A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row below is one stack test recorded against a source in Wayne County, Michigan during 2023. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Wayne County facility page.
Wayne County, Michigan, 2023
Air-emissions stack tests in Wayne County, other years
Air-emissions stack tests recorded in Wayne County, Michigan, 2023
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2023-12-13 | U S STEEL GREAT LAKES WORKS — high-priority violation on file | Pass | State |
| 2023-12-12 | GLWA WATER RESOURCE RECOVERY FACILITY | Pass | State |
| 2023-12-05 | DEARBORN INDUSTRIAL GENERATION | Pending | State |
| 2023-11-21 | CLEVELAND-CLIFFS STEEL CORPORATION DEARBORN WORKS | Pass | State |
| 2023-11-14 | ROUSH INDUSTRIES | Pass | State |
| 2023-11-07 | GLWA WATER RESOURCE RECOVERY FACILITY | Pass | State |
| 2023-11-07 | FLAT ROCK METAL, INC. | Pass | State |
| 2023-10-31 | CARMEUSE LIME INC, RIVER ROUGE OPERATION — high-priority violation on file | Pass | State |
| 2023-10-25 | UNITED STATES GYPSUM COMPANY | Pass | State |
| 2023-10-12 | FCA US LLC - DETROIT ASSEMBLY COMPLEX — high-priority violation on file | Pending | State |
| 2023-10-10 | CONSUMERS ENERGY - NORTHVILLE COMPRESSOR STATION | Pass | State |
| 2023-10-03 | FORD MOTOR COMPANY ROUGE COMPLEX | Pending | State |
| 2023-09-29 | SAUK TRAIL HILLS DEVELOPMENT | Pending | State |
| 2023-09-19 | CLEVELAND-CLIFFS STEEL CORPORATION DEARBORN WORKS | Pass | State |
| 2023-09-12 | EES COKE BATTERY, LLC — high-priority violation on file | Pass | State |
| 2023-08-17 | CLEVELAND-CLIFFS STEEL CORPORATION DEARBORN WORKS | Pass | State |
| 2023-08-01 | CLEVELAND-CLIFFS STEEL CORPORATION DEARBORN WORKS | Fail | State |
| 2023-07-25 | FORD MOTOR COMPANY - FLAT ROCK ASSEMBLY | Pass | State |
| 2023-07-20 | MARATHON PETROLEUM COMPANY LP — high-priority violation on file | Pass | State |
| 2023-07-12 | GLWA WATER RESOURCE RECOVERY FACILITY | Pass | State |
| 2023-07-11 | MARATHON PETROLEUM COMPANY LP — high-priority violation on file | Pass | State |
| 2023-07-11 | FCA US LLC - DETROIT ASSEMBLY COMPLEX — high-priority violation on file | Pass | State |
| 2023-06-29 | FORD MOTOR COMPANY - FLAT ROCK ASSEMBLY | Pending | State |
| 2023-06-14 | SUMPTER GENERATING PLANT | Pass | State |
| 2023-06-06 | MARATHON PETROLEUM COMPANY LP — high-priority violation on file | Pass | State |
| 2023-05-23 | CLEVELAND-CLIFFS STEEL CORPORATION DEARBORN WORKS | Pass | State |
| 2023-05-16 | CLEVELAND-CLIFFS STEEL CORPORATION DEARBORN WORKS | Pending | State |
| 2023-04-24 | MARATHON PETROLEUM COMPANY LP — high-priority violation on file | Pass | State |
| 2023-04-18 | MARATHON PETROLEUM COMPANY LP — high-priority violation on file | Pass | State |
| 2023-03-23 | U S STEEL GREAT LAKES WORKS — high-priority violation on file | Pass | State |
| 2023-02-28 | MARATHON PETROLEUM COMPANY LP — high-priority violation on file | Pass | State |
| 2023-02-21 | FCA US LLC - DETROIT ASSEMBLY COMPLEX — high-priority violation on file | Pending | State |
| 2023-02-21 | FCA US LLC - DETROIT ASSEMBLY COMPLEX — high-priority violation on file | Pending | State |
| 2023-01-18 | FCA US LLC - TRENTON ENGINE COMPLEX | Pass | State |