EPA Air · stack tests by county and year
Air-emissions stack tests in Monroe County, Wisconsin, 2026
- 20Stack tests
A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row below is one stack test recorded against a source in Monroe County, Wisconsin during 2026. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Monroe County facility page.
Monroe County, Wisconsin, 2026
Air-emissions stack tests in Monroe County, other years
Air-emissions stack tests recorded in Monroe County, Wisconsin, 2026
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2026-07-21 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2026-07-13 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2026-07-13 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2026-07-08 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2026-07-06 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2026-07-06 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2026-07-06 | WE ENERGIES - VALLEY POWER PLANT | Pass | State |
| 2026-06-22 | WMWI - METRO RECYCLING & DISPOSAL | Pass | State |
| 2026-06-22 | WMWI - METRO RECYCLING & DISPOSAL | Pass | State |
| 2026-06-18 | MOLSON COORS USA LLC | Pass | State |
| 2026-06-02 | PPG INDUSTRIES — high-priority violation on file | Pass | State |
| 2026-05-27 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2026-04-27 | MMSD-JONES ISLAND WATER RECLAMATION FACILITY | Pass | State |
| 2026-04-13 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2026-04-13 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2026-04-13 | WE ENERGIES - VALLEY POWER PLANT | Pass | State |
| 2026-03-14 | U.S. ENERGY MILWAUKEE JONES ISLAND TERMINAL | Pass | State |
| 2026-02-11 | BRADY WORLDWIDE - FLORIST AVE PLT | Pass | State |
| 2026-01-19 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2026-01-19 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
Dates as filed by the agency that recorded the stack test. Figures from EPA’s ICIS-AIR download.
What this page shows
This page covers Clean Air Act facilities in the EPA air register with stack tests in Monroe, WI, in 2026. It lists 20 stack tests recorded in 2026.