A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row below is one stack test recorded against a source in Monroe County, Wisconsin during 2021. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Monroe County facility page.
Monroe County, Wisconsin, 2021
Air-emissions stack tests in Monroe County, other years
Air-emissions stack tests recorded in Monroe County, Wisconsin, 2021
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2021-12-15 | MOLSON COORS USA LLC | Pass | State |
| 2021-12-08 | THE NEWARK GROUP, INC. | Pass | State |
| 2021-10-28 | APPLETON GRP LLC — high-priority violation on file | Pass | State |
| 2021-09-22 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2021-09-21 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2021-09-09 | GREDE LLC - LIBERTY — high-priority violation on file | Pass | State |
| 2021-08-19 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2021-08-09 | WE ENERGIES - VALLEY POWER PLANT | Pass | State |
| 2021-07-21 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2021-07-21 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2021-07-21 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2021-07-20 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2021-07-20 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2021-07-20 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2021-07-15 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2021-07-14 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2021-07-14 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2021-07-13 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2021-06-14 | SUEDPACK OAK CREEK CORP | Pass | State |
| 2021-06-01 | MMSD-JONES ISLAND WATER RECLAMATION FACILITY | Pass | State |
| 2021-05-25 | MOLSON COORS USA LLC | Pass | State |
| 2021-05-10 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2021-04-25 | U.S. ENERGY MILWAUKEE JONES ISLAND TERMINAL | Pass | State |
| 2021-04-20 | MMSD-JONES ISLAND WATER RECLAMATION FACILITY | Pass | State |
| 2021-03-23 | WMWI - METRO RECYCLING & DISPOSAL | Pass | State |
| 2021-03-23 | WMWI - METRO RECYCLING & DISPOSAL | Pass | State |
| 2021-03-17 | BRADY WORLDWIDE - FLORIST AVE PLT | Pass | State |
| 2021-03-04 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | N/A | State |
| 2021-03-04 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | N/A | State |
| 2021-02-04 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2021-02-02 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2021-02-01 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2021-01-28 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2021-01-28 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2021-01-19 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2021-01-19 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Pass | State |
| 2021-01-12 | WE ENERGIES-OAK CREEK POWER PLANT — high-priority violation on file | Fail | State |