EPA Air · stack tests by county and year
Air-emissions stack tests in Monroe County, Georgia, 2017
- 48Stack tests
A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row below is one stack test recorded against a source in Monroe County, Georgia during 2017. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Monroe County facility page.
Monroe County, Georgia, 2017
- Inspections 28
Air-emissions stack tests in Monroe County, other years
Air-emissions stack tests recorded in Monroe County, Georgia, 2017
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2017-12-20 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-12-19 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-09-08 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-09-07 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-09-06 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-09-05 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-09-01 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-08-31 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-08-29 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-08-29 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-05-26 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-05-24 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-05-23 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-05-22 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-05-19 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-05-18 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-05-17 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-05-16 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-05-10 | SMARR ENERGY FACILITY | Pass | State |
| 2017-05-09 | SMARR ENERGY FACILITY | Pass | State |
| 2017-03-14 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-03-08 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-03-07 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-03-03 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-03-03 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-03-03 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-03-02 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-03-02 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-03-02 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-03-01 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-03-01 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-02-28 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-02-28 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-02-28 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-02-28 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-02-22 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-02-16 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-02-16 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-02-16 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-02-16 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-02-16 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-02-16 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-02-15 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-02-15 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-02-14 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-02-14 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-02-14 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2017-02-14 | GA POWER CO. - PLANT SCHERER | Pass | State |
Dates as filed by the agency that recorded the stack test. Figures from EPA’s ICIS-AIR download.