Air-emissions stack tests in Monroe County, Wisconsin, 2020
- 28Stack tests
A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row below is one stack test recorded against a source in Monroe County, Wisconsin during 2020. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Monroe County facility page.
Monroe County, Wisconsin, 2020
- Inspections 14
Air-emissions stack tests in Monroe County, other years
Air-emissions stack tests recorded in Monroe County, Wisconsin, 2020
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2020-12-01 | THE NEWARK GROUP, INC. | Pass | State |
| 2020-12-01 | SONOCO METAL PACKAGING LLC | Pass | State |
| 2020-11-17 | MMSD-JONES ISLAND WATER RECLAMATION FACILITY | Pass | State |
| 2020-11-05 | MOLSON COORS USA LLC | Pass | State |
| 2020-10-27 | GREDE LLC - LIBERTY — high-priority violation on file | Pass | State |
| 2020-10-27 | WMWI - METRO RECYCLING & DISPOSAL | Pass | State |
| 2020-10-20 | CASHTON MUNICIPAL LIGHT AND WATER DEPART | Fail | State |
| 2020-10-13 | MAYNARD STEEL CASTING CO | Pass | State |
| 2020-09-09 | WE ENERGIES - VALLEY POWER PLANT | Pass | State |
| 2020-08-31 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2020-08-31 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2020-08-28 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2020-08-25 | MILWAUKEE REGIONAL MEDICAL CENTER THERMAL SERVICES INC | Pass | State |
| 2020-08-25 | STARK PAVEMENT CORP | N/A | State |
| 2020-08-24 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2020-08-24 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2020-08-20 | WE ENERGIES - VALLEY POWER PLANT | Pass | State |
| 2020-08-13 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2020-08-11 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2020-07-22 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2020-07-21 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2020-07-07 | BUCKEYE TERMINALS LLC | Pass | State |
| 2020-05-20 | BRADY WORLDWIDE - FLORIST AVE PLT | Pass | State |
| 2020-04-30 | MOLSON COORS USA LLC | Pass | State |
| 2020-02-26 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2020-02-20 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2020-02-20 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2020-01-21 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
Dates as filed by the agency that recorded the stack test. Figures from EPA’s ICIS-AIR download.