EPA Air · stack tests by county and year
Air-emissions stack tests in Monroe County, Georgia, 2019
- 54Stack tests
A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row below is one stack test recorded against a source in Monroe County, Georgia during 2019. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Monroe County facility page.
Monroe County, Georgia, 2019
- Inspections 28
Air-emissions stack tests in Monroe County, other years
Air-emissions stack tests recorded in Monroe County, Georgia, 2019
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2019-11-22 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-11-22 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-11-21 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-11-21 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-11-20 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-11-20 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-11-19 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-11-19 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-09-18 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-09-18 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-09-17 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-09-17 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-08-22 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-08-22 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-08-21 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-08-21 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-05-15 | SMARR ENERGY FACILITY | Pass | State |
| 2019-05-14 | SMARR ENERGY FACILITY | Pass | State |
| 2019-05-03 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-05-03 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-04-23 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-04-23 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-02-08 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-02-08 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-02-08 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-02-08 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-02-07 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-02-07 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-02-06 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-02-06 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-02-06 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-02-06 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-01-25 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-01-24 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-01-23 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-01-23 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-01-22 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-01-22 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-01-18 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-01-18 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-01-18 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-01-18 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-01-17 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-01-16 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-01-16 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-01-16 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-01-16 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-01-15 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-01-12 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-01-12 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-01-09 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-01-09 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-01-08 | GA POWER CO. - PLANT SCHERER | Pass | State |
| 2019-01-08 | GA POWER CO. - PLANT SCHERER | Pass | State |
Dates as filed by the agency that recorded the stack test. Figures from EPA’s ICIS-AIR download.