EPA Air · stack tests by county and year
Air-emissions stack tests in Marathon County, Wisconsin, 2024
- 22Stack tests
A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row below is one stack test recorded against a source in Marathon County, Wisconsin during 2024. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Marathon County facility page.
Marathon County, Wisconsin, 2024
Air-emissions stack tests in Marathon County, other years
Air-emissions stack tests recorded in Marathon County, Wisconsin, 2024
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2024-12-17 | MARATHON COUNTY LANDFILL | Pass | State |
| 2024-11-05 | WI PUBLIC SERVICE WESTON POWER PLANT | Pass | State |
| 2024-10-28 | WISCONSIN ELECTRIC POWER COMPANY (DBA WE ENERGIES) - ROTHSCHILD BIOMASS COGENERA — high-priority violation on file | Pass | State |
| 2024-10-22 | WI PUBLIC SERVICE WESTON POWER PLANT | Pass | State |
| 2024-10-08 | WISCONSIN ELECTRIC POWER COMPANY (DBA WE ENERGIES) - ROTHSCHILD BIOMASS COGENERA — high-priority violation on file | Pass | State |
| 2024-08-20 | MULLINS CHEESE INC — high-priority violation on file | Pass | State |
| 2024-08-13 | WISCONSIN ELECTRIC POWER COMPANY (DBA WE ENERGIES) - ROTHSCHILD BIOMASS COGENERA — high-priority violation on file | Pass | State |
| 2024-07-22 | WI PUBLIC SERVICE WESTON POWER PLANT | Pass | State |
| 2024-07-15 | WI PUBLIC SERVICE WESTON POWER PLANT | Pass | State |
| 2024-07-15 | WI PUBLIC SERVICE WESTON POWER PLANT | Pass | State |
| 2024-07-15 | WI PUBLIC SERVICE WESTON POWER PLANT | Pass | State |
| 2024-07-15 | WI PUBLIC SERVICE WESTON POWER PLANT | Pass | State |
| 2024-07-10 | CRYSTAL FINISHING SYSTEMS INC | Fail | State |
| 2024-06-25 | APOGEE WAUSAU GROUP INC LINETEC DIVISION — high-priority violation on file | Pass | State |
| 2024-06-03 | WISCONSIN ELECTRIC POWER COMPANY (DBA WE ENERGIES) - ROTHSCHILD BIOMASS COGENERA — high-priority violation on file | Pass | State |
| 2024-05-15 | MARTH WOOD SHAVINGS SUPPLY INC — high-priority violation on file | Fail | State |
| 2024-05-14 | WI PUBLIC SERVICE WESTON POWER PLANT | Pass | State |
| 2024-05-13 | WI PUBLIC SERVICE WESTON POWER PLANT | Pass | State |
| 2024-05-13 | WI PUBLIC SERVICE WESTON POWER PLANT | Pass | State |
| 2024-05-13 | WI PUBLIC SERVICE WESTON POWER PLANT | Pass | State |
| 2024-03-25 | AHLSTROM MOSINEE, LLC — high-priority violation on file | Pass | State |
| 2024-02-14 | CRYSTAL FINISHING SYSTEMS INC | Pass | State |
Dates as filed by the agency that recorded the stack test. Figures from EPA’s ICIS-AIR download.