Air-emissions stack tests in Monroe County, Georgia, 2024

A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row below is one stack test recorded against a source in Monroe County, Georgia during 2024. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Monroe County facility page.

Monroe County, Georgia, 2024

Air-emissions stack tests in Monroe County, other years

Air-emissions stack tests recorded in Monroe County, Georgia, 2024

DateFacilityKindAgency
2024-12-16GA POWER CO. - PLANT SCHERERPassState
2024-11-14GA POWER CO. - PLANT SCHERERPassState
2024-11-14GA POWER CO. - PLANT SCHERERPassState
2024-11-13GA POWER CO. - PLANT SCHERERPassState
2024-11-13GA POWER CO. - PLANT SCHERERPassState
2024-11-13GA POWER CO. - PLANT SCHERERPassState
2024-11-12GA POWER CO. - PLANT SCHERERPassState
2024-11-12GA POWER CO. - PLANT SCHERERPassState
2024-10-25GA POWER CO. - PLANT SCHERERPassState
2024-08-28GA POWER CO. - PLANT SCHERERPassState
2024-07-18GA POWER CO. - PLANT SCHERERPassState
2024-06-26SMARR ENERGY FACILITYPassState
2024-06-25SMARR ENERGY FACILITYPassState
2024-06-20C.W. MATTHEWS CONTRACTING CO., INC. - PLANT #48 MACONPassState
2024-05-09GA POWER CO. - PLANT SCHERERPassState
2024-05-08GA POWER CO. - PLANT SCHERERPassState
2024-04-10GA POWER CO. - PLANT SCHERERPassState
2024-04-10GA POWER CO. - PLANT SCHERERPassState
2024-04-10GA POWER CO. - PLANT SCHERERPassState
2024-04-10GA POWER CO. - PLANT SCHERERPassState
2024-04-09GA POWER CO. - PLANT SCHERERPassState
2024-04-09GA POWER CO. - PLANT SCHERERPassState
2024-04-04GA POWER CO. - PLANT SCHERERPassState
2024-04-04GA POWER CO. - PLANT SCHERERPassState
2024-04-04GA POWER CO. - PLANT SCHERERPassState
2024-04-04GA POWER CO. - PLANT SCHERERPassState
2024-04-03GA POWER CO. - PLANT SCHERERPassState
2024-04-02GA POWER CO. - PLANT SCHERERPassState
2024-01-04GA POWER CO. - PLANT SCHERERPassState

Dates as filed by the agency that recorded the stack test. Figures from EPA’s ICIS-AIR download.