCE RECOVERY FACILITY | Pass | State |
| 2017-04-19 | GLWA WATER RESOURCE RECOVERY FACILITY | Pass | State |
| 2017-04-12 | FORD MOTOR COMPANY ROUGE COMPLEX | Pass | State |
| 2017-04-07 | DETROIT METROPOLITAN WAYNE COUNTY AIRPORT | Pass | State |
| 2017-04-05 | MARATHON PETROLEUM COMPANY LP — high-priority violation on file | Pass | State |
| 2017-04-03 | MARATHON PETROLEUM COMPANY LP — high-priority violation on file | Pass | State |
| 2017-03-28 | CLEVELAND-CLIFFS STEEL CORPORATION DEARBORN WORKS | Pass | State |
| 2017-03-22 | FORD MOTOR COMPANY - FLAT ROCK ASSEMBLY | Pass | State |
| 2017-03-22 | FORD MOTOR COMPANY - FLAT ROCK ASSEMBLY | Pass | State |
| 2017-03-15 | MARATHON PETROLEUM COMPANY LP — high-priority violation on file | Pass | State |
| 2017-03-08 | FORD MOTOR COMPANY WAYNE COMPLEX | Pass | State |
| 2017-03-01 | BUCKEYE TERMINALS, LLC - WOODHAVEN TERMINAL | Fail | State |
| 2017-02-27 | MARATHON PETROLEUM COMPANY LP — high-priority violation on file | Pass | State |
| 2017-02-14 | U S STEEL GREAT LAKES WORKS — high-priority violation on file | Pass | State |
| 2017-02-09 | FORD MOTOR COMPANY ROUGE COMPLEX | Pass | State |
| 2017-01-18 | ADIENT ROMULUS | Pass | State |
Dates as filed by the agency that recorded the stack test. Figures from EPA’s ICIS-AIR download.